Select Committee on Public Accounts Forty-Sixth Report


2  Performance of individual projects

7. The United Kingdom spends around £6.5 billion annually on the acquisition of some 50 major equipment projects. Often these projects have been delayed and over budget. In 2005-06, 19 of the major equipment projects (excluding the Typhoon aircraft) were forecast to cost £27 billion, some 11% over approved budget, and had been delayed by a further 33 months.7[7]

8. The trend in the Department's performance against its Key User Requirements is worsening, with only 17 projects expected to achieve all requirements, one fewer than in 2004-05. The Department believes that this is because project teams are taking a deeper look at whether or not there is a risk that any of the requirements will not be delivered and highlighting areas where they cannot guarantee delivery, so that appropriate mitigating action can be taken.8[8]

9. The Department had improved its performance against planned in-service dates with in-year additional delays reduced from 144 months four years ago, down to 33 months for 2005-06. There was also greater consistency across the programme with 14 projects reporting no new delays. If equipment can be accepted into service on time, cost overruns will also be limited. Of the 36 new projects of £20 million or more in value that the Department has approved since 2003, 34 are forecast at or under budget, 33 are expected to beat their predicted in-service date and 35 should deliver all key user requirements. On the so-called "toxic legacy" projects,9[9] however, it is still struggling to manage the consequences of inadequate contractual arrangements put in place some years ago.10[10]

10. It is too early to say whether the Department's confidence in its improved performance is warranted. Historically delays and cost increases have worsened in the later years. The cost of the Astute Class submarine project has continued to spiral and is now £1 billion over the original budget. The Department now acknowledges that the original deal was flawed. Only one boat is firmly priced whilst the design and construction costs for three submarines were calculated without having first appreciated the requirements for delivery and the likely timescales. The Department negotiated a new arrangement for a target cost incentive fee for designing and building the first submarine, but there was still uncertainty as to whether the arrangements the Department had put in place would be deliverable.11[11] HMS Astute is on schedule to enter service late in 2008, but the need to keep the current boats in service longer than anticipated creates an additional pressure on the budget.12[12]

11. The Department believed that its overall performance on acquisition is favourable when compared to its international counterparts. In 2005 HVR Consulting Services Limited scrutinised cost and time estimates for 22 major programmes, using information from the Major Projects Report 2004, and compared them to outcomes in other nations and historic Departmental projects. Thirteen of the current projects scrutinised came in at or below the cost forecasts produced by the model, and 21 projects were expected to deliver ahead of that modelled from analysis of comparable programmes.13[13] Figure 3 below, for example, shows the cost history of nuclear attack submarine construction in the United Kingdom and the United States of America. The data (from public domain sources in 2005) is normalised to 'cost per ton' because submarines of the United States of America are generally bigger than those used by the Royal Navy. It shows that, despite large cost overruns, the Astute Class submarine is below the trend line.14[14]

Figure 3: Historic cost comparisons for nuclear attack submarines


Source: Ministry of Defence analysis based on Family of Advanced Cost Estimating Tools model used by HVR Consulting Services Limited

12. The Department has reconsidered how it will design and build future submarines in order to keep building costs affordable. Lessons learned from the Astute project include how to realistically plan and use Computer-Aided Design; keeping to the required timescale in the design and build cycle to maintain sufficient skill in the workforce; and using new methods of construction which were pioneered in the United States of America. Should the government decide to invest in a successor to the nuclear deterrent, these lessons will need to feed into the project. Building a successor is estimated to cost in the region of £19 billion and take up to 18 years, and will involve the management of significant technical and commercial risks. The Director-General Nuclear is currently working with the defence industry to understand the technical issues and identify ways to control future costs.15[15]

13. The original Skynet 5 PFI deal, signed in 2003, relied on the contractor obtaining insurance to mitigate risks to the satellites during the launch phase and while in orbit. Within six months of signing the deal the contractor proposed to restructure the contract to overcome insufficient capacity in the space insurance market. Restructuring extended the contract for two years at a cost of £822 million, although there is no operational need for the additional years' service. The Department would have been entitled to a 50% share of any gains from a 'refinancing only' deal if the investors' returns exceeded a predicted rate of return of 16.45%. During the negotiations, however, the Department's financial advisers calculated the theoretical gain as a result of refinancing, and based on their assumptions the Department would not have been due to receive any share of the gain. The Department has no ability to check whether the 16.45% threshold was breached and has had to rely on the contractor's assurance that it was not owed a share of the gains. Whilst the Department believes the gain achieved by the contractor, Paradigm, balances out the increased risk the contractor was taking on, Paradigm also has two additional years of the annual tariff for the PFI service and the potential to generate third party revenue from the excess capacity.16[16]


7 7   C&AG's Report, paras 2, 3; Qq 76-77, 85 Back

8 8   C&AG's Report, para 1.22; Qq 12, 25 Back

9 9   Astute, Nimrod MRA4 aircraft and Type 45 Destroyer Back

1 10  0 Qq 82-83, 124 Back

1 11  1 Committee of Public Accounts, Forty-third Report of Session 2003-04, Ministry of Defence: Major Projects Report 2005, HC 889; Qq 8-9, 97 Back

1 12  2 Qq 9, 95 Back

1 13  3 Qq 73, 79 Back

1 14  4 Ev 25 Back

1 15  5 Qq 11, 83, 129-130; Ev 24 Back

1 16  6 C&AG's Report, Appendix 3, paras 17, 19; Ev 22 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 11 September 2007