Select Committee on Trade and Industry Written Evidence


APPENDIX 59

Memorandum by the Energy Networks Association (ENA)

INTRODUCTION

  This document is offered as a primer in understanding the challenges and opportunities that distributed generation (DG) have for UK electricity networks. It has been prepared by ENA with expertise in regulation and distributed generation with input from the incumbent distribution network operators (DNOs), together with the transmission operators. It assumes a basic knowledge of electricity systems and the regulatory environment.

WHAT IS DG?

  There is no internationally recognized and adopted definition of DG. For the purposes of this submission we have used a similar definition to that used in the Energy Review[1] which relates to the wide range of generation technologies that are not directly connected to the electricity transmission network. These can provide electricity from renewable energy sources such as wind, wave, tidal, waste, sunlight and water. They can also be associated with the combined heat and power (CHP) technologies.

  Such generators vary significantly in size and range; from sub-kW size domestic photo-voltaic (PV) and micro-combined heat and power (CHP) systems connected to low-voltage (LV) distribution networks to several hundred MW wind farms connected to higher voltage distribution networks.

  The identification and consideration of any network issues (eg technical, commercial and regulatory) that might constrain the deployment and development of DG has been an important consideration of the UK Government, Ofgem and various electricity industry stakeholders (in particular since the research which fed into the 2003 Energy White Paper).

BENEFITS OF DG

  It is widely recognised that distributed generation, including renewables and low carbon co-generation can make a significant contribution to meeting the key challenges the energy industry is currently facing. The potential benefits include:

    —  Climate change benefits primarily through increased penetration and use of renewables and displacement of gas power stations that might otherwise be built.

    —  Security of supply benefits primarily through improving energy security by diversification of energy sources.

    —  Economic benefits brought about through avoidance/deferral of network investment and reduced electrical losses.

  However, there are also costs associated with the connection and operation of DG in a network. These will be determined by the capability of the nation's electricity networks to absorb and adapt to different developments in electricity generation patterns. The issue is less one of the fundamental nature of distribution networks but of the nature and location of generation likely to be connected. Generally, generation that is intermittent and/or remote from the load centre will tend to add rather than remove network costs.

EXISTING AND PROJECTED DG ACTIVITY

  ENA collates statistics on the amount, type and size of distributed generation connections and connection applications in the UK distribution networks on a quarterly basis[2]. The data show that the amount of distributed generation being connected has been steadily increasing even though the spread of connections across the UK is not even.

  At the end of March 2006, the installed capacity of DG was over 12GW (almost half of which was conventional generation, primarily CCGT.) The dominant "new" technologies are CHP (32%), onshore wind (7%), offshore wind (2%), hydro (6%), landfill and sewage gas (6%) and waste incineration (4%). The biomass and energy crops plants and tidal and wave energy installations make up a small proportion of the current generation mix. The amount of micro-generation (solar, micro-wind power and micro CHP) is relatively insignificant.

  The connection of wind farms (both offshore and onshore) has made the most significant contribution to the levels of DG connected over the last two years. Connections of landfill/sewage/biogas and waste incineration plants have also been notable. The majority of newly connected plants are medium or large size (eg over 10MW) developments.

  Both the volume and types of DG connecting to the different DNO networks vary significantly. The highest growth has been in Scotland, East Anglia and the South East. In areas with abundant supplies of renewable resources, the increase in DG capacity was as much as 7% between December 2004 and January 2006, whilst other areas saw very little increase. Such developments are closely linked with the wind activity in particular being stronger in Scotland than in England and Wales. Despite current low levels of micro-generation, higher penetrations of these technologies are usually found in urban areas.

  Even though these statistics provide a useful insight into recent history, they should be approached with caution as an indication of how the UK DG "mix" is likely to develop. It is our view that growth in DG is likely to continue and the clustering will become more marked. Planning permission consents indicate that the networks serving geographic areas with larger amounts of wind resources are likely to see a similar or slightly higher rate of wind connections than over recent years. Also, many areas are likely to see an increase in biomass generation, crudely divided between energy crop fuelled systems in rural areas and refuse burning plants in towns and cities[3].

  This clustering of generation presents a challenge for DNOs, especially in areas abundant with renewable resources, as these tend to be in rural locations, typically with a relatively weak local network. As the number of such connections increases, network issues may become even more critical. Some of the existing rural networks are considered to be relatively weak as they were designed to provide connection to small loads over a widespread area and to sparse communities. Regional Spatial Strategies often identify these areas as being most suitable for large scale wind development. Accordingly, a significant number of schemes have been proposed. Furthermore, many of these communities see renewable generation as a means of providing sustainability and income in the longer term, and we might expect to see additional DG proposals in these locations.

Micro-generation

  The current volume of micro-generation connected to distribution networks is very small. Several recent studies have looked at the potential for increased roll-out of these technologies. Depending on the assumptions made, a range of projections have indicated the amount of micro-generation installations possibly reaching as high as 21GW by 2050. The projections for 2010 are considerably lower, in the range of between 77MW and 2.5GW. [4]

  The impact of micro-generation on networks has not been a significant issue to date. There have not been clustering problems in existing networks as a result of customers choosing to install micro-generators, either as a new device or as a replacement (for example, of a previous heating system). In the future, however, local authorities may require developers to install smaller generators on new buildings as a requirement of obtaining planning consent. Where there are new housing developments that contain micro-generation, the network will specifically be designed to cater for the technical issues. However, a scenario that could create a real challenge is where there is a high penetration of domestic CHP on existing networks that are not designed for bi-directional power flow. This might arise if domestic CHP became the dominant choice, through either scheme economics (as prices fall and the value of energy generated rises) or mandated standards (eg changes to building regulations).

CONNECTING AND OPERATING WITH DG—TECHNICAL ISSUES

  Distribution networks are planned and developed in accordance with the Electricity Safety Quality and Continuity Regulations (ESQCR) 2002, and the security of supply standard, Engineering Recommendation (ER) P2/6.

  The distribution networks' security standard specifies the quality of service as experienced by customers and is measured by the time taken to restore power supplies following a pre-defined set of outages. Historically, with very little or no generation present, distribution networks have been designed to be operated as "passive" networks which primarily convey electrical energy from high-voltage transmission networks to end users. The real-time control of distribution networks is limited to managing unplanned outages arising from faults and planned outages to permit access to the network to facilitate customer connections and network development projects.

  The UK's electricity networks are designed in general to deliver energy via high voltage and low voltage systems, with a "top down" direction of power flows. Increasing levels of DG in distribution networks pose certain operational and control challenges for traditionally designed and operated distribution networks. The key technical challenges relate to power flow management, voltage control and fault level management. These challenges tend to be different in rural and urban settings. In urban areas the issue is predominantly fault level, whilst in rural areas voltage management and load flow tend to be the main issues. Additional issues are related to protection requirements, the harmonics and stability.

  It should be noted that there are recognised engineering solutions to all these technical issues[5]. The industry has significantly broadened its toolkit over the past five years through work sponsored by DTI and Ofgem, through working groups including Embedded Generation Working Group (EGWG), Distributed Generation Co-ordinating Group (DGCG) and Electricity Networks Strategy Group (ENSG), through the DTI Technology Programme and Ofgem's Innovation Funding Incentive (IFI) and Registered Power Zones (RPZ) initiatives. Continued work to reduce the costs of accommodating DG relies upon these support mechanisms. Whilst the majority of solutions include the application of new or advanced technology, a new infrastructure is likely to be required in areas where there is high penetration of DG and a sparse network.

  The operation of micro-generation connected to the low voltage (230V and 400V) network can cause statutory voltage limits, recommended voltage unbalance levels and switchgear fault ratings to be exceeded. However, the level at which this happens will depend upon the generator and network characteristics[6]. Across the UK there are a range of distribution network designs and operating practices and thus the impact will vary accordingly. Mitigation could take the form of more advanced control systems, plant and switchgear upgrade but network augmentation will often be required.

Network losses

  The impact of distributed generation on network losses is another aspect of DG integration that requires due consideration. For a traditional distribution network, power normally flows from the grid supply point down through the voltage levels. Injection of power from DG changes the pattern of power flow and therefore the energy losses during the transportation of electrical energy. The relationship between DG and network losses is quite complex and dependent on location of connection, its operation/export profile, the type of network and the interaction between demand and generation. A DG connection could either decrease or increase the network losses. Furthermore, the DG connections may reduce the losses at some voltage levels while increasing the losses at other voltage levels[7].

  The impact of micro-generation technologies on network losses at LV levels, and the inter-relationship between various network management techniques aimed at facilitating DG connection and the level of network losses also deserves careful consideration.

  In summary, whilst new low carbon generation technologies are certainly able to facilitate low carbon economy goals, they may often lead to the networks operating sub-optimally from a losses perspective. In such instances, any future regulatory incentive framework which is put in place will need to ensure that network operators are encouraged to take decisions which are consistent with the government's energy and environmental policy objectives.

CONNECTING AND OPERATING WITH DG—REGULATORY ISSUES

  The regulatory framework that has governed the networks post-privatisation has been a great success. The private electricity companies have been allowed to run their own businesses within a regulatory regime which has encouraged the fullest possible utilisation of existing network assets. This framework has served the country well with a 50% real reduction in use of system charges since privatisation. However, more than two thirds of the network is now nearing the end of its design life and will need to be replaced sooner rather than later. This will require substantial and sustained increases in investment by the DNOs. Ofgem acknowledged this during the most recent price control review (DPCR4), allowing a 48% increase in DNO capital investment over the five years to 2010, compared with the previous period (2000-05).

  As part of its response to the Government's environmental objectives and for the development of renewables in particular, Ofgem also introduced new mechanisms for the DNOs to facilitate the connection of DG. They comprised:

    —  Revised connection charging arrangements for connecting to the distribution network based upon a "shallower charging methodology" and the introduction of generator use of system charges designed to reduce the generators' initial cost of connection. (In addition, the DNOs are working together under ENA, and with industry stakeholders, to develop an enduring framework for charging for connection and use of the system, which will apply both to demand and generation, and be cost reflective, transparent and facilitate competition in supply and generation).

    —  A package of incentives for DNOs to respond proactively to requests from generators to connect to their network. These included:

    —  an incentive for connecting DG (that also applies to micro-generation) which is set at 80% pass through plus £2.50/kW/year (£3 in the North of Scotland). Also, generators connected at HV and above receive compensation for access failure.

    —  an Innovation Funding Incentive (IFI) to cover most of the cost of development projects focused on the technical development of distribution networks to deliver value to end customers. This incentive was introduced in response to concerns that the current regulatory framework was discouraging R&D funding by DNOs. It is also designed to encourage collaboration between DNOs, universities, suppliers and manufacturers.

    —  The creation of Regional Power Zones which encourages DNOs to provide new, innovative and more cost-effective solutions to DG connections.

  In addition, the incentive on DNOs to reduce their network losses was increased by over 50% to £48/MWh (in 2004-05 prices).

  These incentives have applied since April 2005 and thus experience of their effectiveness is limited. However, it may be possible to draw some tentative conclusions from their operation to date.

    —  First, it is not clear that the revised connection charging arrangement has attracted increased levels of DG onto the system. This is not surprising as the current incentive does not give DNOs a positive incentive to promote DG connections; indeed uncertainty over the future application of Generator Distribution Use of System charges may actually be acting as a barrier to DG entry. Overall however, we believe that the "shallower" charging policy has not been a major consideration when developers are considering whether or not to develop a site. Other factors, such as availability of generation resource, planning permission and more direct incentive schemes such as Renewable Obligation Certificates (ROCs) are far more important.

    —  There is concern that the DG incentives package actually drives DNOs to take a short term/low risk approach to determining reinforcement proposals. There are many uncertainties in potential DG developments (financial viability, planning consent, landowner consent etc) and the developers tend to seek application at a very early date, before these uncertainties are removed. The new DG revenue incentive does not provide full pass-through of capital invested. So DNOs will naturally minimise their risk by investing only what is required to accommodate DG on a scheme by scheme basis, once they are reasonably sure that each scheme will go ahead. This may not lead to the optimal development of the distribution system.

    —  In addition, while the DG incentive is effective in ensuring that effective localised infrastructure is put in place, it does not fund the deep reinforcement required in resource rich, infrastructure sparse areas. The current incentive arrangements should therefore be augmented with a mechanism that takes a holistic view of likely network requirements in the medium to long-term and changes DG from being a bolt-on extra to an integral part of the way DNOs develop their networks.

    —  Whilst ENA supports the RPZ initiative, it has its practical shortcomings, mainly around finding first, a network opportunity, secondly, a suitable novel technology and a co-operative developer all at the same time. However, there is a deeper concern that its scope is too narrow. This is because it rewards DNOs only for making DG capacity available, and essentially creates "reception" networks that simply accept more DG onto an otherwise standard system.

    —  Despite some concerns voiced about whether the RPZ framework is achieving its objectives of demonstrating innovation[8], Ofgem's initiatives have provided a welcome opportunity to develop new ideas and pilot new operational control schemes. The RPZ initiative in particular provides a very useful platform to stimulate the deployment of active distribution networks and demonstrate more innovative generation and network technologies. Several DG-related IFI projects are currently under way (eg demand side management and virtual power plant, single phase LV regulator, OHL fault passage indicators etc) and also, three RPZ schemes (within Central Networks, SSE and EDF Energy's areas).

FACILITATING DG CONNECTIONS

  The DNOs have done much over the last five years to facilitate connection of DG by providing and successfully implementing technical solutions and hence removing the majority of technical (and technical/commercial) barriers to the development of distributed generation.

  Examples of work achieved with ENA involvement include (but are not limited to):

    —  A common technical guide to the connection of generation to distribution networks.

    —  A banding guide for DG.

    —  New Engineering Technical Reports (ETRs) 124 and 126 related to active management of power flows and voltage levels respectively, applying new techniques to reduce DG connection costs while maintaining system security.

    —  A new ER G83/1 for the connection of micro-generation.

    —  The review of planning/security standard ER P2/5 ie publication of ER P2/6 which accounts for DG contribution to network security by quantifying the ability of various forms of DG to displace networks assets. This tends to reduce overall system costs, to the benefit of customers in general, rather than benefiting DG developers directly.

    —  A system of reporting the distribution related DG activity.

  DNOs have also been very active in re-examining traditional operating practices and looking for innovative technological and technical solutions that will lead not only to more cost-effective and efficient connection and operation of distributed generation but also prevent significant reinforcements. Developing new technical solutions in the areas of voltage control and power flow management have been most intensive as these are often the initial barriers faced in the connection and operation of DG. Another area of activity is communications and control which is seen as key to enabling active distribution networks.

  Whilst the uptake of micro-generation has been relatively slow to date, DNOs have recognised that the impact of these technologies on low voltage distribution networks is potentially significant if larger penetrations are to occur in the future. The most likely limitation will arise due to network design practices for local low voltage networks and possibly also for 11kV feeders. Realising the full potential of lower voltage networks in particular will require further clarification of the requirements under ESQCR that would potentially permit a wider (LV) voltage operating range within specified parameters and hence permit a wider penetration of DG (especially micro-generation) into LV networks.

A WAY FORWARD

  Although it is impossible to predict with certainty the precise future structure of the electricity networks, it is widely expected that the UK will progressively move towards a network with a wide range of generation technologies in use at every level of the distribution and transmission system. Load as well as generation will be controllable and local areas of the network will become more self controlling. Customers themselves may become a more integrated part of the control of DNO networks. The distribution network may become an integral part of an overall energy delivery system as electricity, heating, cooling and transport become co-ordinated. On the one hand, this may smooth power demand and production, but on the other it will add a new dimension to the operational and control requirements.

  These considerations are complemented by the fact that much of the equipment on our electricity networks is increasingly at the end of its serviceable life. The requirement for investment to replace ageing equipment and reinforce the networks is coupled with an opportunity to facilitate the integration of new and emerging generation and network technologies which will offer many benefits to increasingly aware and actively engaged energy customers. As very significant investment will be required to simply renew this infrastructure, the most efficient way forward is to incorporate advanced and innovative technologies and solutions when planning this renewal. The approach to "design-in" for greater network capability and functionality will also allow for managing uncertainties and future, as yet unforeseen, changes.

  Planning for the future is essential so that we make the best use of technological innovation but also deal with all the commercial, regulatory and environmental considerations as well. The industry is considering the ways that would allow it to plan for the rolling replacement of ageing network assets while building in additional capacity, capability, flexibility and resilience that will be needed to meet customers' expectations, security of supply and climate change objectives.

  ENA has consistently called upon Ofgem to consider the long term investment needs of the network companies in the context of a time frame well beyond the traditional five years of a single network price review period. ENA is therefore encouraged that Ofgem has stated in its response to the Energy Review (April 2006) its intention to work with the network operators to draw together and publish long term scenarios for network developments reflecting perspectives on broader and long term trends. ENA has also welcomed the Energy Review's recommendation that Ofgem and Government will undertake a comprehensive review of the incentives and barriers that impact on distributed electricity generation (including CHP).

  There is a need for appropriate business drivers and regulatory incentives to encourage the developments necessary for the nation's networks to deliver what is required of them over the long term. The present regulatory regime is designed for a passive network and provides, for example, little opportunity for generators to participate in voltage control, ancillary services or to coordinate their output. It also requires developments on the network to be considered on a case by case basis with new network users desiring the cheapest solutions. This gives little opportunity for co-ordination and long term strategic planning or scope to adopt new technologies or operating practices.

  In most circumstances, as traditional techniques are sufficient to allow new connections of load or generation, there is no business case to adopt more innovative methods even if they may be more efficient in the long term. In the situations where conventional techniques are not adequate there is not sufficient time or resources to build the confidence to use Active Network Management (ANM). Moreover, the current regulatory incentives to improve quality of supply in terms of Customer Minutes Lost (CMLs) and Customer Interruptions (CIs)) do not necessarily support and encourage an innovative approach to network management that ANM techniques introduce.

  The present regulatory framework should therefore be reviewed to ensure that there are no regulatory disincentives to ANM development. The effective development of active network architecture requires a more long term and well-aligned incentive programme to allow DNOs to invest in ANM solutions. Innovation and investment is increasingly important because "like for like" replacement will not secure the change in network and service capabilities that will be needed to meet rising consumer expectations and recent changes in government objectives.

  It should also be noted that there will be major differences between DNOs in the volumes and types of DG connecting to their networks and thus the impact that DG will have on them will also differ. Consequently, any new regulatory framework which is developed must be sufficiently flexible to accommodate these differences, ie "one size does not fit all".

  The cumulative impact of micro-generation technologies is another area that would require further attention. Additional Government support for a few mixed micro-generation based installations could be helpful to provide much needed learning experiences for all stakeholders. The network operators in particular would benefit from practical "real world" tests of appropriate scale where the effects of micro-generation technologies can be properly planned for, assessed and tested.

INDUSTRY-GOVERNMENT COLLABORATION

  ENA members are currently working with other industry stakeholders through the DTI/Ofgem led cross-industry ENSG on the development of a comprehensive analysis of longer-term generation scenarios and development of the corresponding network architecture options. It is already widely acknowledged that all futures would require an increasing application of advanced network technologies and information and communication technologies that should be able to facilitate a range of alternative electricity system developments, from centralised to distributed[9].

  Investment into and adoption of these technologies would be critical if enhanced capability, capacity and flexibility of networks are to be achieved in the longer term. These scenarios should not be developed in isolation and ENA is discussing with Ofgem, how this work can be brought together to avoid unnecessary duplication.

  Steps have already been taken by DNOs to develop even closer integration of new generation in the system operation through the active network management (ANM) practices which will allow use of this generation to actively control the system operation and participate in the provision of system security. The initial work involved a detailed analysis and assessment of installed facilities, capacity and operating methodologies in the areas of data acquisition and management, substation and network monitoring, substation and distribution network automation, real-time control, and communications architecture and information models[10]. ANM is found to be increasing on today's distribution networks. Some local ANM solutions are successfully implemented using existing technology already installed on DNO networks. However, wide-scale implementation of ANM will require more technical understanding and confidence in both existing and new technologies and solutions.

  The networks community is also taking the opportunity to look ahead and see how electricity networks might, and, indeed might need to look like in the future. To that end, the networks representatives contributed to developing a framework for guidance to the sector on best practice for developing a technical architecture for future electricity networks[11]. They have also participated in similar activities in Europe, namely development of the "SmartGrids" technology platform. In terms of EU initiatives and activities particularly, it is important to ensure that directives and standards do not develop in ways incompatible with the design and operation of electricity networks in the UK. Discussions are also underway as to how to translate an understanding of all potential technical developments into the management of change in businesses in a liberalised electricity industry.









1   The energy challenge-Energy Review Report, DTI, July 2006. Back

2   http://www.energynetworks.org/spring/engineering/distributedgeneration02.asp Back

3   SUPERGEN Future Network Technologies consortium "Electricity Network Scenarios for 2020", July 2006. Back

4   Accommodating DG, Report to DTI by Econnect Group Ltd (06/1571), July 2006. Back

5   "Technical guide to the connection of generation to the distribution network", K/EL/00318/REP, URN 03/1631. Back

6   "The Impact of SSEG on the Operating Parameters of Distribution Networks", K/EL/00303/04/01, URN 03/1051. Back

7   "Network Losses and DG", DG/CG/00038/00/00, URN no 06/1238. Back

8   "Assessing the Feasibility of Establishing Registered Power Zones on Northern/Yorkshire Electricity Network" Report to DTI by Econnect Group Ltd 2006. Back

9   "Future Network Technologies", Report for DTI, 2006. Back

10   "A technical Review and Assessment of Active Network Management Infrastructures and Practices", DGCG/00068/00/00. Back

11   "Technical Architecture-A First Report: The way ahead", June 2005. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 30 January 2007