Previous Section Index Home Page

11 Jun 2008 : Column 257W—continued

Armoured Fighting Vehicles: Procurement

Nick Harvey: To ask the Secretary of State for Defence if he will make a statement on the planned in-service dates for the Future Rapid Effects System. [209730]

Mr. Bob Ainsworth: In common with all defence equipment programmes, the in-service dates for the future rapid effect system family of armoured vehicles
11 Jun 2008 : Column 258W
will be fixed at the main investment decisions. It is our policy not to release or discuss in-service dates ahead of the main investment decision.

AWE Burghfield

Norman Baker: To ask the Secretary of State for Defence pursuant to the Answer of 24 January 2008, Official Report, column 2138W, on AWE Burghfield, in what way the emergency arrangements infrastructure at AWE Burghfield was affected by the July 2007 flooding; and what steps have been taken to remedy the situation. [208892]

Mr. Bob Ainsworth: As a consequence of the flooding in July 2007, the fallback incident control room, fallback medical centre and health physics support areas at AWE Burghfield sustained some damage. Contingency arrangements were put in place to ensure full emergency response could be activated if required. These were considered by the Nuclear Installations Inspectorate (NII) to be adequate at all times for the activities being undertaken. On 22 April 2008, AWE Burghfield undertook its annual exercise on emergency response arrangements, witnessed by the NII, who considered that the exercise adequately demonstrated AWE Burghfield’s capability in this area.

Norman Baker: To ask the Secretary of State for Defence pursuant to the Answer of 20 May 2008, Official Report, column 178W, on AWE Burghfield, how many of the safety shortfalls identified at AWE Burghfield by the Nuclear Installations Inspectorate remain outstanding; and what the target date is for remedial work to be completed. [208894]

Mr. Bob Ainsworth: The safety case issues to which the hon. Member refers were identified not by the Nuclear Installations Inspectorate, but by AWE plc in its own Periodic Review of Safety. In my answer on 15 January 2008, Official Report, column 1132W, to the hon. Member for Portsmouth, South (Mr. Hancock), I indicated that 50 work packages were due for completion by 31 March 2008 and that the remaining 53 were scheduled to be complete by the end of the year. The 50 work packages were completed by the due date. The remainder remain on course for completion, as planned.

Bombs

Mr. Drew: To ask the Secretary of State for Defence whether he plans to destroy the UK's stock of cluster munitions; what the estimated costs of so doing is; and if he will make a statement. [210147]

Mr. Bob Ainsworth: We will dispose of UK cluster munition stockpiles in accordance with the provisions in the adopted convention. We are assessing the likely costs of disposal and these will be made available to the House as soon as they are known.

Finmeccanica

Mr. Carswell: To ask the Secretary of State for Defence on what date Sir Kevin Tebbit joined the board of Finmeccanica UK. [209601]

Mr. Bob Ainsworth: That is a matter for Finmeccanica.


11 Jun 2008 : Column 259W

Joint Strike Fighter Aircraft: Procurement

Nick Harvey: To ask the Secretary of State for Defence if he will make a statement on the planned in-service dates for the Joint Strike Fighter. [209731]

Mr. Bob Ainsworth: I refer the hon. Member to the answer given by my hon. Friend the Minister for Defence Equipment and Support in the other place on 8 January 2007, Official Report, column WA8. We will not be setting in-service dates for the joint combat aircraft (JCA) until we take the main investment decision, and we will take that decision when the project is sufficiently mature. The joint strike fighter remains our preferred solution to meet the JCA requirement and our current plans for JCA remain coherent with the CVF programme.

Military Aircraft: Helicopters

Nick Harvey: To ask the Secretary of State for Defence how many Ukrainian helicopters are being used by UK forces in current operations; and where they are being used. [209584]

Mr. Bob Ainsworth: The Ministry of Defence does not own, nor has it contracted for, any Ukrainian helicopters for use by UK forces in Iraq or Afghanistan.

Peacekeeping Operations

Mr. Ellwood: To ask the Secretary of State for Defence how many Snatch Land Rovers are deployed in (a) Afghanistan and (b) Iraq. [209615]

Nick Harvey: To ask the Secretary of State for Defence (1) what percentage of (a) CRVT, (b) Saxon, (c) Warrior and (d) Challenger vehicles are in (i) Iraq and (ii) Afghanistan; [209574]

(2) how many Mastiffs are in theatre in (a) Iraq and (b) Afghanistan; [209575]

(3) how many Challenger tanks have been used in (a) Iraq and (b) Afghanistan; and what percentage this represents of all tanks used. [209577]

Mr. Bob Ainsworth: There are no Challenger 2 tanks deployed to Afghanistan and similarly there are no CVRT or Saxon vehicles deployed to Iraq.

I am withholding the rest of the information requested as its disclosure would, or would be likely to prejudice the capability, effectiveness or security of our armed forces.

Peacekeeping Operations: Manpower

John Bercow: To ask the Secretary of State for Defence how many British troops are serving in United Nations or other peacekeeping forces; and in which countries they are serving. [208461]

Mr. Bob Ainsworth: As at 26 May 2008 there were 300 UK service personnel deployed on UN operations, 280 of whom were located in Cyprus. Other locations include Georgia, Nepal, Sudan, Sierra Leone, Democratic Republic of Congo and Liberia.


11 Jun 2008 : Column 260W

The following table shows the number of UK service personnel deployed on operations by location at 26 May 2008. The number of personnel in theatre will naturally fluctuate on a daily basis for a variety of reasons, including leave (rest and recuperation), temporary absence for training, evacuation for medical reasons, the roulement of forces and other factors.

Number of personnel deployed by location( 1)
Location Number

Total

15,120

O f which:

Afghanistan

8,200

Iraq

4,500

Kuwait(2)

900

Qatar

420

Kosovo

330

Cyprus

280

Oman

260

At sea

80

Bahrain

80

Bosnia

10

Other

25

(1) Countries with 10 or more personnel are shown separately. Other countries with fewer than 10 personnel per country include Georgia, Nepal, Sudan, Sierra Leone, Democratic Republic of Congo and Liberia.
(2) Figures for Kuwait are artificially high due to a current Operation Telic Relief In Place (RIP) operation.

UK forces are currently deployed on a wide range of missions, under differing mandates, in a number of countries across the world including those conducted under the auspices of the UN, EU and NATO. The number of UK service personnel serving in these countries is detailed above. The majority of these missions comprise, to one degree or another, activity that could be fairly described as peacekeeping.

Scotland

Angus Robertson: To ask the Secretary of State for Defence what the value of Ministry of Defence property sold in Scotland was in the last (a) year, (b) five years, (c) 10 years and (d) 20 years. [209726]

Derek Twigg: Disposal receipts arising from Ministry of Defence property sales in Scotland since 2000-01 total £124.6 million. This includes £23.6 million in 2007-08 (subject to final audit) and £77.4 million for property sold over the last five financial years. Figures for the years before 2000-01 are not available.

Submarines

Angus Robertson: To ask the Secretary of State for Defence what progress has been made in the detailed concept design stage of the Vanguard successor submarines; and if he will make a statement. [210085]

Mr. Bob Ainsworth: Following the parliamentary vote in support of the Government's decisions on the future of the United Kingdom's nuclear deterrent on 14 March 2007, a collaborative MOD/industry team was formed to take work forward. The team is halfway through the concept phase of the programme, and is working to develop the information and realistic options needed to deliver a robust Initial Gate Business Case in late 2009.


11 Jun 2008 : Column 261W

Transport

Fairtrade Initiative

Mr. Moore: To ask the Secretary of State for Transport pursuant to the answer of 7 February 2008, Official Report, column 1417W, on the Fairtrade initiative, what the value was of Fairtrade produce purchased at her Department's staff catering facilities in each of the last three years; and what proportion of total expenditure this represented. [209019]

Jim Fitzpatrick: The information requested is not held centrally and to obtain this data for the Department (including seven executive agencies) would incur disproportionate cost.

However, it has been estimated that at our main London HQ building the total annual value of Fairtrade purchases is £13,608 and this represents approximately 5 per cent. of total expenditure.

The value of Fairtrade produce purchased by the Vehicle Certification Agency during the six months it has been purchasing Fairtrade products is £1,340.

Purchases undertaken by the Driver and Vehicle Licensing Agency, Driving Standards Agency, Highways Agency and the Vehicle and Operator Services Agency are not separately recorded.

Lorries: Excise Duties

Mr. Steen: To ask the Secretary of State for Transport how many heavy goods vehicles entered the UK from the EU in each of the last three years; and what taxes were imposed per lorry in road tax and other charges. [209892]

Jim Fitzpatrick: The Department collects and publishes data on the numbers of heavy goods vehicles travelling to mainland Europe by vehicle nationality. A breakdown of the data for the last three years is provided in the following table, representing outwards journeys only. Inwards journeys are not collected.

The equivalent data for vehicles travelling to the Republic of Ireland by ferry and across the Irish land boundary are not available.

Powered road goods vehicles travelling to mainland Europe by country of registration
Thousand vehicles
2005 2006 2007

UK

418

406

400

EU(1)

1,407

1,473

1,623

Non-EU(2)

106

134

96

Unknown

10

9

11

Total

1,941

2,021

2,129

(1) For 2005 and 2006, does not include Bulgaria and Romania
(2 )For 2005 and 2006, includes Bulgaria and Romania

EU law is clear that member state policy measures may not inhibit the freedom of movement of goods and may not discriminate (directly or indirectly) according to nationality of haulier or the origin or destination of a vehicle. This of itself precludes any lump-sum tax levied specifically on entry to the UK.


11 Jun 2008 : Column 262W

Motorways: Speed Limits

Mr. Greg Knight: To ask the Secretary of State for Transport what the reasons are for the (a) 50 mile per hour speed limit around the roadworks north of junction 6 on the M1 motorway and (b) 40 mile per hour speed limit at the roadworks on the M40 in the vicinity of junction 1; and if she will make a statement. [210204]

Mr. Tom Harris: The 50 mph speed limit on the M1 north of junction 6 is in place for the duration of the widening works between Junctions 6a and 10, to ensure the safety of roadworkers and road users. The 50 mph speed limit starts at Junction 6 for traffic to flow into the contraflow and safely past the works area.

The 40 mph speed limit is from Swakeleys roundabout on the A40 to M40 J1 at the Denham roundabout, while strengthening and parapet replacement work is being carried out on the Denham Viaduct.

The 40 mph speed limit is in place for the safety of roadworkers and road users, particularly cyclists who could use the narrow lanes during the works on the A40.

Mr. Greg Knight: To ask the Secretary of State for Transport if she will issue guidance to the Highways Agency on operating a consistent policy towards speed limits on motorways when roadworks are taking place in different areas. [210205]

Mr. Tom Harris: National advice on setting temporary speed limits is given in Traffic Signs Manual Chapter 8, which is developed by the Highways Agency on behalf of the Department for Transport. This identifies appropriate speed limits based on the relative risk to road users. The Highways Agency produced additional advice in July 2007 (Chief Highways Engineer Memo 203/07) on how to apply temporary speed limits at road works using the risk based approach in Chapter 8.

Mr. Greg Knight: To ask the Secretary of State for Transport what the reasons are for the 50 mile per hour speed limit remaining in force on the southbound carriageway north of junction 9 of the M1 motorway after the opening of four carriageways to traffic. [210206]

Mr. Tom Harris: The 50 mph speed restriction remains in place for the following reasons.

There are still elements of work to be completed, which may impact on the safety of the travelling public. This mainly involves work to the safety fencing.

Once the safety fence work has been completed, there will still be a safety concern for both the work force and the travelling public. This is because if the 50 mph speed limit is removed, it will mean that four lanes of traffic travelling at 70 mph will be merging into a 50 mph three lane section, where work is still continuing. This could result in an increase in incidents and cause further delays.


Next Section Index Home Page