Select Committee on Public Accounts Forty-Sixth Report


Conclusions and recommendations


1.  The Department's Review of 20 of its largest projects cut their forecast costs by £781 million, but £448 million of this expenditure did not result in a saving to Department as a whole as it was transferred to other budgets. The Department will have to forgo other—so far unspecified—activities which might otherwise have been financed from those budgets. As an integral part of any further reviews, the Department should quantify the opportunity cost to the recipient's budget of having to absorb such transfers of expenditure, and the impact on their continued ability to plan and deliver the capabilities originally expected from those budgets.

2.  The Department has made investment decisions based upon inaccurate forecasts. Such decisions should be contingent on the outcome of an expert independent assessor's examination of the technical, financial and commercial maturity of the major projects and the likelihood they will deliver military benefits anticipated, similar to the examination conducted on the Future (Aircraft) Carrier.

3.  The cost increases and delays on the Astute Class submarine project in part stem from failure to preserve the submarine supply chain. The Defence Industrial Strategy, introduced in December 2005, provides a framework against which to make judgements on the sustainment of critical industrial capabilities. The Department should routinely quantify the cost implications and operational benefits of sustaining critical defence capabilities for individual projects. The Department will also need to apply the learning from the Astute project in planning for a successor to the nuclear deterrent.

4.  The Government has announced plans to embark on a major project to build a successor to the nuclear deterrent, which is estimated to cost in the region of £19 billion and take up to 18 years. Many of the cost overruns on older projects have been due to over-ambition in the original design and a failure to properly understand and budget for costs. The Department will need to apply the learning from Astute to this new project, including how to realistically plan and use Computer-Aided Design; keeping to the required timescale in the design and build cycle; and using new methods of construction pioneered in the United States of America.

5.  Key staff are neither held to account for a project's failure, nor rewarded for its success. The Department will now promote staff in post to retain vital skills, and continuity at key stages of projects, or move staff on in case of failure. The Department should document its approach and how it will measure success, so as to evaluate the expected benefits against the outcomes; and it should share its learning with other government departments.

6.  The Department has not received a share of the gains on the restructuring of the Skynet 5 satellite communications deal. It is also doubtful whether the gain achieved by the contractor, Paradigm, is balanced by the increased risk Paradigm was taking on under the restructured deal. Rather than relying on theoretical models and contractor assurance, the Department should determine the share of the gains to which it is entitled.

7.  The Department has not always sufficiently understood the capabilities of its key suppliers, to act as an intelligent customer. The Department should build on its Key Supplier Management initiative and work with suppliers to identify areas where more joint training and skills development would help develop a stronger shared ethos and mutual understanding.


 