3 Apr 2008 : Column 1267Wcontinued
Ordnance Survey: Cost Effectiveness
Mr. Prisk:
To ask the Secretary of State for Communities and Local Government (1) what account was taken of the cost-benefit analysis commissioned from Cambridge University on trading funds when formulating Ordnance Survey's new public sector task; [197764]
(2) what account was taken of (a) advice and (b) guidance from (i) the Office of Public Sector Information and (ii) the Advisory Panel on Public Sector Information in formulating Ordnance Survey's new public sector task; [197803]
(3) what Government agencies and offices were consulted on the formulation of Ordnance Survey's public sector task. [197804]
3 Apr 2008 : Column 1268W
Mr. Iain Wright:
In April 2007, Ministers asked Ordnance Survey and the Shareholder Executive to work together to prepare a more precise articulation of Ordnance Surveys Public Task as set out in the Ordnance Survey Framework Document 2004. This work was undertaken between April and June 2007.
Ministers approved the revised Public Task document in July 2007 before the Cambridge University study was commissioned. The Shareholder Executive conducted discussions with senior officials in Ordnance Survey and the Department for Communities and Local Government before submitting the Public Task document to Ministers. Neither the Office of Public Sector Information nor the Advisory Panel on Public Sector Information were consulted.
Planning Inspectorate: Appeals
Mrs. Lait:
To ask the Secretary of State for Communities and Local Government how long the Planning Inspectorate takes to (a) register and (b) process a planning appeal; and if she will make a statement. [197477]
Mr. Iain Wright:
The Planning Inspectorate receives about 2,000 appeals a month and aims to register these within three working days. As at 28 March 2008, some 1,530 new planning appeals had not been registered, the oldest of which were received on 29 February. The inspectorate is working hard to retrieve the situation and has introduced measures to allow it to direct more resources into eliminating the backlog. These have seen the number of appeals waiting to be registered fall from over 2000 in December 2007 to the present figure.
Target handling times set by Ministers vary according to the nature and complexity of the planning appeal and the method used to process it. For example, in February, the average time taken following registration to decide appeals proceeding by the written representations method was 18 weeks. For appeals proceeding by hearing or inquiry method, it was 39 weeks. Further details of performance in relation to planning appeals can be found on the inspectorate website:
Planning Permission: Compensation
Lembit Öpik:
To ask the Secretary of State for Communities and Local Government how much was awarded in compensation to planning applications that were rejected but subsequently allowed on appeal in each of the last three years; and how much of this amount was paid to registered social landlords. [198146]
Mr. Iain Wright:
Compensation is not payable for winning an appeal against refusal of planning permission. Parties can apply for an award of costs in planning appeals and applications are determined in accordance with longstanding Government guidance
3 Apr 2008 : Column 1269W
contained in DOE Circular 8/93. Awards are made only where one party is found to have acted unreasonably and as a result caused another to incur quantifiable unnecessary or wasted expense.
The actual amount to be paid is not determined by a costs award. That is for the parties to settle by negotiation initially. Accordingly, no records are available of costs paid following awards on appeal in each of the last three years, whether or not involving social landlords.
The following table shows by financial year, the number of local planning authorities being liable to pay costs following awards made against them by Inspectors and the Secretary of State:
Financial year | Number of local planning authorities liable | Approximate percentage of applications against authorities |
2004-05
|
338
|
34
|
2005-06
|
304
|
39
|
2006-07
|
362
|
38
|
Planning Permission: Floods
Miss McIntosh:
To ask the Secretary of State for Communities and Local Government (1) how many times she has called in a planning authority's decision to proceed with a development in a case where the Environment Agency objected to the development because of flood risk since April 2007; [197755]
(2) for what reasons she permitted developments to proceed in each of the cases referred to in the Environment Agencys Annual Report 2006-07 where the Agency objected to the developments on grounds of flood risk; [197757]
3 Apr 2008 : Column 1270W
(3) for those cases where a development took place against an Environment Agency objection on grounds of flood risk between April 2006 and March 2007 if she will publish (a) the Environment Agency objection and (b) the final decision of the planning authority; and what further steps may be taken in such cases to encourage the planning authority to take greater account of the Agencys objection. [197756]
Mr. Iain Wright:
The Secretary of State has called in four planning applications under the Town and Country Planning (Flooding) (England) Direction 2007, (the Direction). This requires local planning authorities to send details of all applications for major development they are minded to approve where the Environment Agency has an objection, to the Secretary of State to consider whether or not they should be called-in for decision. Since 2007, the Secretary of State has called-in a further four planning applications, not under the Direction, where flooding was a main issue.
The 13 cases referred to in the Environment Agencys HLT5 Report 2006-07, were granted planning permission by the respective local planning authorities before the Direction came into force. The Environment Agencys objections to those applications are tabled as follows.
The Direction requires that where a local planning authority wants to grant planning permission for a major development to which the Environment Agency objects, the authority and the Agency must discuss and agree a course of action which would allow the Agencys objection to be withdrawn. Such discussions are proving fruitful in resolving flood risk issues, and have allowed most of the planning applications referred to the Secretary of State, to be returned to the local planning authorities for decision.
Details of the high level target 5 (HLT5) 2006-07: 13 major development proposals granted planning permission contrary to Environment Agency concerns |
Local planning authority | Nature of development | Flood zone | Reason for Environment Agency objection |
North Lincolnshire Council
|
Barton upon Humber. Proposed tipping of cement kiln dust and inert factory waste above existing approved levels.
|
3
|
The proposal involved significant land raising within the floodplain. Environment Agency objected as no Flood Risk Assessment (FRA) had been submitted, and was concerned about possible increased flood risk to third parties. Extensive consultation with the LPA, but LPA knowingly overruled Environment Agency advice on the grounds that the proposal would have other environmental improvements.
|
West Lindsey District Council
|
Gainsborough. Erection of 38 residential units.
|
3
|
The Environment Agency objected to the application on grounds that the site is within Flood Zone 3 high risk and no Flood Risk Assessment had been submitted with the application. A FRA was subsequently submitted; however the Environment Agency maintained its earlier objection on the grounds that the FRA had not considered the flood risk posed by a breach in the banks of the nearby River Trent. However, the Environment Agency did not object to the allocation of the site in the (now adopted) Local Plan, and the site benefits from an extant planning permission. The LPA considered it unreasonable to refuse the application, given the earlier approval and the Local Plan status.
|
East Lindsey District Council
|
Mablethorpe. Proposed development of 10 single storey dwellings (bungalows).
|
3
|
The Environment Agency objected on the basis that the site is located within Flood Zone 3 high risk, and the LPAs own adopted catchment-wide flood risk assessment showed the site could flood to depths between 1-1.5 m in the event of a breach in the raised sea defences. The Environment Agency therefore considered the site inappropriate for single storey development. Site already has an extant planning permission for a similar proposal before the LPAs own flood risk assessment had been prepared. Despite the flood risk, the LPA considered it unreasonable to refuse the new application, given the earlier approval.
|
3 Apr 2008 : Column 1271W
3 Apr 2008 : Column 1272W
East Lindsey District Council
|
Chapel St. Leonards. Erection of 18 dwellings, estate roads and vehicular/pedestrian access.
|
3
|
The Environment Agency objected on that basis that the site is located within Flood Zone 3 high risk, and the LPAs own adopted catchment-wide flood risk assessment showed that the site could flood to depths greater than 2 m in the event of a breach in the raised sea defences. The assessment identifies the site as being within the critical velocity zonethe highest subdivision of risk as set out in the assessment. Given the predicted speed/depths of floodwater and the risk to life and property, the Environment Agency advised the LPA that residential development was generally not suitable in this area and objected. However, the site had an extant planning permission dating back to 1994, prior to the consideration of flood risk, and the LPA granted planning permission on the basis that this application represented a betterment in flood risk terms compared with that 1994 permission.
|
East Lindsey District Council
|
Chapel St. Leonards. Change of use of agricultural land to 71 pitch touring caravan site.
|
3
|
The Environment Agency objected on the basis that the site is located within Flood Zone 3 high risk, and the LPAs own adopted catchment-wide flood risk assessment showed that the site could flood to depths of between 1 and 2 m in the event of a breach in the raised sea defences. The assessment identifies the site as being within the Rapid Inundation Zonewhere flood waters are greater than 0.5 m and/or have a velocity of greater than 1 m/second. Given the predicted speed/depths of floodwater and the risk to life and property, the Environment Agency advised the LPA that it could not support an application for a new caravan site in such flood depth zones, and objected. The LPA accepted the dangers, but overruled the objection on the grounds of overriding tourism and economic benefits.
|
Plymouth City Council
|
Plymouth. Temporary permission for the provision of motor cycle speedway track and ancillary accommodation and facilities.
|
3
|
The Environment Agency objected as the site lies within Flood Zone 3 High Risk, and yet no Flood Risk Assessment was submitted with the planning application as required by Government guidance PPG25. The LPA approved the application without re-consulting the Environment Agency, as a proposal on the same site had been upheld at appeal in 1998, when an Inspector found that no demonstrable harm would result from that development, although in that case the site was to have been raised (hence appropriately defended). This appeal decision predates Government policy on development and flood risk, and the need for FRAs. A permanent permission application has subsequently been submitted and approved. A FRA was submitted with this application allowing the Environment Agency to remove its objection.
|
Mid Suffolk District Council
|
Stowmarket. Construction of a new access road incorporating new junction arrangements and bridge with ancillary works.
|
3
|
The Environment Agency objected as development might lead to a loss of flood storage capacity, and the Flood Risk Assessment submitted was unsatisfactory as it was for a different site to the actual proposal. From the information submitted it was not clear whether the bridge proposal would impede flood flows by encroaching into FZ3. Although the Environment Agency responded late to this consultation, our response was in time to influence the decision. Delegated decision, so our concerns were not reported to committee.
|
Doncaster Metropolitan Borough Council
|
Doncaster. Factory/warehouse extension.
|
2/3
|
The application site fell partly within flood zones 2 and 3. Although the LPA received a Flood Risk Assessment from the developers to accompany the planning application, the Environment Agency never received this. The Environment Agency therefore objected on the grounds that no FRA had been prepared to accompany the application, in accordance with PPG25. Our objection was not reported upon in processing the planning application. As a result, the fact that the FRA had never been received was not picked up, and the Environment Agencys objection was never recorded.
|
Sandwell Metropolitan Borough Council
|
West Bromwich. Two new distribution/industrial units with associated service yards and car parking.
|
1
|
The objection relates only to surface water run off risk, not development in a high risk flood zone. Due to the size of this application (> 2 Ha), the Environment Agency objected on the ground that no Flood Risk Assessment had been submitted, and the surface water runoff could increase the flood risk to others. The LPA consulted the Environment Agency late, and our response was never reported to committee as the application was determined before it was received. A condition was attached to the planning permission requiring a FRA to be carried out retrospectively before the development commences.
|
Stafford Borough Council
|
Stafford. Development of an automotive complex.
|
1
|
The objection relates only to surface water run off risk, not development in a high risk flood zone. The application site lay within a longstanding employment site under development at the time of the application. Due to the size of this application (> 4 Ha), the Environment Agency objected on the ground that no Flood Risk Assessment had been submitted, as required under PPG25, and the surface water runoff could increase the flood risk to others. Environment Agency concerns were reported to committee, and the committee report acknowledges that the application should be decided in accordance with latest Government policy on flood risk and development. The committee however approved the application.
|
3 Apr 2008 : Column 1273W
3 Apr 2008 : Column 1274W
London Borough of Barnet
|
Barnet. Outline application for 23 houses and 78 flats.
|
1
|
The objection relates only to surface water run off, not development in a high risk flood zone. The Environment Agency objected on the ground that due to its size, the application might present a significant flood risk to others from the generation of surface water run-off, and therefore required a Flood Risk Assessment, as per Government guidance. The LPA approved the proposal without requesting a FRA from the developer, or re-consulting the Environment Agency. The LPA included a condition on the planning permission requiring the developer to retrospectively carry out a FRA before development commences.
|
Swindon Borough Council
|
Swindon. Redevelopment of former railway works for hotel, offices, retail, 211 apartments and ancillary uses.
|
1
|
Although this site lies within flood zone 1, due to the size of the site (3.4 Ha) and the nature of the development proposal, the Environment Agency was concerned that the application might present a significant flood risk to others from the generation of surface water run-off. The applicant was required therefore to provide a Flood Risk Assessment to accompany the application, as per Government guidance. Initially the Environment Agency requested further information about whether a FRA had been carried out, and requested an extension to the consultation period. There is no record of any extension being agreed, and the Environment Agency finally submitted a late response (June 2006) objecting to the proposal on the ground that no FRA had been submitted. The LPA did not approve the proposal until February 2007. Environment Agency concerns were not reported to committee.
|
West Berkshire District Council
|
Hungerford. Erection of 36 residential units with associated car parking.
|
1
|
An Outline Planning Permission was granted in 2005 for 16 dwellings, which the Environment Agency provided comments on in 2002. As the site lies within Flood Zone 1 the Environment Agency requested a surface water condition, which was applied to the extant permission. A subsequent planning application was submitted for 36 residential units in 2006. Although the applicant provided a Flood Risk Assessment in accordance with Government guidance, the Environment Agency objected as it was not satisfied with the surface water drainage strategy submitted as part of the FRA. The development could present a flood risk to others by generating surface water run-off. The Environment Agencys objection was reported to the Planning Committee in August 2006. The objection was not resolved before planning permission was granted. The Council applied a condition requiring full details of the surface water drainage system to be submitted before development commenced on the site. Despite ongoing negotiations the proposed surface water drainage system still does not meet Environment Agency requirements.
|
Rackspace
Mr. Hands:
To ask the Secretary of State for Communities and Local Government what the value was of each contract awarded to Rackspace by (a) her Department and its predecessors and (b) its agencies in each of the last nine years. [197511]
Mr. Dhanda:
No contracts have been awarded to Rackspace by the Department or its predecessor, the Office of the Deputy Prime Minister, which was formed in May 2002.
No contracts have been awarded to Rackspace by the Departments agencies.