Crossrail BillSchedule 6 — Acquisition of land shown within limits on deposited plansPart 1 — Purposes for which certain land may be acquired
108
(1)
(2)
(3)
Area
Number of land shown on
Purpose for which land may
deposited plans
be acquired or used
1411 and 1411a
The provision of a
working site and the
5
diversion of public
utilities’ apparatus.
1440a and 1440b
The provision of
protective works for the
construction of Work No.
10
2/8A
1443
working site.
London Borough of
4 and 7
Newham
working site and
15
6d
The provision of barge
loading facilities and
mitigation works.
20
8a, 8c and 8d
9 and 10
The provision of access
for construction and
operational purposes
25
and the diversion of
public utilities’
apparatus.
75
30
111, 112 and 115
138, 139, 146, 148, 149, 151
35
to 154, 158, 162, 174, 175
working site, access for
and 178
construction and
and works to pumping
station.
40
182 and 190 to 192
194 to 196
109
216, 217, 219 to 221, 223,
224, 233, 236 to 238, 240,
241 and 251
261, 270, 273 and 274
331
The diversion of electric
high voltage
underground cables.
330a and 330b
294 to 297, 314, 316, 356,
363, 376, 381, 382 and 386
566, 578, 591 to 597, 599,
600, 604, 607, 609, 611,
working site, diversion
612, 615 and 617
of overhead electric
cables and access for
maintenance.
413, 416 and 418
610, 616, 618, 620 to 665,
The provision and
671 to 683, 685 to 694 and
renewal of railway
698 to 703
systems and station
facilities for operational
purposes.
684
695
666 and 668
667 and 669
30b, 30c, 31b, 31c, 32b,
Greenwich
39c, 39d, 39e, 39f and 44b
110
31d, 38b and 39a
33a, 36a, 41a and 39g
working site and access
operational purposes.
85
86
and protective works.
98, 105 and 112a
working site, the
utilities’ apparatus and
the provision of access
103
The diversion of public
110a and 110b
112b
124 and 126
underground cables and
other public utilities’
142, 143, 145 and 147
150
111
154
180
188 and 189
228
62
Bexley
72, 74, 76 and 77
63, 65, 66 and 67
for construction.
69 to 71
1, 2, 6, 8, 13, 15, 22 to 25,
Redbridge
27 to 37, 42 to 68 and 70 to
38
The provision of access.
39 and 40
63a and 64b
64c
working site, access and
depot facilities.
69
112
87a
97
9 to 11
Barking & Dagenham
systems for operational
19
22
and the diversion of high
pressure gas pipelines.
3
Havering
6 and 7
9
diversion of high
25 and 26
113
36 and 38
pressure gas pipelines,
the relocation of gas
pressure reduction
stations and the removal
of a gas holder.
87
94
122, 125, 126 and 128 to
133
and temporary station
facilities.
114, 115, 119, 121, 123, 124
and 127
construction, the
the provision and
renewal of station
97 to 102, 135 to 137 and
139, 141 to 147, 150 to 153,
155 to 159, 183, 185 to 193
and 196 to 199
148
169a
195
Borough of Brentwood
1 to 23 and 25 to 32
114
34 and 39
51
District of Basildon
7 to 12
District of Tendring
1 to 5
systems and depot
Royal Borough of
25a
Windsor & Maidenhead
39 to 41
improvement of station
53 to 61 and 64 to 67
and renewal of railway
purposes and the
63
68
69 to 71, 73 and 74
working area.
District of South Bucks
1 and 4 to 7
1a and 1b