Select Committee on Transport Fourth Report


4  LONDON UNDERGROUND

78. Responsibility for the performance of London Underground (LUL) was transferred to Transport for London (TfL) in July 2003. The Department's PSA target—to cut underground journey times by increasing capacity and reducing delays—was therefore dropped in the 2004 Spending Review. In its place, the Department agreed with the Mayor of London a set of six key indicators, five of which are increased incrementally.[119] The targets are:

  • excess journey time;
  • excess train journey time;[120]
  • operated train kilometres;
  • percentage of schedule operated;
  • overall customer satisfaction; and
  • the percentage of peak trains cancelled because no driver is available.

79. The terrorist attacks of July 2005 had a very significant impact on LUL's performance against its targets: five lines were closed or partially suspended until 4 August 2005, LUL have been without the trains involved in the incidents, a new requirement that trains must have a working radio to remain in service has been introduced, the number of security alerts has increased and some of the staff involved in the incidents have as a consequence taken time off work. It is therefore difficult to evaluate LUL's performance against its targets accurately, though figures up to 25 June 2005 suggest that five of the six targets were being met or exceeded.

80. In the longer-term, many of the improvements to London Underground's service rest on the success of the public-private partnership agreement (PPP). They include an overall increase of 25% in the capacity of the system by 2016 and the replacement or refurbishment of 80% of the Underground's track. Under the PPP, three private-sector infrastructure companies (infracos) lease the Underground's assets for a 30-year term, during which time they are required to maintain and upgrade them. Payments to the infracos are performance-based, with companies receiving bonuses if certain performance thresholds are met and paying abatements if they are not.

81. The PPP Arbiter, an independent statutory office-holder appointed to give directions and guidance to the parties to the PPP agreements, published his first annual review of the two of the infracos, Metronet BCV and Metronet SSL, in November 2006.[121] The review, initiated by the infracos concerned, asked the Arbiter to "provide a definitive statement by reference to the facts" as to whether or not the two infracos had "performed [their] activities in an overall efficient and economic manner and in accordance with Good Industry Practice".[122]

82. In reaching this conclusion, the Arbiter recognised that Metronet had introduced a number of initiatives over the previous year to address shortcomings in its performance and to put more emphasis on whole-life asset management but identified a number of areas of weakness remain including:

  • stations, where Metronet is significantly behind schedule in delivering its obligations;
  • track, where there have been insufficient resources to deliver required volumes of work and poor delivery of maintenance and renewals;
  • asset management and risk management, where there has so far been limited application of risk-based approaches that link to underlying costs and serviceability of assets, and changes in costs have been inadequately challenged at project level.[123]

83. These findings give rise to serious concern, given that the Government's plans for longer-term improvement to the Underground rest almost entirely on the PPP. The Secretary of State and the Permanent Secretary both acknowledged the severity of the problem but the Secretary of State was confident that the framework of bonuses and abatements contained the solution:

    "the contract has been designed in such a way for the framework to provide the potential solution … It is important that Metronet raises its game, but that the framework of the PPP contract allows for both London Underground and TfL to ensure that that performance in improvement is achieved".[124]

The Permanent Secretary described the financial penalties for failure as "severe" and told us that, in his view, Metronet was "in grave danger of having all of the shareholder funds wiped out and that the shareholders may well have to recapitalise".[125]

84. Metronet's poor performance in discharging its duties under the PPP agreement is cause for serious concern. Though the PPP contract was designed to reward good performance and penalise poor performance, we do not share the Secretary of State's confidence that, having performed so poorly thus far, Metronet will suddenly find that the contract produces an incentive to improve. We will continue to monitor developments in this area closely but the Government must be alive to the need to judge the PPP on the improvements it actually generates, rather than the hypothetical merits of the reward scheme it embodies.



119   Indicators were adjusted downwards following the terrorist attacks on 7 July 2005. The target for percentage of trains cancelled because no driver was available remains fixed at 0.6%. See Department for Transport Annual Report 2006, Cm 6817, pp. 271-273. Back

120   Excess train journey time means delays to services. Excess journey time means excess train journey time plus delays experienced at the station, for example, while queuing for tickets. Back

121   The Arbiter is appointed under sections 225-237 of the Greater London Authority Act 1999.  Back

122   Office of the PPP Arbiter, Annual Metronet Report 2006, 16 November 2006, p. 1. Back

123   Ibid., pp. 10-11. Back

124   QQ 104-105. Back

125   Q 110. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 15 February 2007