Letter from CSC Computer Sciences Ltd
Further to your request earlier today, I am
pleased to provide the following information regarding the planned
PAS go-live dates for Acute NHS hospitals scheduled for the next
four months up to the end of October 2006.
Trust |
Care Setting |
Go-live Date |
Functionality |
Robert Jones and Agnes Hunt |
Acute |
17 July 2006 |
PAS Theatres on 12 March 2007 |
North Cheshire |
Acute |
28 August 2006 |
PAS Theatres on 20 November Maternity on 27 November |
South Warwickshire |
Acute |
25 September 2006 |
PAS, A&E |
East Lancashire |
Acute |
9 October 2006 |
PAS |
South Manchester University Hospital |
Acute |
9 October 2006 |
PAS Theatres on 1 January 2007 |
Southport and Ormskirk |
Acute |
23 October 2006 |
PAS Theatres |
These projects have either already started, or the Project
Initiation Documents have been signed off. In all cases, the CSC
and CfH project teams are working towards achieving these dates.
To date CSC has completed 46 Deployments across 50 PCTs,
nine Acutes and four Mental Health Trusts. A total of 28,176 End
User Accounts have been enabled across 764 locations.
23 June 2006
|