6 Oct 2008 : Column 468W—continued


6 Oct 2008 : Column 469W

6 Oct 2008 : Column 470W
Local authority Original expected project completion date Current expected project completion date Major reasons for delay

Wave 1

Bradford

December 2007

September 2008

Challenging original completion expectations; Issues around use of untested processes

Bristol

April 2008

January 2009

Challenging original completion expectations; Issues around use of untested processes

Greenwich

April 2009

September 2011

Piloting of non-standard BSF procurement model by local authority has been problematic and has caused considerable delay; Local resourcing difficulties; Issues around use of untested processes

Knowsley

September 2009

January 2010

Issues around use of untested processes

Lancashire

September 2010

August 2010

Leeds

September 2010

September 2011

Issues around use of untested processes

Leicester

September 2011

September 2011

Lewisham

July 2010

September 2010

Issues around use of untested processes

Manchester

September 2009

June 2011

Challenging original completion expectations; Issues around use of untested processes; later project rescoping, including integrating seven new academies

Newcastle

March 2011

March 2011

Newham

January 2009

March 2011

Challenging original completion expectations; Issues around use of untested processes; Local resourcing difficulties

Sheffield

March 2010

April 2011

Challenging original completion expectations; Issues around use of untested processes

Solihull

September 2008

September 2009

Challenging original completion expectations; Issues around use of untested processes

STaG

December 2012

January 2013

Issues around use of untested processes

Sunderland

Jan 2010

September 2010

Challenging original completion expectations; Issues around use of untested processes

Waltham Forest

September 2008

September 2008

Wave 2

Birmingham

September 2010

September 2011

Challenging original completion expectations; Local resourcing difficulties; More time taken to develop transformational strategy; later project rescoping, including integrating new academies

Hackney

September 2013

November 2013

Issues around use of untested processes

Haringey

March 2011

October 2011

Issues around use of untested processes

Islington

September 2011

September 2012

Local resourcing difficulties; More time taken to develop transformational strategy

Kingston-upon-Hull

September 2014

September 2014

Lambeth

September 2010

September 2010

Liverpool

September 2010

September 2011

Local resourcing difficulties; More time taken to develop transformational strategy; Issues around use of untested processes; Piloting of non-standard BSF procurement model by local authority has caused some delay

Middlesbrough

September 2011

September 2012

Local resourcing difficulties; changes to procurement strategy to achieve a better value for money outcome caused some delay

Nottingham

December 2010

December 2010

Tower Hamlets

June 2011

December 2011

Local resourcing difficulties; More time taken to develop transformational strategy

Wave 3

Barnsley

September 2011

September 2011

Bradford

August 2010

August 2010

Derbyshire

August 2011

August 2011

Durham

September 2011

September 2011

Kent

April 2011

July 2011

Luton

September 2010

November 2012

Local resourcing difficulties; Issues around identifying new sites for new schools have caused delay to the project

N Lincs

June 2011

April 2012

Local resourcing difficulties; More time taken to develop transformational strategy

Salford

January 2012

September 2012

More time taken to develop transformational strategy

Sandwell

March 2011

July 2011

More time taken to develop transformational strategy

Southwark

November 2014

April 2014

Tameside

January 2011

February 2011

More time taken to develop transformational strategy

Westminster

December 2010

November 2010

Notes:
1. Formal baseline dates were only set for the first wave. Expected completion dates for projects beyond wave 3 are not confirmed until the outline business case is approved.
2. Stoke, a Wave 1 project, is currently reviewing the proposals and timelines put forward in its outline business case following the Children’s Services going into intervention and therefore has not been included as the expected finish date has not been finalised.

Child Minding

Mrs. Maria Miller: To ask the Secretary of State for Children, Schools and Families how many registered childminders there were in each region in each quarter of the last three years. [223747]


6 Oct 2008 : Column 471W

Beverley Hughes: The information requested is shown in the table.


6 Oct 2008 : Column 472W
Number( 1, 2) of registered childminders for children under eight years of age, position at each quarter from 2005/06 to 2008/09, by Government Office Region in England
2005/06 2006/07 2007/08 2008/09

Apr to Jun Jul to Sep Oct to Dec Jan to Mar Apr to Jun Jul to Sep Oct to Dec Jan to Mar Apr to Jun Jul to Sep Oct to Dec Jan to Mar Apr to Jun

England

70,900

71,100

71,500

71,600

71,600

71,200

71,500

69,900

68,300

67,400

65,800

64,600

64,300

North East

3,500

3,500

3,600

3,600

3,600

3,500

3,500

3,500

3,400

3,200

3,200

3,100

3,100

North West England

8,300

8,300

8,300

8,300

8,300

8,200

8,200

8,100

7,800

7,600

7,500

7,400

7,300

Yorkshire and the Humber

6,700

6,700

6,700

6,800

6,800

6,800

6,700

6,500

6,400

6,200

6,100

6,000

5,900

East Midlands

5,900

5,900

5,900

5,900

5,900

5,900

5,900

5,900

5,800

5,700

5,600

5,400

5,400

West Midlands

6,400

6,400

6,300

6,200

6,200

6,300

6,200

6,200

6,000

5,900

5,700

5,600

5,500

East of England

8,500

8,600

8,600

8,500

8,500

8,500

8,500

8,500

8,300

8,200

7,800

7,700

7,700

Inner London

3,500

3,500

3,600

3,600

3,700

3,700

3,800

3,700

3,700

3,700

3,600

3,500

3,500

Outer London

8,000

8,100

8,100

8,200

8,200

8,200

8,200

8,000

7,800

7,800

7,600

7,400

7,400

South East England

13,600

13,500

13,700

13,800

13,700

13,500

13,700

13,200

12,900

12,900

12,700

12,500

12,500

South West England

6,600

6,600

6,700

6,700

6,700

6,600

6,600

6,400

6,200

6,200

6,100

6,000

6,000

(1) Figures have been rounded to the nearest 100.
(2) Data Source: Ofsted