- continued
         House of Commons

back to previous text

Schedule 4 - Overhead lines: consent

212.     Schedule 4 sets out the alternative consents regime that will apply to the installation of overhead electric lines within the Bill limits, given the disapplication of section 37 of the Electricity Act 1989 in clause 4.

213.     Paragraph 2 requires any installation to be made in accordance with the consent granted by the appropriate Ministers (defined in paragraph 12 for these purposes as the Secretary of State for Transport and the Secretary of State for Business, Enterprise and Regulatory Reform, acting jointly).

214.     Paragraph 3 sets out what an application for consent should contain.

215.     Paragraph 4 allows the appropriate Ministers to request in writing that the application be supplemented by specified additional information.

216.     Paragraph 5 sets out the publicity requirements that must be complied with in respect of certain applications.

217.     Paragraph 6 allows the appropriate Ministers, within 14 days of receiving an application for consent, to invite the local planning authority to comment on the application. The local planning authority have 28 days to comment on the application.

218.     Paragraph 7 requires the appropriate Ministers, within 14 days of receiving an application for consent, if they consider that the application relates to certain matters, to invite certain other bodies to comment on the application. Those bodies - Natural England and the Historic Buildings and Monuments Commission for England (more commonly known as English Heritage) - will have 14 days to comment on the application.

219.     Paragraph 8 sets out the grounds on which an application for consent by the nominated undertaker may be refused.

220.     Paragraph 9 allows the appropriate Ministers to make the grant of consent subject to any conditions they deem appropriate.

221.     Paragraph 10 allows the Secretary of State to vary or revoke the consent granted, after the period specified in the consent, which will not be less than ten years from the date of installation.

222.     Paragraph 11 provides that subject to paragraph 10, the consent granted will continue in force for the period specified in the consent.

Schedule 5 - Temporary possession and use of land

223.     Schedule 5 allows the nominated undertaker temporarily to take over possession of, and make use of, land in connection with carrying out the Crossrail works. The land in question is shown in the table in paragraph 1, together with the purposes for which the land may be used. This table therefore gives an indication of the purposes for which certain parcels of land may be temporarily used (for example, for mitigation works, utility diversions, means of access, the provision of working space, for highway access purposes, or for a worksite). The paragraph requires at least 28 days notice to be given to the owners and occupiers of the land before possession is taken, and the possession is time-limited to one year after completion of the works unless the owners agree otherwise. Compensation may be payable for such possession, with any disputes about such compensation to be determined under the Land Compensation Act 1961.

224.     Paragraph 2 requires the nominated undertaker, before giving up possession of any land used under paragraph 1, to put the land in question back into such condition as may be agreed in a scheme between him, the owners of the land and the local planning authority, or determined by the appropriate Ministers (for these purposes defined as the Secretary of State for Transport and the Secretary of State for Communities and Local Government, acting jointly). The paragraph also sets out what such a scheme may and may not require.

225.     Paragraph 3 allows the nominated undertaker to use any road situated on land specified in paragraph 8 of Schedule 6 for the passage of persons or vehicles. Compensation may be payable for any loss suffered as a result of such use, with any disputes about such compensation to be determined under the Land Compensation Act 1961.

226.     Paragraph 4 allows the nominated undertaker, during the maintenance period of any work (which is defined as being up to five years from the date on which the work is brought into general use), to enter upon and take possession of land within the Bill limits and within 20 metres of any scheduled work, if such possession is necessary for maintaining the work. The power granted by the paragraph does not apply to any house or garden, or land not subject to compulsory purchase under the Bill, and the nominated undertaker must give at least 28 days notice to the owners and occupiers of the land before possession is taken. The nominated undertaker may only remain in possession of such land as long as is reasonably necessary, and must, before giving up possession, restore the land in question to the reasonable satisfaction of the owners of the land. Compensation may be payable for any loss suffered as a result of such use, with any disputes about such compensation to be determined under the Land Compensation Act 1961.

227.     Paragraph 5 allows for private rights of way to be temporarily suspended and provides that compensation may be payable to anyone who suffers loss as a result of any such extinguishment, with any disputes about such compensation to be determined under the Land Compensation Act 1961.

228.     Paragraph 6 sets out the arrangements for the enforcement of any possession required under the paragraph, should the owner or occupier of the land in question refuse to give up possession of it or hinder the taking of possession. It makes similar provision to that applying to the taking of possession following notice of entry on a compulsory purchase.

Schedule 6 - Acquisition of land shown within limits on deposited plans

Part 1 - Purposes for which certain land may be acquired

229.     Part 1 sets out in a table the purposes for which certain land may be acquired. The land identified in columns (1) and (2) may be acquired or used for the purpose set out in column (3). This table therefore gives an indication of the purposes for which certain parcels of land may be acquired or used (for example, utility diversions, means of access, or for a worksite).

Part 2 - Application of legislation relating to compulsory purchase

230.     Paragraphs 1, 2 and 3 provide that the Lands Clauses Consolidation Act 1845 will not apply to the compulsory acquisition of land under the Bill. Instead, Part 1 of the Compulsory Purchase Act 1965 is to apply, as it applies to a compulsory purchase order to which Schedule 1 to the Acquisition of Land Act 1981 applies, and as if the Bill when enacted were a compulsory purchase order under the 1981 Act. However, section 4 of the 1965 Act is not to apply and section 11 of and Schedule 3 to the 1965 Act are to have effect with the amendments mentioned in paragraph 3(3) and (4). These amendments extend the normal time period between notice to treat and entering and taking possession of land from 14 days to one month (in the case of subsoil, or where an easement or other right only is sought) and from 14 days to three months (in the case of all other land).

231.     Paragraphs 4 and 5 provide that the Compulsory Purchase (Vesting Declarations) Act 1981, an alternative means of obtaining land the subject of compulsory purchase, is to apply with modifications as if the Bill, when enacted, were a compulsory purchase order. Similar amendments to the application of the 1981 Act as can be found in paragraph 5 of Schedule 4 to the Channel Tunnel Rail Link Act 1996 are also made.

Part 3 - Supplementary provisions

232.     Paragraphs 6 and 7 allow for the Secretary of State, instead of acquiring all of a person's interests in land outright, to have the power to acquire compulsorily easements and other rights for any purpose for which the land may be acquired, by creating new easements or rights. Where a new right is created, the Compulsory Purchase Act 1965 as applied by the Bill is to have effect subject to the modifications mentioned in paragraph 7.

233.     Paragraph 8 sets out land where, in order to reduce blight, rights of way only over land may be obtained. In such cases the Secretary of State is not to have power to acquire the land itself.

234.     Paragraph 9 sets out land where, because it is railway land comprised in the Heathrow Express Railway or needed for access to such land, rights only over land may be obtained. In this case, the rights that may be acquired are limited to rights of access to, or passage along, the existing railway.

235.     Paragraph 10 sets out land where the compulsory purchase power in clause 6 is limited to only so much of the land in question as is described in the table in the paragraph. These limitations are intended to reduce blight.

236.     Paragraph 11 gives the Secretary of State the power to acquire subsoil only, without being required to acquire any greater interest in any other part of the land. Certain of the land shown on the deposited plans is required for underground running tunnels and ancillary works which will be more than 9 metres deep. In these cases it is proposed that only the subsoil of the land may be taken (that is, where it is at a depth of more than 9 metres below the surface of the land). A table of this "subsoil only" land is included in the paragraph.

237.     Paragraph 12 sets out further land where the compulsory purchase power in clause 6 is limited to rights of way or subsoil more than 9 metres below the surface only.

238.     Paragraph 13 allows the Secretary of State, by order, to provide that new rights may be acquired by such persons as are specified in the order. Some of the land within the Bill limits, particularly that outside the limits of deviation but within the limits of land to be acquired or used, is intended to be used for the purposes of diverting statutory undertakers' apparatus. For apparatus placed underground, it would be common for this to be done by the acquisition of easements by the utility concerned, rather than by acquiring the land outright. This paragraph permits this.

239.     Paragraphs 14, 15 and 16 provide, as is traditional in Bills providing for the acquisition of land, an alternative procedure to that set out in section 8(1) of the Compulsory Purchase Act 1965 relating to the acquisition of part only of certain properties. This alternative procedure would have to be invoked by appending the alternative provisions to the relevant notice to treat when it is served.

240.     Paragraph 17 applies the provisions about minerals applying to compulsory purchase orders in Schedule 2 to the Acquisition of Land Act 1981..

241.     Paragraphs 18 and 19 set out the arrangements to apply if the Secretary of State extends the time limit for the exercise of compulsory purchase powers under clause 6(7).

242.     Paragraph 20 applies section 4 of the Acquisition of Land Act 1981, which deals with situations where unnecessary things have been done to obtain compensation or increased compensation, as if the Bill when enacted were a compulsory purchase order for the purposes of the 1981 Act.

Schedule 7 - Planning Conditions

Part 1 - Qualifying Authorities

243.     Paragraph 1 allows the Secretary of State, by means of an order, to name "qualifying authorities" for the purposes of Schedule 7. It is intended that these will be local planning authorities which, by the time the Select Committee in the House of Lords reports, have given the Secretary of State various undertakings about handling of planning applications (intended to be included in a Planning Memorandum which is being developed with local authorities). A similar arrangement was adopted for the planning aspects of the Channel Tunnel Rail Link.

244.     Paragraph 1 also allows the Secretary of State to make orders revoking the conferring of "qualifying authority" status and to make subsequent naming orders in certain circumstances. Before making such order, the Secretary of State is to consult the nominated undertaker and, if it is not the body requesting the order, the relevant local planning authority.

245.     Paragraph 2 allows for any order under paragraph 1 to set out any transitional arrangements that may be necessary (for example, were a local planning authority to cease to be a qualifying authority for the purposes of the Bill whilst a number of undetermined planning applications were before it).

Part 2 - Development in the area of a unitary authority

246.     Paragraph 3 establishes Part 2 as the regime to apply in respect of development carried out in the area of unitary authorities (for example, those local planning authorities in London).

247.     Paragraph 4 establishes the circumstances in which the planning conditions for which the Part provides apply, different conditions applying, in general, according to whether the development is in the area of a non-qualifying or qualifying authority.

248.     Paragraph 5 provides for certain matters of detail to be the subject of requests for the approval of the non-qualifying unitary authorities and provides that the only grounds on which they can refuse a request is that the development to which it relates should and could reasonably be carried out elsewhere within Bill limits, or that the design or external appearance of any building to which they relate ought to be modified to preserve the local environment or amenity, and is capable of being reasonably modified to do so.

249.     Paragraph 6 provides for certain matters of detail to be the subject of requests for the approval of the qualifying unitary authorities and sets out the grounds on which such authorities can refuse a request. The list of operations and works includes construction works, minor constructions works, fences and walls, artificial lighting, waste and spoil disposal and borrow pits.

250.     Paragraph 7 sets out construction arrangements over which a qualifying unitary authority shall have some control, including road transport, the handling of re-useable spoil and top soil, storage sites, construction camps, screening, artificial lighting, the suppression of dust and mud on the highway.

251.     Paragraph 8 provides that for the disposal of waste or spoil, or the excavation of bulk materials from borrow pits, no disposal or excavation shall commence unless the nominated undertaker has first agreed with a qualifying unitary authority a scheme for the restoration of the land on which the disposal or excavation is to take place. The only ground on which the authority can refuse to agree such a scheme is that the scheme ought to be modified, and is reasonably capable of being so modified.

252.     Paragraphs 9 and 10 provide for a qualifying unitary authority to grant approval before any Crossrail works are brought into use, other than for stations, depots and the tunnelled sections of Crossrail. That approval is to be granted if the authority considers that no reasonably practicable measures to mitigate the effect on the local environment or amenity are necessary, or it has agreed a scheme for such measures.

253.     Paragraph 11 provides for any land used for construction purposes with respect to the scheduled works, where other restoration provisions of the Bill do not apply to it, to be restored in accordance with a scheme agreed with the unitary authority. If no scheme is so agreed within 6 months of completion of the scheduled works concerned, the scheme is determined by the appropriate Ministers. This provision applies to both qualifying and non-qualifying unitary authorities.

Part 3 - Development not in the area of a unitary authority

254.     Paragraph 12 establishes Part 3 as the regime to apply to development carried out in non-unitary authority areas (for example, Essex). Responsibility for such development is split between district councils and the county council. The Part therefore provides for conditions which apply to the development for which district councils are responsible and conditions which apply to the development for which the county council is responsible.

255.     Paragraph 13 establishes the circumstances in which the district planning conditions for which the Part provides apply, different conditions applying, in general, according to whether the development is in the area of a non-qualifying district council or qualifying district council. Paragraph 14 and 15 apply do not apply in relation to certain development, referred to in this paragraph as "excepted development". The development in question is development for which the county council is responsible (and in relation to which the corresponding conditions found in paragraphs 21 and 22 apply).

256.     Paragraph 14 provides for certain matters of detail to be the subject of requests for the approval of the non-qualifying district councils and the only grounds on which they can refuse a request is that the development to which it relates should and could reasonably be carried out elsewhere within Bill limits, or that the design or external appearance of any building to which they relate ought to be modified to preserve the local environment or amenity, and is capable of being reasonably modified to do so.

257.     Paragraph 15 provides for certain matters of detail to be the subject of requests for the approval of the qualifying district council and sets out the grounds on which a qualifying district council can refuse a request. The list of operations and works includes construction works, minor constructions works, fences and walls and artificial lighting.

258.     Paragraph 16 sets out construction arrangements over which a qualifying district council shall have some control, including storage sites, construction camps, screening, artificial lighting, the suppression of dust and mud on the highway.

259.     Paragraphs 17 and 18 provide for a qualifying district council to grant approval before any Crossrail works are brought into use, other than for stations, depots and the tunnelled sections of Crossrail. That approval is to be granted if the council considers that no reasonably practicable measures to mitigate the effect on the local environment or amenity are necessary, or it has agreed a scheme for such measures.

260.     Paragraph 19 provides for any land used for construction purposes with respect to the scheduled works, where other restoration provisions of the Bill do not apply to it, to be restored in accordance with a scheme agreed with the district council. If no scheme is so agreed within 6 months of completion of the scheduled works concerned, the scheme is determined by the appropriate Ministers. This provision applies to both qualifying and non-qualifying district councils.

261.     Paragraph 20 establishes the circumstances in which the country planning conditions for which the Part provides apply. The conditions only apply if the county council concerned is a qualifying authority.

262.     Paragraph 21 sets out the conditions that may be applied to requests for the approval of details in respect of a qualifying county council for the disposal of waste or spoil, or the excavation of bulk materials from borrow pits.

263.     Paragraph 22 sets out construction arrangements over which a qualifying county council shall have some control, including storage sites, construction camps, screening, artificial lighting, the suppression of dust and mud on the highway.

264.     Paragraph 23 provides that for the disposal of waste or spoil, or the excavation of bulk materials from borrow pits, no disposal or excavation shall commence unless the nominated undertaker has first agreed with the qualifying county council a scheme for the restoration of the land on which the disposal or excavation is to take place. The only ground on which the council can refuse to agree such a scheme is that the scheme ought to be modified, and is reasonably capable of being so modified.

265.     Paragraph 24 provide for a qualifying county council to have some control over the routes by which heavy goods vehicles travel by road to and from working and storage sites, sites where material might be re-used, and waste disposal sites.

Part 4 - Supplementary

266.     Paragraph 25 provides that the local planning authority is not required to entertain a request for detailed planning permission unless the nominated undertaker has first submitted to that authority a programme of the permissions it intends to seek from the authority in question, and an explanation of how the matters dealt with in the permission sought fit into the wider Crossrail scheme.

267.     Paragraph 26 sets out a process for local planning authorities, where they consider a request for detailed planning permission relates to matters which may affect nature conservation, the conservation of the natural beauty or amenity of the countryside, or a site of archaeological or historic interest, to seek the views of Natural England or the Historic Buildings and Monuments Commission for England (commonly known as English Heritage), as appropriate. Those bodies are to have 21 days to comment on any such request.

268.     Paragraph 27 sets out a similar consultation provision in respect of the Environment Agency.

269.     Paragraphs 28 and 29 set out a mechanism for the Secretary of State for Transport, and the Secretary of State for Communities and Local Government, acting jointly, to issue directions either restricting a local planning authority's powers under the Schedule, or to "call-in" a particular request for approval under the Schedule.

270.     Paragraphs 30-35 set out a mechanism for the nominated undertaker to appeal decisions by local planning authorities under the Schedule to the Secretary of State for Transport, and the Secretary of State for Communities and Local Government, acting jointly.

271.     Paragraph 36 empowers the Secretary of State, by order subject to negative resolution, to amend Schedule 7 to allow the Olympic Delivery Authority to become a "qualifying authority" in connection with Crossrail. A qualifying authority is a local planning authority which has given the Secretary of State undertakings concerning the handling of planning applications for Crossrail.

Schedule 8 - Extension of Permitted Development Rights: supplementary provisions

272.     Clause 15 of the Bill allows statutory undertakers to rely on their own permitted development rights for works they carry out in relation to Crossrail, provided that the significant impacts of such diversions have been environmentally assessed for the purpose of the project as a whole. However, Schedule 8 enables the Secretary of State to intervene in this process for the purposes of avoiding a breach of a relevant Parliamentary undertaking or securing that the environmental effects of carrying out the development are not materially different from those assessed.

273.      Paragraph 1 provides the power for the Secretary of State to intervene to impose conditions on such development.

274.     Paragraphs 2 and 3 provide a further power for the Secretary of State to intervene in respect of proposed development where he is of the opinion that such development has not been the subject of environmental assessment or where it appears to the Secretary of State that a Parliamentary undertaking may be broken. The effect of this intervention is that the utility developer's deemed planning permission for such works is suspended or liable to revocation.

275.     Paragraphs 4-6 provide a mechanism for notifying the concerned developer and responsible planning authority of the Secretary of State's intervention and the reasons for it.

Schedule 9 - Heritage: disapplication and modification of controls

276.     Schedule 9 essentially disapplies the normal heritage protections provided in respect of listed buildings, buildings in conservation areas, and ancient monuments, that might be affected by the Crossrail works. Notwithstanding these disapplications, the intention is to seek to agree the detailed arrangements that will apply to the relatively small number of such buildings etc likely to be significantly affected with English Heritage outside the Bill during its passage.

277.     Paragraph 1 lists in a table the buildings affected, and provides that in relation to the Crossrail works, if a listed building had been listed immediately before 15th December 2004 and is specified in the table:

  • section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 should not apply;

  • to the extent that a notice issued in relation to the building under section 38(1) of that Act requires the taking of steps which would be rendered ineffective or substantially ineffective by works proposed to be carried out in exercise of the powers conferred by the Bill when enacted, it should not have effect or cease to have effect;

  • no steps may be taken under section 42(1) of that Act which would be rendered ineffective or substantially ineffective by such works and;

  • no works may be executed for the preservation of the building under section 54 of that Act which will be rendered ineffective or substantially ineffective by such works.

278.     The same disapplications apply to any building which was not a listed building before 15th December 2004 but is listed on or after that date.

279.     The table also lists buildings which are situated in a conservation area but are not listed buildings. In relation to these buildings, section 74 of the Planning (Listed Buildings and Conservation Areas) Act 1990 is disapplied with respect to their demolition if the demolition is in exercise of the powers conferred by the Bill. A similar disapplication applies in relation to a building within an area which becomes a conservation area on or after 15th December 2004.

280.     Paragraph 2 deals with listed buildings which may be affected by settlement. In relation to these buildings similar disapplications as those above apply, save that the disapplication of section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 would only apply to works for the alteration or extension of the building which are carried out in exercise of powers conferred by the Bill for the purpose of maintaining or restoring its character as a building of special architectural or historical interest.

281.     Paragraph 3 provides that section 59 of the Planning (Listed Buildings and Conservation Areas) Act 1990 does not apply to anything done in exercise of the powers conferred by the Bill with respect to works.

282.     Paragraph 4 modifies the application of the Ancient Monuments and Archaeological Areas Act 1979 ("the 1979 Act") in respect of Crossrail works:

  • section 2 of the 1979 Act does not apply to any works authorised by the Bill;

  • the powers of entry conferred by sections 6(1), 6A(1) and 26 are not to be exercisable in relation to land used for or in connection with the carrying out of such works;

  • the provisions of the 1979 Act with respect to functions of a person as a guardian, and the provisions of any agreement under section 17, are to have effect subject to the powers conferred by the Bill with respect to works;

  • section 19 is not to apply in relation to a monument which is closed by the nominated undertaker for the purposes of, in connection with, or in consequence of the carrying out of any of the Crossrail works;

  • regulations under subsection (3) or (4A) of that section are not to apply to the Crossrail works, and the power conferred by subsection (6) of that section is not to be exercisable so as to prevent or restrict the exercise of such powers;

  • in section 25 of the 1979 Act, subsection (2) is not to authorise the superintendence of the carrying out of any of the Crossrail works, and subsection (3) is not to apply in relation to advice given in connection with the carrying out of any of those works;

  • section 28 is not to apply to anything done in exercise of the powers conferred by the Bill with respect of works.

  • section 35 is likewise not to apply to operations carried out in the exercise of those powers.

  • section 39(1) is to have effect as if operations carried out in exercise of those powers were exempt operations; and

  • subsection (1) of section 42 is not to apply to the use of a metal detector for the purposes of or in connection with the Crossrail works, and subsection (3) of that section is likewise not to apply to the removal of objects discovered by the use of a metal detector for those purposes.

283.     Paragraph 5 modifies the application of the National Heritage Act 1983 to the Crossrail works. The power of entry conferred by section 36(1) of the 1983 Act is only to be exercisable in relation to land used, or intended for use, for or in connection with the Crossrail works with the consent of a nominated undertaker, such consent not to be unreasonably withheld. Such consent may be given subject to compliance with any reasonable requirements or conditions imposed for reasons of safety or for the purpose of preventing interference with or delay to the works. Any disputes about this are to be determined by the appropriate Ministers unless the parties agree to arbitration. For this purpose the appropriate Ministers means the Secretary of State for Transport and the Secretary of State for Culture, Media and Sport, acting jointly. And subsection (6) of section 36 of the 1983 Act, which regulates the right to enter land for the purposes of record keeping, is not to apply to land on which works authorised by the Bill are being carried out.

 
previous Section Bill Home page continue
 
House of Commons home page Houses of Parliament home page House of Lords home page search Page enquiries ordering index

© Parliamentary copyright 2007
Prepared: 9 November 2007