Select Committee on Public Accounts Thirty-Second Report


3  Improving planning and project management

11. Natural England were considering a potential project to open up coastal land to public access. It will be important to learn and apply the lessons from the Countryside Agency's implementation of the right to roam across England's mountain, moor, heath, down and registered common land. The Countryside Agency lacked proper records management procedures to respond to queries from the public and inexplicably lost many of the letters received, including correspondence from the Chairman of this Committee. In addition, the Countryside Agency significantly underestimated the cost of implementing the right to roam, with a consequent impact on funding for other projects. The Agency had estimated in December 2000 that the project would cost £28 million, whereas out-turn amounted to £52.6 million of Agency expenditure, and a total cost to central government amounting to £69 million. The £28 million estimate was a key consideration in deciding to go ahead with the project, and in prioritising between the project and the Agency's other responsibilities and initiatives. In order to fund the higher than anticipated expenditure on the 'right to roam' project, the Agency had deferred work on other schemes, such as National Trails and Discovering Lost Ways, and terminated its Vital Villages programme earlier than planned.[13]

12. The Department's 2001 Public Service Agreement included a timetable set by Ministers for all designated land to be made accessible to the public by December 2005. In their haste to deliver the right to roam project in time to meet the commitment, the Countryside Agency did not adequately pilot test the work involved and underestimated the cost of key tasks. The Agency had not carried out a scoping exercise before preparing its original estimate and it did not know the extent of the work required to map and designate the land covered by the new rights. At the time the target was agreed, neither the Department nor the Agency had questioned the timetable. Instead of a mapping pilot the Agency had rolled out the project area by area so that lessons learnt in each area could be applied to the next. The contract for the mapping was open-ended as it was based on 'day rates', and costs increased from £5.3 million to £16 million (excluding VAT). The Agency did not pilot the website on access land. Such an approach would have helped to pre-empt and resolve before the system went live the difficulties subsequently experienced by users in locating places to walk.[14]

13. The Agency's Management Board received no specific written reports on the progress and costs of the project for a period of eighteen months, from October 2001 until April 2003. It did not have an open access project board, detailed project plan or risk register until it began to improve the management of the project in 2003.[15]

14. Maintaining open access in 2006-07 is expected to cost some £13 million. At the time of the Committee's hearing, however, Natural England and the Department were uncertain of what future money had been allocated to maintaining access rights beyond 2007. Future costs will include maintaining access, signage and safety of access land; maintaining and updating the website, helpline and leaflets; and a re-mapping exercise that Natural England is committed to carry out in 2016.[16]



13   Qq 2-3, 4-6, 11, 12, 49, 63, 86-7, 94, 103; C&AG's Report, para 1.6, Appendix 3, para 1 Back

14   Qq 25-6, 50, 65-70; C&AG's Report, Appendix 3, para 4 Back

15   Qq 9, 24, 28-32; C&AG's Report, Appendix 3, paras 6-8 Back

16   Qq 45, 131; C&AG's Report, para 1.6 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 21 June 2007