2 The termination of the PFI Contract
11. Construction work on site began in July 1998.[31]
Deficiencies in JLC Ltd's designs were identified by the Department's
technical advisor, HDR, and the project's Independent Certifier
in early 1999.[32] As
construction continued numerous problems arose, including significant
problems with the performance of JLC Ltd's designs, which resulted
in delays in the completion of all construction phases. These
delays ranged from six months up to nearly four years, and altogether
the project has been delayed by five to six years.[33]
12. The Department offered advice to Laser on solving
the design problems, including advice from the Department's engineering
advisers, HDR.[34] The
Department was however concerned not to take back from Laser the
design risk that had been transferred to it under the PFI contract.
The Department therefore felt unable to step in and insist on
design changes for fear that by doing so it would accept some
of the design risk, and decided to leave the problems with Laser.[35]
13. The Department considered terminating the contract
on three occasions between 2001 and 2003.[36]
On the first occasion, in 2001, it considered doing so on the
basis of Laser's performance. On the second, towards the end of
the same year, it considered doing so because Laser had signed
an agreement with John Laing plc relaxing the performance requirements
in the construction contract without the Department's consent;
and on the third because of Laser's late delivery.[37]
On each occasion the Department received firm legal advice from
experts in construction law that it would be risky to initiate
termination, particularly while Laser was still solvent and willing
to continue, because it might itself be liable for damages.[38]
The Department was also concerned at the potential difficulty
of finding a replacement contractor, and the likelihood that the
project's evident problems would have meant that it could only
have done so by paying a much higher price.[39]
14. Treasury guidance recommends the provision in
PFI projects of step-in rights for lenders. These rights entitle
the lenders in defined circumstances to take control of a project
and are intended to provide an opportunity for the lenders to
revive the project, thereby avoiding the disruption of a termination.[40]
However, Laser's lenders chose not to exercise their rights to
step-in to the project because they did not want to assume responsibility
for solving the problems with the design.[41]
15. By mid-2004 Laser had exhausted the funds available
to it to complete the building and on 7 July 2004 it proposed
to the Department that the PFI contract should either be revised
and re financed, or terminated.[42]
The Department decided on termination, but sought to achieve it
by negotiation, which it considered would probably get a better
and quicker result than a formal termination for contractor default.[43]
16. The agreement between Laser and the Department
provided for the appointment of an Independent Certifier to determine
the completion of each phase of the building, paid for jointly
by Laser and the Department.[44]
By 5 July 2004, the Independent Certifier had signed off completion
of the last of the building modules.[45]
The Department considered that some of the construction phases
had been wrongly certified and referred the matter to adjudication.[46]
The adjudicator concluded that the Department did not have beneficial
use of the space at issue, and decided in favour of the Department.[47]
17. The Department and Laser formally terminated
the contract in December 2004.[48]
The Department paid Laser £75 million for its interest in
the building and assumed responsibility for its completion.[49]
The Department's opening position in negotiating the termination
sum was informed by the contractual provisions governing contractor
default. Under these provisions the termination sum was the lesser
of the lender's liabilities, initially assessed at £93 million,
and Laser's construction costs, adjusted for the projected cost
to the Department of completing the project and any unpaid damages
owed by the company, initially assessed at £54 million.[50]
As negotiations progressed, the Department estimated that a more
realistic assessment would be between £86 million and £73
million; the agreed termination sum was near the lower boundary
of this range.[51]
18. Over three years passed from when the Department
first considered termination of the contract to the actual termination,
but a lot of work was completed during this period.[52]
And if had it pushed for termination of the contract in 2001,
it would not have been in as good a position as had been achieved,
with a nearly completed building.[53]
It was confident that the remaining construction work could be
completed within a budget of £18 million and that the scientific
modules would be 98 per cent ready for occupancy by the end of
March 2007.[54] With
completion, the Department's investment in the new facilities
was likely to total £140 million (2005 prices), £10
million more than the total of Laser's budgeted construction cost
of £113 million (2005 prices) and the Department's procurement
and other budgeted costs of £17 million (2005 prices).[55]
Laser, its owners and its contractors reported losses totalling
over £100 million.[56]
31 C&AG's Report, Figure 3 Back
32
C&AG's Report, para 2.9 Back
33
C&AG's Report, paras 1.10, 1.11; Figures 5, 6; Q 23 Back
34
Qq 35-36 Back
35
Q 8 Back
36
Q 8, C&AG's Report, para 1.20 Back
37
Q 8; C&AG's Report, para 1.20 Back
38
Qq 8, 76, 103; C&AG's Report, paras 3.18-3.21 Back
39
Qq 8, 76, 104-106 Back
40
HM Treasury, Standardisation of PFI Contracts Version 3,
April 2004, para 31.1.3 Back
41
C&AG's Report, para 1.27; Qq 100-101 Back
42
C&AG's Report, paras 1.22-1.24, 1.28-1.29, Figure 8 Back
43
Q 78 Back
44
C&AG's Report, para 1.9; Q 73 Back
45
C&AG's Report, Figure 3 Back
46
Qq 69, 75, 123 Back
47
Q 75 Back
48
C&AG's Report, Figure 3 Back
49
C&AG's Report, para 1.4 Back
50
Qq 10, 77; C&AG's Report, paras 4.3 Back
51
Q 10 Back
52
Q 8 Back
53
Q 8, 76 Back
54
Qq 16-17 Back
55
C&AG's Report, para 4.15; Q 22 Back
56
C&AG's Report, Figure 2 Back
|