Select Committee on Public Accounts Fifty-Fifth Report


Conclusions and recommendations


1.  The Department and the Rural Payments Agency failed to implement the single payment scheme effectively. By the end of March 2006 it had paid farmers only 15% of the £1,515 million due, compared with its target of 96%, causing significant hardship. Taxpayers will have to pay additional implementation costs. In addition to a provision of £131 million included in the Department's accounts for 2005-06, the Department has had to secure a supplementary estimate of £305 million to meet the potential cost of disallowance of expenditure by the European Commission arising on the 2005 and 2006 single payment schemes and the previous schemes administered by the Agency.

2.  At the end of October 2006, some 3,000 cases for the 2005 scheme remained to be settled. The Agency subsequently managed to progress some of these outstanding payments, but 911 claimants had yet to receive anything and 2,184 claimants were awaiting a final 'top-up' payment by the time payments started to be made under the 2006 scheme on 1 December 2006. By May 2007 there were 24 claims, mostly probate cases, which remained unpaid, but the Agency was still reviewing the accuracy of a substantial number of claims already processed and making adjustments both for over and under payment.

3.  There are a number of lessons to be learned by the Agency, the Department and government bodies more widely.
     
  i.   The scheme is small, covering only some 116,000 claimants, but the Department made it unnecessarily complex by choosing to adopt the most demanding implementation options. It selected the 'dynamic hybrid' option for calculating entitlement, a one year implementation timescale, and no de minimis threshold for claims. Scheme parameters should not be chosen in isolation, but with due regard to the overall complexity and risk they will jointly present.
  ii.   Because the government sought to implement the single payment scheme at the same time as a wider business change initiative, the Agency shed too many of its experienced staff and their knowledge at a time when it needed them most. It then spent some £14.3 million on agency staff in 2005-06 to process 2005 single payment scheme claims. Before combining projects, their interdependency and the potential for compounding risk should be assessed as well as the risks of the individual projects.
  iii   Implementation of the project started before the specification of the single payment scheme was finalised. The aim was to meet the March 2006 payment deadline, but the result was that the Agency had to make assumptions on what the final regulations from the European Commission would contain. It subsequently had to make 23 substantial changes to its computer systems to reflect policy and regulatory revisions. The risk of having to make changes later in the development of the scheme could have been given more weight in determining the implementation timetable at the outset.
  iv   Processing capacity had not taken sufficient account of the number of maps and mapping changes that would need to be processed. The scheme was based on land area managed, and incentivised farmers and new claimants to register additional land. A proper estimate of the scale of the work should be made by appropriate modelling and testing.
  v   The Agency tested each key element of the IT scheme before introduction but testing in isolation did not fully simulate the real world environment and problems emerged later. Failure to test computer systems completely and adequately is a problem we have often seen with government IT projects. Time should be built in to test the IT systems as a whole as well as the individual components within it to obtain adequate assurance that components are fully compatible and deliver the required business process.
  vi   Without an individual or small team processing a whole claim end to end, claimants found it difficult to obtain advice and information on the status of their claim and Agency staff were hampered in their attempts to resolve claimants' queries. The Agency had instead decided to adopt a task based design for claims processing to enable staff in different offices to work on any tasks relating to any claim, but it did not adequately consider the customer interest in following their claims through the process and the consequent impact of the new way of working on customer service. The development of new business processes should take the customers' requirements into account in the design of the proposed system and any potential contingency arrangements.
  vii   A lack of information was the principal cause of frustration and complaint within the farming community. Automated telephone lines provided unhelpful responses such as "there is nothing that the call centre staff can tell you about your payment". Farmers were discouraged from pursuing queries by being told that "If you contact us, this will divert resources away from the urgent tasks of completing validations and making full payments". A communications strategy should be developed which keeps all concerned but particularly customers in touch.
  viii   The Agency could not easily determine how much work remained outstanding on claims each week and how long it would take to complete them. The Agency had deferred development of software to draw out key information on the progress of each claim to focus resources on other parts of the system it considered to be critical. Those with oversight of the project thus found it difficult to distinguish between real progress and inherent optimism within the project team. Specific measures should be developed from the outset to enable implementation progress to be assessed objectively, and make sure management information systems enable appropriate data to be tracked.
  ix   The Agency mothballed one contingency system on the basis it would have experienced the same data accuracy problems as the main system, although it would have allowed processing on a claim by claim rather than a task by task basis. The Agency also decided not to invoke partial payments available from the end of January 2006 because it expected to make full payments in March 2006, but in the end was unable to do so. Genuine and workable contingency arrangements commensurate with the project profile and risk need to be factored into the business case and developed from the outset.
  x   The Department did not recommend specifying a minimum claim size, unlike Germany which specified a minimum claim of 100 Euros (around £68). Adopting a similar approach would have reduced the number of claims by almost 14,000 (12%) and saved administration costs which may well have exceeded the sums claimed. In designing processes and in supporting documentation such as application forms, cost effective opportunities to simplify should be identified and implemented.
  xi   The Department and Agency established separate boards to provide technical programme management and critical challenge but there was a lack of clarity as to which Board or individual was ultimately responsible for decisions. The challenge board took a greater role in decision making as the project proceeded, blurring its scrutiny role. The departmental Permanent Secretary at the time, Sir Brian Bender, bears responsibility for administrative failure leading to additional costs that together risk exceeding £400 million. There needs to be a clear distinction within project governance structures between those responsible for oversight and challenge and those managing the decision making process, even when a project reaches a crisis point.
  xii   The Agency's management team recognised the risks to delivery of the project, but the Chief Executive, Johnston McNeill, felt unable to show that it could not be delivered. At issue, however, was not just the feasibility of the project, but the acceptability of the risks, which were acknowledged to be high. If Accounting Officers believe that their assessment of risk is being discounted, the proper course of action is to seek a direction from the departmental Accounting Officer or Minister concerned as to whether they should proceed.
  xiii   The structures originally set up to oversee the project included two Senior Responsible Owners, one for policy (in the Department) and one for implementation (in the Agency). Splitting the role of Senior Responsible Owner was bad practice, and undermined the Department's ability to challenge the Agency's progress reports. Every project should have one Senior Responsible Owner so that lines of accountability and responsibility are clear. The Department should agree progress milestones with the Senior Responsible Owner, whose pay and performance bonuses should be directly linked to performance objectives and programme delivery. Every project should have objective targets and progress data so that any corrective action can be triggered quickly.
  xiv   The implementation of the single payment scheme was subject to four Office of Government Commerce Gateway Reviews between May 2004 and February 2006, and three of these Reviews assessed the programme as "red". Development work on the computer system nevertheless continued and no contingency plan was invoked, despite limited confidence that the system would be ready on time. If 'red' reviews are to be taken seriously, departments need to be explicit about the circumstances in which they would lead to fundamental review or termination of a project.
  xv   We are disappointed that it took the present Accounting Officer, Mrs Helen Ghosh, nine months to provide the Committee with a full account (in the form requested) of the total cost to public funds of removing Mr Johnston McNeill from office as Chief Executive of the Rural Payments Agency and from employment as a civil servant. We expect Accounting Officers to show better co-operation with such requests by the Committee.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 6 September 2007