Implications for the transmission
network
144. Consideration
of the long-term potential of local energy has led some commentators
to speculate about the implications it would have for the transmission
network. At face value, an energy system in which all electricity
needs were sourced locally would suggest a diminished role for
a transmission network for transporting large quantities of electricity
over distances. However, as National Grid note this would only
be the case were there no need to exchange power between local
networks (i.e. they were self-sufficient in all situations) and
if there were minimal differences in the cost of producing electricity
in each area.[215]
This is not likely to be the case even with a very large expansion
of local energy capacity. We have seen already in Chapter 2 that
particular types of technology are only suited to certain locations.
As Dr Jim Watson told us: "even if everybody in the country
had a CHP boiler and a PV roof they are not always going to generate
at times you want the energy".[216]
Combined with the intermittency of some renewable sources and
the need for large-scale back-up capacity, this means there will
still be a need for a transmission network for balancing demand
and supply across the system.
145. National Grid's
conclusion is based on analysis of the potential energy systems
the UK would need to have in place by 2050 if it were to meet
the Royal Commission on Environmental Pollution's target to reduce
carbon dioxide emissions by 60%. In its report, the Commission
outlined four possible scenarios for meeting the target. In each
of these it assumed a major renewables programme, including a
significant role for PV panels, and domestic and district-CHP.
For all four scenarios, National Grid found that the transmission
network remained as necessary as it is today, if not even more
so. This conclusion has significant implications. Some of the
debate over energy policy in the past year has focused on the
apparent choice the UK faces between adopting a centralised or
decentralised energy system. National Grid's finding suggests
that, in fact, these two approaches are not mutually exclusive.
As the Energy Saving Trust said to us: "it is too simplistic
to have an either/or".[217]
In other words, new large-scale power stations would not preclude
the possibility of a big expansion in local energy capacity at
the same time.
146. The continued
importance of the transmission network reflects the fact that,
although cost reductions for local energy systems may in the future
negate the economies of scale for larger power stations, the network
is still required to provide economies of system. It enables the
diversity between different generation sources to be exploited,
and minimises the need for flexible back-up capacity.[218]
This is not to say that a large expansion of local energy would
not have any impact on the transmission network. For example,
National Grid suggests that within-day flows of electricity between
the transmission and distribution systems might change from their
current pattern, thus requiring the operator to perform its role
in a different way from at present. Also, in Chapter 2 we noted
that there was some potential for savings from the reduced need
for network investment, estimated at £35 million a year by
2020, were local energy to contribute around 10% of the UK's electricity
supply by then.[219]
147. The UK
will still require a transmission network even if there is very
large growth in the level of local energy capacity. This is because
local energy supply is rarely likely to match local demand exactly.
Hence there will be a continued need for a transmission network
that can balance electricity flows across regions and maintain
security of supply. The capacity needs of the network will depend
on the sources of electricity, although some research suggests
local energy can make a small contribution to reducing the cost
of maintaining and operating the network.
Planning for the long-term
148. The
scale of investment required to replace the large proportion of
the infrastructure currently coming to the end of its design life
suggests to us the importance of long-term planning to ensure
sensible and timely investment. The Energy Networks Association
told us that Ofgem needed to place greater emphasis on long-term
thinking, and that the structure of the current distribution and
transmission price control reviews, every five years, was not
necessarily conducive to encouraging companies to look beyond
the short-term.[220]
In its evidence, Ofgem told us that it did produce 20 to 25-year
forward-looking studies at the time of its price control reviews,
which it took into consideration in the latter, but admitted that
it did not always make it clear that it had done so.[221]
The industry has welcomed Ofgem's commitment in the 2006 Energy
Review to publish long-term scenarios of the network implications
of different types of generating capacity, including new nuclear
build and local energy.[222]
149. Developing
an understanding of the long-term implications for the network
infrastructure of different energy technologies, including local
energy, is important for ensuring timely and cost-effective investment.
This is particularly the case given the potentially long lead
times for new grid capacity. We welcome Ofgem's commitment to
publish long-term scenarios of network development, and hope the
industry will make use of these in planning its investment programme.
150. The argument
made by some lobby groups, however, that local energy production
either renders investment in renewing the grid unnecessary, or
will be frustrated by such investment, is not one we accept. Local
energy has a potentially important role to play in meeting the
UK's carbon dioxide reduction targets and enhancing security of
energy supply, but it will take many years to fulfil its potential.
200 CE Electric UK, Central Networks, EDF Energy, Scottish
and Southern Energy, Scottish Power, United Utilities, and Western
Power Distribution. Back
201
Qq 5 (Sussex Energy Group) and 181 (Institution of Engineering
and Technology) Back
202
Q 5 (Sussex Energy Group) Back
203
Department of Trade and Industry, Our Energy Challenge: Securing
clean, Affordable energy for the long-term, January 2006 Back
204
Appendix 59 (Energy Networks Association) Back
205
Appendices 1 (ABB) and 59 (Energy Networks Association) Back
206
Q 193 (Institution of Engineering and Technology) Back
207
Q 298 (Energy Networks Association) Back
208
Energy Saving Trust, Potential for Microgeneration Study and
Analysis, November 2005 Back
209
Q 505 (Ofgem) in Trade and Industry Committee, Fourth Report of
Session 2005-06, New Nuclear? Examining the issues, HC
1122; Appendix 42 (Ofgem) Back
210
Appendix 61 (Energy Saving Trust) Back
211
Q 308 (Energy Networks Association) and Appendix 59 (Energy Networks
Association) Back
212
Qq 192 (Institution of Engineering and Technology) and 320 (Energy
Networks Association) Back
213
Appendix 32 (Institution of Engineering and Technology) Back
214
Appendix 67 (Sussex Energy Group) Back
215
Appendix 63 (National Grid) Back
216
Q 17 (Sussex Energy Group) Back
217
Q 244 (Energy Saving Trust) Back
218
Appendix 63 (National Grid) Back
219
Department of Trade and Industry, System Integration of Additional
Microgeneration, September 2004 Back
220
Q 339 (Energy Networks Association) Back
221
Q 499 (Ofgem) in Trade and Industry Committee, Fourth Report of
Session 2005-06, New Nuclear? Examining the issues, HC
1122 Back
222
Appendices 58 (EDF Energy) and 59 (Energy Networks Association)
Back