Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 280-299)

DEPARTMENT FOR ENVIRONMENT, FOOD & RURAL AFFAIRS AND RURAL PAYMENTS AGENCY

MONDAY 9 JULY 2007

  Q280  Mr Davidson: I understand that. So many of the changes that were introduced, all of which are expensive as we all know to our cost, came about partly as a result of stakeholder influence and stakeholder observations being acceded to by Ministers.

  Johnston McNeill: I think this matter was discussed in some detail in the evidence given by the NFU to the Environment, Food and Rural Affairs Select Committee, for example. It is not something I was close to personally, but I have scanned it and it is obvious that there were a lot of discussions about what this should really look like in detail.

  Q281  Mr Davidson: The NFU helped to dig the hole in the first place, and that is helpful to know.

  On Accenture, we have heard repeatedly how IT contractors are grossly over-optimistic—they are also over-expensive, but that is a different matter. To what extent does that over-optimism apply here? Can we, with hindsight, look back and say that Accenture should not have said to you that this can be done, because it was obvious that it could not be done, or were the changes that were subsequently introduced so complex that no reasonable IT contractor could have been expected to cope with them?

  Johnston McNeill: I think Accenture would argue with some force, as it has done in previous discussions in another Committee, that the system was delivered and worked. The very fact that we were able to process and make payments in February and March tends to support that.

  Q282  Mr Davidson: As I understand it, the system worked but payments were made at a rate of 10 a week when 1,000 a week were needed. The system worked, but the difference was like that between buying a Ferrari or a Model T Ford. They both move along the road, but it depends on how fast you want to move, how much you want to carry and so on. I do not want to say that Accenture is the Model T Ford of such situations, but is that not a reasonable parallel to draw?

  Johnston McNeill: I understand your point. We had some significant issues with system performance in terms of how many claims it could get through, its availability—it had to be brought down at night for work to be done and for modifications to be made—and so on. We had numerous discussions with Accenture about improving that. However, in terms of functionality, the system worked.

  Q283  Mr Davidson: This system worked, but only if you did not use it to the necessary capacity. Then it was perfect.

  Johnston McNeill: The same system has been used for 2006 claims, and I understand that the bulk of claims—96.14% or close to it—were dealt with by the end of June in line with EU requirements, so the system has worked well this year. It worked for us last year. I have no doubt—I agree with you—that the system required tidying up and needed to be less clunky. I accept that it was unreliable in some respects, but it worked and it continues to be developed.

  Q284  Mr Davidson: So Accenture deserves some of the credit for what happened.

  The notes state that when Mrs. Ghosh was with us, she described: "a conspiracy of optimism" in the Agency. Were you over-optimistic? Was her comment reasonable?

  Johnston McNeill: No, I do not think so, nor was the comment in the NAO Report. I have asked repeatedly to see the optimistic Reports that I am supposed to have sent to Lord Bach.

  What does not sit comfortably with me, Chairman, is when you tell me that we were over-optimistic, and on page 43 of the very same NAO Report you see a consistent line of red lights. That is our assessment in the RPA to the Executive Review Group in DEFRA of what we thought progress looked like. As you see, there is no shortage of red lights. It is a peculiar sort of optimism from where I am sitting.

  You have had a Permanent Secretary before the Environment, Food and Rural Affairs Committee—Sir Brian Bender—who has openly discussed 40% confidence levels in the Agency, and you say that we were over-optimistic. I have asked repeatedly to see the papers. The papers that went to Lord Bach came jointly from Andy Lebrecht and me from CAPRI, and Brian Bender chaired the Executive Review Group, which also Reported to Ministers. I am not aware that we were over-optimistic anywhere. We were frank, forthright and explained the difficulties that we regularly faced.

  Q285  Mr Davidson: I understand that. That is why I am confused. How could we have the situation that you told us about, and which was described in the NAO Report, yet Mrs Ghosh can still refer to: "a conspiracy of optimism"? That obviously implies a lack of communication and understanding somewhere. You are in front of us, so I am asking you. How do you think that could have arisen? Given that you are saying that Mrs Ghosh's statement was not reasonable, how could she have got into a position where she was able to say that? She obviously misunderstood.

  Johnston McNeill: Perhaps it was more suitable than reasonable.

  Q286  Mr Davidson: That is a reasonable response.

  In terms of feedback, I cannot quite understand the point about how things just seem to have gone wrong apparently so suddenly at the end. Can you just clarify whether you think, with hindsight, that any particular improvements in the system of feeding back ought to have been made that would have allowed the Secretary of State or those in the Department who were making the decisions to be aware earlier; or were they also suffering from a conspiracy of optimism?

  Johnston McNeill: No. I think the Report makes a fair observation, which I accept and which we had already come to realise as we got closer to the final systems development. In moving to a task-based approach to working we did not have a sophisticated enough understanding of the relationship between tasks outstanding and actual clearance. The work that is now being done, which in fact was commissioned with Accenture some time ago, is on better understanding; if you phone up about a claim, we want to know how many tasks relate to your claim. We also need to have the facility of getting those tasks attached to your claim.

  To be perfectly frank, that is something of a step backward from the original concept from PricewaterhouseCoopers, which was almost to deskill the work and have tasks so that you could group the task in various categories, and issue desk instructions to staff who, with minimum training, could address those particular issues quickly and clear them off and hence get the claims through. But there is a need—and it is well recognised now—to move towards a better understanding of the relationship between those tasks and individual claims. If we had had that, we would have been able to say, "There are 20,000 claims here which have only two tasks each. Now, if we could isolate those tasks we could clear 40,000 tasks and pay 20,000 claims." We did not have that facility, and that was an error. I accept that.

  Q287  Mr Davidson: In terms of that error, would it have been reasonable for PricewaterhouseCoopers to have understood that situation before giving its advice on the breakdown of tasks?

  Johnston McNeill: That side of things was one of the casualties that resulted when we were starting to de-scope the work that Accenture delivered. Accenture's line was quite straight: "If you want this delivered and you want payments in February, we cannot do all this." Certain parts of the work and certain parts of the scope, would to have to be removed. While the sophisticated management and information system was all very well, the fact was that it was Rolls-Royce system; it was going to take a lot of work to build. It was going to have a serious impact and so parts of it, I am afraid, had to be sacrificed. On reflection, as I have said before, that was an error.

  Q288  Mr Davidson: Did they tell you that it could not be done after they had got the money for it?

  Johnston McNeill: No. The arrangement, as set out in the case study Report that the OGC produced, is that Accenture was on a fixed-price contract and tightly managed—perhaps over-tightly in terms of the contractual arrangements.

  Q289  Mr Bacon: Mr McNeill, you said to the Select Committee on Environment, Food and Rural Affairs, in response to a question from Mr Duddridge, that "We never turned and said, `This is not do-able'. As I said, only at the fifty-ninth minute of the eleventh hour did we discover we had a problem which did not make it do-able."[2] I think you meant by that a problem that made it not do-able. You have said that it was somewhere between 20 February and 10 March when you became aware that it was not do-able. Can you pinpoint more precisely when?

  Q290  Mr Bacon: They were sticking? Clogging, in other words.

  Johnston McNeill: Staff were working twilight shifts and maximising use of the system. They would clear a certain category of task only to discover that the impact of that would not be realised until the next day, because the system has to run overnight to enable you to understand the impact on the remaining tasks, or how many tasks would result. It started to become apparent that, indeed, additional tasks were being generated.

  Q291  Mr Bacon: The doing of the tasks created more tasks: and indeed, paragraph 20 of the Report said that you were not able accurately to predict how many new tasks would be created by the performing of tasks. At what date, then, did it become clear to you, between 20 February and 10 March, that it was not do-able?

  Johnston McNeill: The payments went out on 20 February, and it became clear that it was not do-able when we started to monitor payment performance.

  Q292  Mr Bacon: After how many more days did you become aware that it was not do-able?

  Johnston McNeill: I do not recollect that detail, but it was a relatively small number of days, after which the Agency went back and began investigating in detail what was happening.

  Q293  Mr Bacon: Was it within a few days? Presumably, the situation became worse and worse?

  Johnston McNeill: The period between 20 February and 10 March is 18 days.

  Q294  Mr Bacon: I am not clear about why it took so long. You said to Mr David Taylor that the: "Department understood that this was a high risk, one of the top high risks" in Government. The Chairman of that Committee said that: "the scheme was high risk at the beginning, and it got riskier" and you answered that you "had a very sophisticated risk assessment model". Later, you said: "I have to say it was a particularly sophisticated approach to assessing risk."

  I am grateful that you pointed out the Gateway Reviews, which showed that there were 16 reds in a row between December 2004 and March 2006, but no double reds. The Committee has an arrangement with Sir John Bourn that when there is a double red, a Permanent Secretary will notify him, and he will then notify the Chairman of the Committee. There were no double reds, but 16 reds on the chart on page 43 of the Report.

  Johnston McNeill: That is not the OGC's Report of risk, but the Agency's. If you look, you will see that it states that it is the "Executive Group's risk matrix".

  Q295  Mr Bacon: I am sorry—you are absolutely right; the gateway review is on page 44. In fact, your assessment was still more bleak than the OGC's.

  Johnston McNeill: Absolutely.

  Q296  Mr Bacon: You said that you: "had a very sophisticated risk assessment model" and also that: "it was a particularly sophisticated approach to assessing risk". However, your assessments, made over two years, marked the risk with red after red, which was a bleaker assessment than that of the OGC's external Gateway Review. How was it that you began for the first time in late February or early March—very late in the day—to realise that it was not do-able?

  Johnston McNeill: The use of the traffic lights is confusing. Red does not mean stop. Red means that there are significant issues that need to be addressed, which means that one has to take mitigating action. For each red, we would have told the Executive Review Group what the business case, scope, schedule and resources issues were. We would go through that, and say what we needed to do about the red. We would address the issues for the month marked red, and move on.

  Q297  Mr Bacon: I am aware of the fact that red does not mean stop. In fact, that is one of the criticisms that has been levelled at the OGC process, because a double, triple or quadruple red does not mean stop. No one will ever say that a situation is sufficiently bad that the risks of continuing are greater than the risks of not continuing. You are not responsible for the fact that red after red does not mean stop. However, given that your own internal assessment was so consistently bleak for so long, one might have thought that you, as Accounting Officer, might have said: "This is too bleak and it is not good enough, so my recommendation is that we should not continue."

  Johnston McNeill: We are talking about the Executive Review Group. My point is that I was sitting with the Permanent Secretary, as the Chief Executive of the Agency and the senior person responsible for the programme, and saying that we had such a level of risk. I also said that if we were to deliver, we must do this and that, and sought his and the board's agreement to proceed.

  Q298  Mr Bacon: Having got agreement, would you then proceed?

  Johnston McNeill: We would push on and make changes.

  Q299  Mr Bacon: And then meet three months later and you would have another series of reds.

  Johnston McNeill: Absolutely, because the programme was high risk, and incredibly complex and difficult.


2   Environment, Food and Rural Affairs Select Committee, 15 January 2007, HC 107-II Johnston McNeill: Well, it became apparent that claims were moving through level 1 validation, which is a basic check on name, address and whatnot, and then level 2 validation was more complex. They were sticking in level 2 validation. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 6 September 2007