Select Committee on Public Accounts Fifty-Fifth Report


2  What went wrong

9. European Union Regulations offered some discretion to Member States over how to implement the single payment scheme. In August 2004, Ministers decided to introduce the scheme in England using the most complex, "dynamic hybrid", basis of payment, following advice from officials that the scheme was deliverable for 2005 claims. Under a dynamic hybrid rate, payments to claimants are based partly on the historic rate and partly on a flat rate per hectare. Over time, the historic rate proportion declines until payments are wholly based on a flat rate. For farmers in England who had previously received subsidies, 90% of the payment in the first year was calculated by reference to amounts received in the past and 10% on a flat rate per hectare. Wales and Scotland adopted the "static historic" rate of payment[10] and Northern Ireland adopted the "static hybrid" [11] rate.[12]

10. Germany was the only other European country to adopt the dynamic hybrid rate in 2005. In Germany the Federal Ministry of Food, Agriculture and Consumer Protection used its contingency scheme to make advance payments in December 2005, and final payments in April to June 2006. The German government also specified a minimum claim size of 100 Euros. Figure 2 below shows that notifying farmers in England of a minimum claim of 100 Euros would have reduced the number of claims by 14,000 or 12%, thus mitigating the increase in the number of claimants to 116,000 in 2005 compared with 70,000 in 2004 under previous schemes.[13]

Figure 2: A large proportion of claims in 2005 were for a relatively small amount of money


Source: National Audit Office analysis of Rural Payments Agency Data

11. Achieving the challenging timetable agreed with Ministers was made difficult because the Department and the Agency underestimated the amount of work involved. The timetable to develop the new computer system was based on assumptions on the likely policy content of the final scheme. By December 2004, however, the Agency had identified 23 changes required to be made to the system largely to incorporate changes to European Union regulations and legal clarification of those regulations, Ministerial decisions and other identified changes. Implementing the changes deferred the forecast date for making payments from December 2005 to February 2006, but pressure on the timetable also led to the Agency accepting IT components before they had been fully tested. Work on developing a digital map of farmers' lands (as required by European Regulations) commenced in 2002. The Agency did not pilot test adequately the process of registering farmers, accurately mapping their land and confirming eligibility. It had expected to record 1.7 million parcels of land but had to deal with 2.1 million parcels. Once the Agency started processing the 2005 single payment scheme a backlog of farmers' map registration forms built up, reaching 31,000 forms by September 2005.[14]

12. Implementation was further complicated due to the decision to incorporate the work into an existing business change programme. The computer system became a key feature of the Agency's reorganisation plans to reduce staff numbers. Processing of claims was switched to a 'by task' basis instead of using a single member of staff or small team to process a whole claim from start to finish. Overcoming the difficulties with processing claims depended on the Agency having sufficient skilled staff to resolve outstanding queries. The Agency had, however, let 1,000 experienced staff leave on redundancy terms during 2005-06 as part of re-organisation plans to reduce headcount by 1,800 posts. Under pressure to meet payment deadlines, the Agency spent £14.3 million recruiting temporary staff. It also cancelled the second wave of planned redundancies. The Agency was unable to say whether it had recruited any of its former employees to work as temporary staff.[15]

13. The Office of Government Commerce Gateway Reviews had raised specific concerns about the progress of the project and the June 2005 review in particular had questioned whether the project would succeed. The Department considered that the 'red' reviews did not necessitate that the project should be stopped, but instead that they should take action to address the risks identified. The National Audit Office had recommended that in future for key mission critical projects where the Office of Government Commerce had a direct intervention role, the Senior Responsible Owner should specify, in conjunction with departmental officials, the circumstances in which the results of a Gateway Review should be used to advise senior officials and Ministers that a project should be stopped or fundamentally reviewed. The Accounting Officer suggested that the Gateway process could usefully assist in judging the underlying capability of an organisation to deliver the necessary change.[16]

14. Despite the high risks identified from the outset in implementing the project, the Department lacked genuine workable contingency arrangements and hence in response to warning signals the Department and Agency continued to press ahead. The Department explained that the contingency computer systems available at different stages of the project would have relied on the same data such as the maps and hence would have encountered similar problems. However, 90% of the 2005 payment was based on amounts received by farmers in the past, and the number of claims at just over 116,000 was relatively small so that contingency arrangements to maintain farmers' cash flow should have been practicable.[17]

15. According to the Agency's financial data, the outturn cost of the project to implement the single payment scheme at March 2006 was £122 million, some £46.5 million more than anticipated with further increases likely to take account of key elements of the system deferred such as the software to extract management information. The provision of £131 million for potential disallowance by the European Commission of payments for the 2005 scheme year exceeded the project cost, illustrating the poor value for money achieved. In February 2007 Parliament approved a supplementary estimate of £305 million to meet the potential cost of additional disallowance on the 2005 and 2006 single payment schemes and residual liabilities on the previous schemes administered by the Rural Payments Agency. The business change programme (which includes the single payment scheme) had cost £258 million by March 2006 and was expected to achieve efficiency savings of only £7.5 million by March 2009. The departmental Accounting Officer agreed that expected benefits from the project and programmes had not been achieved and more costs were likely before savings arose. Nevertheless, the Agency now had a Rural Land Register, digitised maps and good customer data on which it could build for the future.[18]

16. Contrary to advice from the Office of Government Commerce, the Department and the Agency put in place two Senior Responsible Owners to oversee the project, one, in the Department, responsible for policy and one, in the Agency, responsible for implementation. Both Senior Responsible Owners and the then permanent secretary of the department, Sir Brian Bender, were directly involved in the programme. The Director General for Sustainable Farming, Food and Fisheries in the Department, Mr Andy Lebrecht, was the Senior Responsible Owner with oversight of the policy framework relating to Common Agricultural Policy Reform. The former Chief Executive for the Rural Payments Agency, Mr Johnston McNeill, was the Senior Responsible Owner for the implementation of the single payment scheme and the Accounting Officer for the Rural Payments Agency. The division between Senior Responsible Owners meant, however, that he had to implement policy decisions to which he had not always been party.[19]

17. There were two key oversight boards. The CAP Reform Implementation Board (CAPRI), responsible for programme management, was alternately chaired by the two Senior Responsible Owners, Mr Johnston McNeill and Mr Andy Lebrecht. The Executive Review Group, chaired by the Department's Permanent Secretary, considered papers previously reviewed by CAPRI, and its terms of reference were to provide a critical challenge function. Responsibilities between the two boards became blurred as the project proceeded and both took greater control of implementation, rather than one acting as a challenge to the other. As the crisis developed, documents were often prepared at the last minute and reports to senior officials were long and complex and did not routinely draw out key messages or corrective actions required, making it difficult to challenge the basis of some of the data submitted. The pressure to have systems ready in time led the Agency to defer development of the computer programme required to extract management information. Only between 20 February and 10 March 2006 did it become clear to the Agency that it would not be able to meet the target of paying claims by the end of March. In the absence of reliable management data, the project team and officials were unable to draw adequately informed conclusions and were not sufficiently alive to the likelihood of failure and its consequences.[20]

18. The Chief Executive of the Rural Payments Agency, Mr Johnston McNeill, was removed from post in mid-March 2006 following the failure to deliver the single payment scheme and having lost the confidence of Ministers and the Department's Accounting Officer. Many of the other senior managers in the Agency were transferred to posts elsewhere in the Department's sponsored bodies considered to be more compatible with their skills. The Department confirmed that no member of staff had received an official warning or been subject to any other disciplinary action over the project's failure.[21]

19. The former Chief Executive remained on leave of absence on full pay of £114,000 a year until 1 December 2006. The delay in resolving the former Chief Executive's employment status was due to his ill health and the need to establish his precise contractual and, therefore, pension and lump-sum entitlements. In 2004-05 he had received a performance bonus of some £21,000 (equivalent to some 18.5% of salary). The departmental Accounting Officer explained that the Chief Executive's performance targets had been linked to the Agency's targets and that they had not specifically included delivery of the single payment scheme. The Department confirmed that it did not make any severance payment to the former Chief Executive when his employment was terminated. He had received six months pay in lieu of notice totalling some £60,000. In addition, the Civil Service Appeal Board recommended that the Department should award Mr McNeill £60,800 compensation for failing to adhere to formal processes and providing him an opportunity for appeal to an independent adjudicator.[22]

20. The Interim Acting Chief Executive of the Agency had simplified the 2006 scheme application form to assist in processing claims and had also improved customer support systems. Inherent design problems within the information technology systems meant that the Agency was still not able to deal adequately with specific queries about individual claims or provide an enquiry service for callers at its local offices. The Agency commissioned consultants to review the IT system and, in the longer term, it aimed to improve its customer service by resolving potential queries earlier in the process. The Agency was developing a recovery plan which should be fully implemented by April 2008.[23]

21. The Committee's hearing on 'Delivering Successful IT-enabled Business Change' highlighted the importance of senior level engagement and for Departments to act as an intelligent client by clearly specifying the business processes to be changed and the outcomes they want to achieve. In particular, the Treasury's New Major Projects Review Group aims to ensure that complex projects, such as the implementation of the single payment scheme, are subject to high levels of scrutiny. The departmental Accounting Officer recognised the importance of developing appropriate business processes, and of making sure organisations had the right leadership capacity and soft skills capability.[24]


10   Based on average direct payment receipts of each farmer between 2000 and 2002 under previous subsidy schemes. Back

11   Payments are based partly on the average direct payment receipts of each farmer between 2000 and 2002, and partly on a flat rate per hectare of land. Back

12   C&AG's Report, paras 17, 1.7; Appendix 1; Qq 2, 3, 18-20, 188-189, 200 Back

13   C&AG's Report, paras 1.3, 2.6; Figure 1; Appendix 1; Qq 2, 3, 18-20, 36, 50, 114, 144-150 Back

14   C&AG's Report, paras 2.2-2.3, 2.5-2.8; Qq 1, 2, 3, 10, 11, 12, 28, 109-112, 192, 200, 256, 275 Back

15   C&AG's Report, para 2.9-2.10, 4.2; Qq 21-22, 44, 59, 65,148, 249-252 Back

16   Qq 10, 28, 42, 70-74, 157-164, 296-297 Back

17   C&AG's Report, paras 5.1-5.5; Qq 2, 10, 206 Back

18   C&AG's Report paras 3, 15; Qq 9, 47-48, 106; Spring Supplementary Estimate, HC 293 2006-07 Back

19   Qq 204, 244, 246, 304-306 Back

20   C&AG's Report, paras 25, 26, 5.7, 5.9-5.11; Qq 1, 10, 16, 56, 61, 203, 260-263, 267, 286, 289, 297 Back

21   Qq 31-32, 58, 81-86, 115-116, 210, 268 Back

22   Qq 15, 28, 33-35, 71,165-166, 167-187, 307, 315 Back

23   C&AG's Report, para 4; Qq 6, 17, 25, 88, 98 Back

24   C&AG's Report, paras 27-28; Qq 8, 9; Committee of Public Accounts, Twenty-seventh Report, Session 2006-07, Delivering successful IT-enabled business change, HC 113 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 6 September 2007