Select Committee on Transport Fourth Report


2  ADMINISTRATION OF THE DEPARTMENT FOR TRANSPORT

Shared Services

4. The Department for Transport is an 'early adopter' in the programme to introduce 'shared services' across Whitehall. The purpose of the Shared Services programme is to "introduce more modern, simpler and standardised support services processes—initially in HR, finance and payroll—leading to both efficiency and effectiveness improvements."[3] The Programme is part of the Department's response to the Gershon efficiency review.[4] When we looked at the Shared Services programme during our inquiry into the Department's Executive Agencies[5], we noted that the exact cost remains unclear.[6] We also raised concerns over whether the level of optimism bias included in the plan—then £5.3 million—was sufficient. [7]

5. We were therefore less than impressed when the Permanent Secretary told us in our recent evidence session that the optimism bias "was not optimistic enough" and that the overall cost of the project had escalated from the original £50 million.[8] One reason for the cost increase is because implementation of the project has been delayed. The migration of the Driver and Vehicle Licensing Agency and the Driving Standards Agency onto the system has been held back from August 2006 to April 2007 while problems are resolved. The Department told us that: "getting the solution right before its 'switch on' is more sensible and ultimately likely to be less costly than trying to deal with problems or issues afterwards."[9] We agree that the Department should ensure the new system works before attempting to move operations on to it, but we are disappointed by the delay and concerned by its effect on the Department's ability to deliver its programme.

6. Firm revised cost estimates are not yet available but the Permanent Secretary told us: "this project has been put together on the basis of a very conservative business case, and even with some cost increase the business case is still positive".[10] The estimated costs of the programme have risen consistently since its inception and we expect the Department to keep a tight control on further cost rises to ensure that the programme ultimately delivers value for money.

7. There are also concerns over the suitability of the Department for Transport to be in the vanguard of the project. The Cabinet Office's policy is that "Government Corporate Services (human resources, finance, IT, procurement, etc) could be delivered through a handful of professional organisations—serving a minimum of 20,000 but preferably 50,000 or more customers [i.e. staff]."[11] But in the Department for Transport group, there are just 19,000 staff. The Permanent Secretary explained that 3,000 volunteer staff in the Coast Guard Rescue Service took the total number of staff over the minimum threshold for a viable shared services programme.[12] The volunteers require travel and subsistence payments and therefore need to be included in the system. We are concerned that the Department has to rely on thousands of volunteers to make up the numbers to ensure a viable service. It is possible that in the long-run a shared services function serving fewer than 50,000 staff will not survive and we believe the Department, being one of the most advanced in developing a shared services function, is well placed to offer its services to other Departments.

8. The Committee applauds the Department's efforts to improve the efficiency and effectiveness of its support services but we continue to be concerned by cost increases and delays in implementation of the shared services programme. In July 2006 we drew attention to likely problems with the level of optimism bias in the project, and we are concerned that this continues to cause difficulties. We urge the Department to scrutinise its figures carefully and re-examine its risk assessment in order to ensure that the plans more accurately predict the likely final cost. We encourage it to actively seek customers for its service from outside the Departmental group in the future, in order to secure the long-term viability of the programme.


3   Ev 6 Back

4   Sir Peter Gershon CBE, Releasing Resources for the Frontline: Independent Review of Public Sector Efficiency, HM Treasury, July 2004. Back

5   Transport Committee, Ninth Report of Session 2005-06, The work of the Department for Transport's Agencies - Driver and Vehicle Operator Group and the Highways Agency, HC 907  Back

6   ibid para 14 Back

7   Optimism bias is the demonstrated systematic tendency for appraisers to be over-optimistic about key project parameters. It must be accounted for explicitly in all appraisals. Back

8   Qq 143-144 Back

9   Ev 6 Back

10   Q144 and see Ev 46 Back

11   Transformational Government 2006, Cm 6970, page 16 Back

12   Q150 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 15 February 2007