Helping the industry plan for
additional capacity
99. The project-based nature of much construction
activity means that the industry often takes a short-term attitude
when making decisions about capacity investment, and fails to
invest in areas such as training, new technologies, innovative
ways of working or client relations, all of which could raise
productive capacity in the long run.[145]
For example, an apprentice would usually gain experience through
working on several projects over time. However, a small contractor
may not be able to offer sufficient employment security for them
to be able to complete their training. Ultimately, the client
suffers the consequences of this short-termism through higher
tender prices and an end-product delivered through traditional
construction methods, rather than using practices designed to
give them best value.[146]
100. As the largest client to the construction
industry, the public sector could potentially structure its work
to give the sector's supply chains the security to invest in their
capacity. The Construction Confederation told us the industry
has "a great capacity to deliver when it gets engaged early".[147]
Buildoffsite said that engaging as early as possible with suppliers
helps to ensure that the optimum construction techniques are identified
and gives them time to plan for greater investment in manufacturing
capacity and the required skilled resources.[148]
Indeed, this view was echoed by most of the industry's main representative
bodies.[149] In evidence,
the Minister himself also agreed that there is "huge potential
[
] for the public sector in its procurement activity to
be helpful to the industry, and indeed to promote improvement".[150]
101. While the public sector provides the most
stable part of the industry's work in one sense, at the programme
and project level it has often been characterised by volatility
and poorly co-ordinated demand. This partly reflects the political
context in which the public sector operates. That said, ARUP told
us other countries, for example France, generally have a greater
capacity than the UK for the delivery of large infrastructure
projects on time and to budget because of their use of longer-term
investment planning.[151]
In recent years, there has been a growing acknowledgement in the
UK of the importance of early engagement with the construction
sector to help ensure it can deliver the Government's investment
pledges. For example, the spending review system provides an indication
of spending on public sector construction anticipated in the following
three years, as do longer-term planned programmes of expenditure
such as Building Schools for the Future. Elsewhere, Ofwat is setting
out long-term investment plans for the water industry and the
Department for Transport is developing a 30-year national rail
strategy. However, such intentions are inevitably subject to the
perennial uncertainty over longer-term public spending plans.
Statements of policy, such as the commitment for all new homes
to be 'zero carbon' by 2016, also provide information to the construction
sector on the direction of travel of the Building Regulations
and where it should focus its capacity investment.
102. In the area of planning, the Government
is currently introducing a new single system for major infrastructure.
The reforms will include the establishment of National Policy
Statements to inform planning decisions on major projects. They
have the potential to make the consent system for infrastructure
projects more predictable, which could allow the construction
industry to plan more effectively for their delivery, although,
as the Institution of Civil Engineers told us, this would have
to be "accompanied by increased cross-government planning
of construction work flow".[152]
Another change in planning policy, this time at a local level,
has been the introduction of Planning Policy Statement 3 on Housing,
which entered into force in April 2007. This requires local authorities
to identify a rolling five-year forward supply of developable
land sufficient to meet their agreed housing requirements. This
information should help developers to plan for the longer-term,
but house building rates will still depend on the strength of
the housing market.[153]
103. Despite these improvements in the Government's
approach, the construction industry believes it could still do
better. The Construction Products Association (CPA) told us that
while details of government spending plans were useful for the
sector, firms would find it more helpful if these were set out,
for example, in terms of number of schools to be built rather
than overall expenditure levels. The CPA said it is "output
targets, not input spend, which interests us".[154]
In addition, whereas some parts of the public sector have improved
information flow to the construction industry, there are many
other areas where there is still uncertainty and confusion because
the Government either does not collect information on progress
towards a particular target, or does not communicate well when
programmes have been delayed or changed.[155]
104. The CPA produces an annual report which
monitors and assesses the delivery of the Government's plans for
investment in the built environment.[156]
It covers six areas of activitysocial housing, schools,
the NHS estate, roads, the rail network, and wateron which
it scores the Government's performance against its targets and
makes recommendations. In its most recent report the CPA gave
three stars out of a potential five for the public sector's new
build work, but only two stars for its efforts with the existing
building stock. The CBI also highlighted its concern about public
sector procurement delays.[157]
It found on average delays in the procurement process on health
Private Finance Initiative schemes amounted to £2.45 million
on each deal. It also cited findings from the Major Contractors'
Group of average delays of just under eight months for health
projects and seven and a half months for schools. The CBI argued
that such procurement delays are "costly to bidders and the
taxpayer and seriously undermine the drive for value for money
and efficiency in public services".[158]
More generally, the Construction Confederation told us the public
sector needed to be more realistic about the delays that tended
to blight major construction programmes.[159]
What is important is the flow of information to the industry when
such delays or cut-backs are anticipated.
105. Not only is it important for the Government
to establish long-term programmes and communicate progress and
changes to planned delivery, it also needs to have adequate phasing
of projects to ensure a steady flow of work to the industry. This
too will help its supply chains keep together experienced teams
that can move from project to project.[160]
This is also important where the timescales for major infrastructure
projects overlap. For instance, the Royal Institution of Chartered
Surveyors noted the general belief by those in the industry that
the Olympics, Crossrail and the M25 expansion would collectively
need careful co-ordination to avoid spikes in construction price
inflation and delays to delivery schedules.[161]
Yet the Institution of Civil Engineers told us at present "there
is little evidence of serious co-ordination".[162]
In a recent report it argued that the Government needed to provide
greater client leadership to the construction industry on the
demand for infrastructure work. It called for the setting up of
an independent national commission for strategic infrastructure
planning whose role would be to co-ordinate spending programmes
across the public sector and "bring an end to unpredictable,
stop-start procurement".[163]
106. In recent years the public sector has responded
to calls for greater co-ordination of construction activity. A
review by Sir Christopher Kelly in 2003 made recommendations on
the importance of engaging suppliers at an early stage and ways
in which sharing supply and demand information can enable better
planning in the construction industry.[164]
This work is now being led by the Public Sector Construction Clients'
Forum (PSCCF). In 2006 the PSCCF produced a report on construction
demand and capacity. One of its key findings was that, assuming
there would be no restrictions on the use of migrant labour, the
UK would not face any significant general labour capacity constraints
between now and 2012, although there would be shortages in some
specific areas such as project management and design.[165]
The study also produced an econometric model to help government
analyse the impact of different scenarios and therefore inform
investment decisions. The Minister told us he thought the Forum
"does give us the opportunity to improve the flow of information
to the industry [
] about what is coming up".[166]
These developments, combined with the current work of ConstructionSkills
to forecast future skills needs, have the potential to enhance
the construction industry's long-term capacity planning. However,
they are still dependent on the provision of reliable and timely
information on construction demand from the rest of the public
sector.
107. If the construction industry
is to have an incentive to improve its capacity to deliver in
the long run by investing in training and new ways of working,
it requires the security of a long-term flow of work. The public
sector is beginning to acknowledge the role it can play in engaging
early with the construction supply chain. It is setting longer-term
investment programmes for public services, introducing a new approach
to planning, and has clearly committed to 'zero-carbon' homes
by 2016. However, it could still do more to improve the flow of
information to the construction industry, particularly when programmes
are delayed, amended, or abandoned. We believe that there is scope
for greater co-ordination of major construction projects to mitigate
the effects on construction price inflation and to ensure a steady
workflow for the industry, although the industry must recognise
that its health is only one of the factors the public sector has
to take into account. Like any other client, different parts of
the public sector will expect to arrange their construction projects
to meet their own needs.
108. One of the responsibilities
of the Chief Construction Officer should be leading the Public
Sector Construction Clients' Forum's work on capacity planning.
The post-holder should work with departments both to improve the
flow of information on construction programmes, and to advise
on their co-ordination. As the industry's largest single client,
the public sector ultimately benefits from such early engagement.
103