Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 80-88)

MINISTRY OF DEFENCE & DEFENCE ESTATES

MONDAY 14 MAY 2007

  Q80  Mr Williams: How long have those provisions been in place?

  Sir Ian Andrews: The dates are in the Report.

  Mr Williams: I have not read every bit of it.

  Sir Ian Andrews: We announced the initial programme of regional prime contracts back in 2001, and we rolled out the fifth on target in 2005. We did the same with our water and waste water contractors, and they are quite properly even more focused on such issues than we were under the previous management arrangements, which from my perspective were frankly wholly inadequate. I have much greater confidence in the arrangements that we have in place now, even with the number of staff that we have. We have identified the needs that are to be met and, as Admiral Laurence was saying, we are driving that as hard as we possibly can. I dispute your statement that it is something to which we do not attach priority, particularly as far as health and safety are concerned.

  Q81  Mr Williams: So does that mean that the information that we are working on here will soon be outdated, but that with only 900 upgrades a year, it will take more than 20 years to upgrade? Are we going to see an improvement in that?

  Sir Ian Andrews: Sorry, but I do not think that that is related to the issue of numbers of safety staff.

  Q82  Mr Alan Williams: You are being specific about the safety side? Okay.

  I shall switch back then for one moment, because a note has just been passed to me. I referred to the July 2007 date for the delivery of guidance, and although I missed this point, I am told that you, Mr Jeffrey, did not recognise the date. The note points out that the date is at the end of paragraph 2.23 on page 26, which says, "The Department intends to produce detailed guidance on responsibilities by July 2007." Earlier in the paragraph, the Report says that the expected date on which the site people will have their work prepared is April 2007.

  Bill Jeffrey: I do apologise, Mr Williams; I had overlooked that. The fact remains, though, that the plan is to introduce the estate management plans themselves by September this year.

  Mr Alan Williams: Thank you very much.

  Chairman: Mr Mitchell has a supplementary.

  Q83  Mr Mitchell: When the contract was let to Modern Housing Solutions, you had to cough up an additional £20 million, and one of the reasons why was a greater than anticipated backlog of work from previous contracts. Does that not indicate that the Department is not supervising its contractors adequately, if it does not know about the backlog of work?

  Bill Jeffrey: It certainly indicates that before the housing plan contract was entered into, the system was much more dispersed. There had been more than 50 individual contracts, and the fact is that the contractor to whom we awarded the overall contract inherited more outstanding problems from the predecessor contractors than they or we expected. They started—it is fair to say—with less than effective information management themselves, but it is something that, as the Report brings out, we have turned around substantially in the past nine months.

  Q84  Mr Mitchell: So, essentially, it was a problem of dispersal rather than inadequate supervision.

  Bill Jeffrey: You could argue that it makes the case for the approach that we have taken, having a single contract for the whole housing estate in England and Wales, because there is better information underpinning it. We now have a better sense with our contractor of the demand levels. To take some figures that appear in the Report, the help desk, which was a problem with the contractor, now responds to almost all calls within 30 seconds, there are better call-out times, and the customer satisfaction ratings from those at the other end of the service is 94% or better. We were not in that position nine months ago.

  Q85  Mr Mitchell: I saw that and did not comment, because it does not provide an open nerve to jump on.

  I have one final question. You do not know the total value of the estate. Is that because you do not know what is going on, or because you would rather that the total value were kept quiet? If it is known publicly, the Government will want to start to getting rid of some of it.

  Bill Jeffrey: The total value of the estate.

  Mr Mitchell: Yes.

  Bill Jeffrey: We can estimate it, and indeed, an estimate appears in the Report. As was brought out in our earlier exchanges, there is a difference between book value and potential market value.

  Mr Mitchell: Okay. Ta.

  Q86  Chairman: If you look at paragraph 2.31 on page 28, you will see that there is a scheme to reduce energy usage at RAF Kinloss. It resulted in annual savings of £340,000, which is very impressive, but why has it not been replicated in other parts of the defence estate?

  Bill Jeffrey: The short point is that something like that saving is being replicated, but I look to Ian Andrews, who leads on sustainability and energy issues for us.

  Sir Ian Andrews: The Kinloss project was a pilot project with the Carbon Trust, with which we entered into a strategic relationship three years ago. Since the Kinloss example, which the Report identified, we have increased the total number of projects across the estate to 10, identifying some £2 million of potential savings for an up-front investment of about £2.3 million—much of that in-year. We are now rolling out a similar process across another 15 sites, and we intend to complete the process for all the high-energy-using sites in due course. It is a very good example of precisely the sort of thing that we can do by involving people who understand the relationship between energy generation and what is discharged into the atmosphere. By coming in to look at that, professional people can help us deliver a more sustainable estate over time.

  Bill Jeffrey: The other point is that, right across the Department, we now have 15% energy efficiency targets built into our budgets, so there is an incentive for people to do exactly this sort of thing.

  Q87  Chairman: Lastly, Vice Admiral, Mr Dunne earlier asked about rats in barracks. I do not know whether there are still rats in Royal Navy ships. Are there? That may be a rather facetious question. Presumably, during the 30 years that you have been in the Navy, accommodation on board ships has transformed, but what do ratings say to you when they talk about how accommodation on board a ship compares with the accommodation ashore?

  Vice Admiral Tim Laurence: It is right that accommodation in modern ships is significantly superior to how it was when I joined the Navy 34 years ago. But what is interesting is that the accommodation that we are building ashore in Portsmouth—I was there last week at the opening of a new block—and in Faslane, for example, is now hugely superior to what we had 20 or 30 years ago. Standards across the piece are increasing. Of course, when they are at sea, sailors accept that life there is uncomfortable. You have to accept that, so they put up with it, to be honest.

  Q88  Chairman: But they do not moan to your face about the accommodation ashore. Or do they?

  Vice Admiral Tim Laurence: Sailors will always moan, given half an opportunity.

  Chairman: Yes, that is my experience.

  Vice Admiral Tim Laurence: When they are living in substandard and old accommodation, we certainly hear about it.

  Chairman: It has been a very interesting hearing, gentlemen. Thank you very much for your attendance. We are very grateful.





 