Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 120-139)

DEPARTMENT OF HEALTH, PROFESSOR PETER HUTTON AND DR ANTHONY NOWLAN

26 JUNE 2006

  Q120  Kitty Ussher: In terms of spreading best practice on procurement, how will that be done across Whitehall? Are you working with the OGC and Gershon processes?

  Mr Granger: We made available to the OGC, when they were producing new guidance to replace the Treasury task force on standard terms and conditions for PFI contracts, all our contracts and indeed some of the lawyers we had worked with participated in that and our head of procurement, Patricia Kelsey, participated as well. They took on board our terms and conditions and negotiation approaches, some of which are set out in this Report, and have made those available to other departments.

  Q121  Dr Pugh: Can we test this hypothesis that robust procurement saves the day? May I start with the big numbers first? In the NAO Report it said that £6.8 billion was saved from the initial bids and £4.5 billion through central procurement. These are very big figures and I cannot help speculating on how you arrive at them. Do you simply take up the gross bids and add them all up and put them down as savings or does a more subtle process take place?

  Mr Granger: Those numbers are not my numbers; those numbers are numbers which owe their provenance to Ovum, who are respected independent industry analysts who looked at the cost of comparable systems when procured on a trust-by-trust basis.

  Q122  Dr Pugh: You did say before that as part of the procurement process you looked at the delivery capacity of whatever suppliers came forward. EDS were replaced eventually by Cable and Wireless on NHSmail. Why was that? What happened there? What were they paid for their efforts?

  Mr Granger: I am afraid I do not have the exact figure with me that they were paid to termination of the contract. I shall let you have a note on that.[9] The reason the contract with EDS was terminated was because, in our opinion, the service which was being delivered was not sufficiently reliable and the new functionality we required was significantly delayed.

  Q123 Dr Pugh: So they did not have the delivery capacity.

  Mr Granger: I did not let the contract with EDS. The contract with EDS was let by the organisation of which Dr Nowlan was a director.

  Q124  Dr Pugh: One way of reducing procurement costs is obviously to shift some of the cost to the local NHS. The figure for additional income is £3.4 billion but presumably this excludes what they would normally spend on IT prior to that. I understand there are savings in the process for introducing the new schemes and so on, but that is not all they are going to spend on IT, is it, by any stretch of the imagination?

  Mr Granger: That is correct. From our business cases it looks as though that number might be a bit high as we get into large-scale deployment. That number was the total estimated cost three years ago in the Treasury business cases around what it would cost the NHS to take on board these systems, not their net cost, and it looks as though the actual cost is going to be significantly lower.

  Q125  Dr Pugh: Significantly more?

  Mr Granger: No, significantly lower.

  Q126  Dr Pugh: Significantly lower?

  Mr Granger: Yes.

  Q127  Dr Pugh: One feature which has been commented on is that some of the contracts appear to be let on the basis that the NHS trusts themselves, willingly or not, will provide IT specialism. Is that the case?

  Mr Granger: It is the case that it is good practice, as set out in many reports from this Committee and indeed significant commentary this afternoon, that significant user involvement is key to the successful delivery of IT programmes. The strategic health authority is committed to provide a number of clinicians primarily rather than IT staff.

  Q128  Dr Pugh: You said earlier—I heard the very words—that there is a known shortage of capacity in NHS IT. Against that background was it wise to construct contracts like that?

  Mr Granger: I am sorry but I was talking about suppliers' capacity. There is a shortage of supplier capacity, which is why capacity has come from other jurisdictions.

  Q129  Dr Pugh: You had no doubts about the trusts' capacity.

  Mr Granger: We left the trusts' capacity intact, rather than having an outsourcing arrangement under TUPE and effectively asset-stripping the trusts out to the supplier communities. We did not repeat a mistake which has been made with some traditional outsourcing arrangements. We recognised that it was essential to have sufficient end-user input to the design and deployment as well. We undertook obligations to make that available as a fair bargain.

  Q130  Dr Pugh: The delays have to some extent cost the trusts money, have they not, because some of them have had to go ahead with renewing their own patient administration systems and so on, as well as making them compliant with the Spine? Can you quantify the cost of that or have you been able to quantify the cost of that?

  Mr Granger: A number of trusts have had to extend their existing systems and they do therefore have cost. When the new systems come in, after the implementation of them, they do not have to pay for that system any more. I do not have an exact number, but in many cases we are providing financial support to trusts for upgrading their existing systems and indeed some of the £80 million support around Choose and Book implementation is to upgrade their existing systems.[10]

  Q131 Dr Pugh: I understand that some of the GPs are very fond of their own kit and software and that you tried to make the system more compliant with that. There is going to be a significant write-off cost, is there not, for stuff which is not Spine compliant at the end of the day? Have you quantified that?

  Mr Granger: Most of it is life expired. If you look at its position on balance sheets it is either leased or life expired. One of the difficulties we have is that a trust such as the Nuffield, which has been the source of much inquiry, had only one month left in which the hospital could operate with its existing system. The same was true 30 miles up the road with an installation you may not have heard of, University Hospital Birmingham, where there were one to two months of life left in the hardware they were using before the hospital would start to run into problems operating; obviously a much larger hospital in Birmingham than the Nuffield. There is limited investment in the existing installations and in many cases—in fact around 50 cases in terms of application software—their systems have been tested to be partially upgraded and become Spinecompliant. We are making best use of existing investment wherever we can as well.

  Q132  Dr Pugh: So you have a fairly shrewd idea of the additional hardware costs for most trusts.

  Mr Granger: I do not know exactly what each trust is spending on additional hardware because that cost is an ongoing expenditure and they are standard arrangements. Where we have gone through full-scale upgrades we now have those numbers and can supply them to you.

  Q133  Dr Pugh: One thing the NAO say about you is that you exerted downward pressure on sub-contractors which are used by many suppliers, Microsoft was just mentioned and in fact is mentioned in the NAO Report. I know you have met Mr Gates and Mr Baumer. How much does the NHS now spend on Microsoft licences?

  Mr Granger: I think you will find the number accurately reflected in this Report. From memory, I think it is something of the order of £50 million a year.

  Q134  Dr Pugh: I think it was £53 million in 2003.

  Mr Granger: I guarantee we have been spending less per licence than anybody else on the planet.

  Q135  Dr Pugh: Is that figure likely to remain somewhat similar.

  Mr Granger: Yes, it is. It is important to note that we have a three-year mark and a six-year mark and the opportunity to step out of that contract if we want to move to open source software if that became mature and more cost effective.

  Q136  Dr Pugh: You do not accept kit, software, hardware or anything unless it is working and somebody has to decide that it is working. Who makes the decision? I certainly do know general practitioners who feel that is satisfactory. I know others who feel it is not. How is the general verdict arrived at that a piece of equipment, a piece of software is working and now has to be paid for?

  Mr Granger: We have a very clear acceptance process. It is agreed with the suppliers during the contracting phase that they sign up to that it goes through this acceptance process. In most cases they are paid, once it has been used, generally 45 days after commencement by users. It has to be in use and accepted by the end-users as well as going through a technical acceptance process.

  Q137  Dr Pugh: May I ask you about an article in the Evening Standard which suggested that you had said to suppliers that if they complained about the system they would be struck off the bidding list, that you had implied as much. You have not done that presumably.

  Mr Granger: Not at all. I think you will find more reliable evidence than the Evening Standard.

  Q138  Dr Pugh: I am just giving you the opportunity to put it on the record.

  Mr Granger: We ran a procurement process which the NAO refer to as bringing the high standards of Civil Service procurements in terms of the probity of the process and we applied those standards. Our suppliers are in many cases somewhat reticent to discuss things but the reticence is for the most part theirs rather than mine.

  Q139  Dr Pugh: You recruited some medical advisers at some point by advertisement to advise you on the project. Did you make them sign a confidentiality agreement and if so why?

  Mr Granger: The people working on the programme have signed arrangements which are similar to those signed by civil servants. For the most part they are being paid for out of funds which flowed through the Department of Health so I see no reason not to do that. We also caused a degree of consternation in our arrangements under those job advertisements that people declared their conflicts of interest. That was quite a quaint and novel arrangement which caused consternation amongst a number of the specialist IT interest groups.


9   Ev 43 Back

10   Ev 43 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 17 April 2007