Previous Section Index Home Page

17 Jun 2008 : Column 849W—continued

Chinook Helicopters

Mr. Meacher: To ask the Secretary of State for Defence whether his Department has initiated disciplinary action against any individual as a consequence of their involvement in the commissioning of the eight Chinook helicopters which remain unairworthy. [210713]


17 Jun 2008 : Column 850W

Mr. Bob Ainsworth [holding answer 16 June 2008]: A full inquiry into the circumstances surrounding the Chinook procurement was held in 2004. It found that the failures were systemic and no individuals were to blame. Lessons have been learnt and procedures have been put in place to avoid a similar occurrence.

Departmental Cost Effectiveness

David Taylor: To ask the Secretary of State for Defence how many times officials in his Department met representatives of the National Audit Office in each year since 1997 to discuss the value for money of his Department's major projects. [211483]

Mr. Bob Ainsworth: MOD officials meet regularly with representatives of the National Audit Office to discuss a variety of subjects, including value for money. The specific nature of individual meetings is not held centrally.

Departmental Responsibilities

Dr. Fox: To ask the Secretary of State for Defence which of his Department's projects gained main gate approval in 2007-08. [210663]

Mr. Bob Ainsworth: This information is not held centrally and could be provided only at disproportionate cost.

Departmental Transport

Mrs. Villiers: To ask the Secretary of State for Defence when each of his Department's and its agencies' green transport plans were introduced; and if he will place in the Library a copy of each such plan. [209414]

Derek Twigg: The Ministry of Defence has not published a green transport plan. In a Department of MOD’s size and complexity, travel is something most tangibly dealt with at site level. Two MOD agencies have published green transport plans: The Hydrographic Office in April 2008 and The Meteorological Office in 2007. I shall place copies of both plans in the Library of the House.

France: Military Alliances

Dr. Fox: To ask the Secretary of State for Defence what plans his Department has to mark the 10th anniversary of the UK-France agreement reached at St Malo in 1998. [211397]

Des Browne: None.

Gibraltar Services Police

Andrew Mackinlay: To ask the Secretary of State for Defence when the Permanent Joint Headquarters appraisals of (a) the proposed transfer of police functions of the Gibraltar Service Police (GSP), (b) the functions and jurisdiction of the GSP on land currently owned and managed by his Department and (c) the future of GSP assets will take place; if he will place in the Library a copy of each appraisal on completion; and if he will make a statement. [211162]


17 Jun 2008 : Column 851W

Mr. Bob Ainsworth: Work is continuing on the future of the Gibraltar Service Police. Part of this process will involve discussions between HQ British Forces Gibraltar and the Government of Gibraltar on future policing options. Once these discussions have concluded, there will be a full appraisal of the options for the future of the GSP before any final decision is taken. I will write to the hon. Member once a final decision has been taken.

Iraq: Peacekeeping Operations

Dr. Murrison: To ask the Secretary of State for Defence which units have been deployed to (a) Iraq and (b) Afghanistan over the last 12 months with full-strength bearing; and how many troops were deployed. [182606]

Des Browne [holding answer 28 January 2008]: All units deploy at the required strength for the tasks they are asked to fulfil during their operational tour.

Information on the number of troops from each unit which deployed to Iraq and Afghanistan in the last 12 months is being collated. I will write to the hon. Member when the information is available.

Substantive answer from Des Browne to Andrew Murrison:

Annex A: Formed unit strengths deployed on recent operational tours
Telic deployments: Telic 9—November 2006 to May 2007
Unit Unit strength

2(nd) Bn Lancashire Regt

455

Queens Royal Lancers

320

1(st) Bn Yorkshire Regt

550

2(nd) Bn The Rifles

703

40 Regiment Royal Artillery

298

3(rd) Bn Mercian Regiment

509



17 Jun 2008 : Column 852W
Telic deployments: Telic 10—June 2007 to November 2007
Unit Unit strength

2(nd) Bn Royal Welsh Regiment

522

1(st) Bn Irish Guards

409

4(th) Bn The Rifles

587

1(st) Regt Royal Horse Artillery

388

Kings Royal Hussars

445


Herrick deployments: Herrick 5—October 2006 to April 2007
Unit Total unit strength

42 and 45 Commando Royal Marines

2,067


Herrick deployments: Herrick 6—April 2007 to October 2007
Unit Unit strength

1(st) Bn Royal Anglian Regt

583

2(nd) Bn Mercian Regiment

466

The Light Dragoons

190


Herrick deployments: Herrick 7—October 2007 to April 2008
Unit Unit strength

40 Commando Royal Marines

822

Household Cavalry Regt

190

1(st) Bn Royal Gurkha Rifles

585

1(st) Bn Coldstream Guards

500

4 Regt Royal Artillery

372


Mike Penning: To ask the Secretary of State for Defence in which vehicles British service personnel were (a) killed and (b) injured as a result of hostile action in (i) Iraq and (ii) Afghanistan in each month since operations started; and if he will make a statement. [210136]

Des Browne: I am withholding the details requested as disclosure would, or would be likely to prejudice the capability, effectiveness or security of the armed forces.

Lynx Helicopters: Procurement

Mr. Carswell: To ask the Secretary of State for Defence whether his Department plans to reduce the number of Future Lynx procured from AgustaWestland; and if he will make a statement. [209595]

Mr. Bob Ainsworth: We currently have no plans to reduce the number of Future Lynx procured.

Mr. Carswell: To ask the Secretary of State for Defence whether he plans to reduce the amount spent on the Future Lynx capability. [209596]

Mr. Bob Ainsworth: We currently have no plans to reduce the overall expenditure on Future Lynx.

Mr. Carswell: To ask the Secretary of State for Defence (1) on what date the decision was taken not to procure the (a) NH90 helicopter, (b) Bell 407 helicopter, (c) EC635 helicopter, (d) AB139 helicopter and (e) UH-60 helicopter to meet the capability to be met by the Future Lynx; [209598]

(2) on what date the business case for the Future Lynx was approved by his Department's Investment Approvals Board; [209599]


17 Jun 2008 : Column 853W

(3) if he will initiate an investigation into the procedures used in reaching the decision to award the Future Lynx contract. [209607]

Mr. Bob Ainsworth: The correct departmental procedures were followed to reach the decision to procure the new Future Lynx helicopter. I do not therefore see a need to initiate any investigation into the procedures followed in arriving at this decision. The final decision was taken by MOD Ministers, following agreement from Her Majesty's Treasury, on 31 May 2006 on the basis of advice and recommendations from the MOD Investment Approvals Board.

Mr. Carswell: To ask the Secretary of State for Defence how much of the Future Lynx Business Plan was completed by November 2005. [209600]

Mr. Bob Ainsworth: The final Future Lynx Main Gate Business Case was submitted to the Department's Investment Approvals Board on 5 December 2005.

Mr. Carswell: To ask the Secretary of State for Defence with reference to the letter of 31 July 2007 from Lord Drayson to the hon. Member for Harwich, (1) what assessment he has made of the ability of Future Lynx to meet the surface combatant maritime rotorcraft capability at a lower cost than alternatives; [209602]

(2) what assessment he has made of the ability of Future Lynx to meet the battlefield reconnaissance helicopter capability at an equivalent cost to alternatives. [209603]

Mr. Bob Ainsworth: The Ministry of Defence follows a detailed approvals process for all major equipment procurement decisions. For all such decisions a range of factors are considered including acquisition cost, the ability of the equipment to meet our capability requirements, technical and programme risk and coherence with the defence industrial strategy. The approvals process is designed to ensure all these factors are considered and procurement decisions are not based on any single factor. In the case of the surface combatant maritime rotorcraft and battlefield reconnaissance helicopter capabilities, following consideration of the range of factors, Future Lynx was considered to be the best solution to meet our requirements.

Mr. Carswell: To ask the Secretary of State for Defence (1) for what reasons his Department did not conduct a competitive process before awarding AgustaWestland the contract to build the Future Lynx to meet the battlefield reconnaissance helicopter requirement; [209604]

(2) what consideration was given to procuring an off-the-shelf helicopter under a competitive process to meet the battlefield reconnaissance helicopter requirement; and what estimate he has made of when helicopters would have been available to the armed forces under such a procurement process. [209605]

Mr. Bob Ainsworth: An assessment was made by the Department in 2001 which concluded that the Future Lynx aircraft likely offered the best through-life approach to the delivery of the Army's battlefield light utility helicopter (BLUH) and Royal Navy's surface combatant maritime rotorcraft (SCMR) requirements and a sole
17 Jun 2008 : Column 854W
source assessment phase was launched. We continued to benchmark the Future Lynx approach against other opportunities, including within the analysis that underpinned the future rotorcraft capability programme during 2004-05, where the Army's requirement was described as the battlefield reconnaissance helicopter (BRH).

The analysis concluded that the delivery of the BRH and the SCMR requirements through a single helicopter type (Future Lynx) provided the best combination of through-life military capability, time to deliver into service, cost and risk. As such, we decided not to launch a competition.

Mr. Carswell: To ask the Secretary of State for Defence what account was taken in the Department's procurement process of the conclusion of the long-term partnering agreement between his Department and AgustaWestland in March 2005, with particular reference to bidders for fulfilment of the Future Lynx contract. [209608]

Mr. Bob Ainsworth: The Heads of Agreement signed with Agusta Westland in March 2005 and announced via a written ministerial statement on 24 March 2005, Official Report, column 83WS, committed the Department to exploring the possibility of partnering. The same statement confirmed that the potential award of a Future Lynx contract was subject to continuing negotiations to agree acceptable contract conditions and prices within clearly defined parameters. The subsequent decision to proceed with Future Lynx was taken as this represented the best through-life approach; its contribution to the sustainment of critical UK skills was a secondary consideration.

Unmanned Air Vehicles

Nick Harvey: To ask the Secretary of State for Defence how many Predator unmanned aerial vehicles the armed forces have; and how many have been (a) used in recent operations and (b) shot down. [209653]

Mr. Bob Ainsworth: The Ministry of Defence has procured three Reaper unmanned aerial vehicles, also known as Predator B. Reaper operations began in Afghanistan in October 2007 and capability continues to be built up. None have been shot down, but one was lost in April 2008 as the result of a forced landing. A replacement will be delivered in due course. We do not comment on the exact numbers of platforms in use on operations at any particular time.

Warships: Guided Weapons

Dr. Fox: To ask the Secretary of State for Defence how many weapons systems have been removed from ships in the Royal Navy because (a) of the need to make expenditure reductions, (b) they were no longer operationally needed and (c) for other reasons in the last 12 months. [210673]

Mr. Bob Ainsworth: As a result of agreed resource priorities, a decision was made in 2007 to remove sea dart weapon systems from two Type 42 Destroyers. Royal Navy Ships continue to be armed with weapon system capabilities required to meet their tasking.


17 Jun 2008 : Column 855W

I am withholding further details as their release would, or would be likely to, prejudice the capability, effectiveness or security of the armed forces.


Next Section Index Home Page