Select Committee on Business and Enterprise Written Evidence


Supplementary memorandum submitted by the Department for Business, Enterprise & Regulatory Reform (BERR)

  I understand the BERR Select Committee Chairman has kindly agreed to consider a paper setting out our proposals to reform the Construction Act, as part of the Committee's inquiry into the construction industry.

  It remains our intention to introduce these measures as soon as Parliamentary time allows. I plan to release draft Bill clauses to the construction industry for comment and I expect to be in a position to do so by early June.

  I look forward to the Committee's report on the construction industry and to the Committee's views on our proposals.

THE EXISTING STRUCTURE OF THE ACT

  1.  The aim of Part II of the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act) is to ensure prompt cash flow through construction supply chains (employer-contractor-sub-contractor) and to encourage swift resolution of disputes. It achieves this by providing a statutory right to refer disputes to adjudication and setting out a payment framework, including the right to be paid by instalments, with which payment provisions in a construction contract must conform.

  2.  When the Act came into force it covered the whole of Great Britain but has now been devolved to the Scottish Parliament. This Construction Act does not apply in Northern Ireland but separate similar legislation was introduced in 1999.

ADJUDICATION

  3.  Section 108 of the Construction Act provides that a party to a construction contract has the right to refer a dispute arising under the contract for adjudication. "Dispute" is defined as including any difference. Subsections 108 (2) to (4) specify the basic framework for adjudication with which such contracts should comply. Section 108(3) states that a contract "shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement." Section 108(5) provides that "if the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply".

  4.  An adjudicator's jurisdiction is derived from his appointment by the agreement of the parties. The adjudicator only has jurisdiction to determine a dispute referred to him arising out of a construction contract. The question whether an adjudicator has the necessary jurisdiction is not itself a dispute arising under the construction contract and any decision of the adjudicator as to his jurisdiction is not binding. An adjudicator must determine the dispute by reference to the contractual terms. Decisions of adjudicators are enforced by way of summary judgement. The courts have taken a robust attitude and will enforce any decision where it is within jurisdiction.

  5.  Section 108 makes no provision in respect of costs of the adjudication.

PAYMENT

  6.  Sections 109-113 set out the payment framework.

    —  Section 109 introduces the right to instalment, stage or periodic payments.

    —  Section 110(1) requires the construction contract to have an adequate mechanism for determining what will become due and when and for the contract to provide a final date for payment in relation to any sum which becomes due.

    —  Section 110(2) requires the payer to give the payee early communication of what will be paid.

    —  Section 111 provides that the payer may not withhold money unless he has communicated in a notice the amount he intends to withhold from the sum due and the grounds for withholding payment to the payee within an agreed period (or no later than the period prescribed in the Scheme). A payment notice under section 110(2) may suffice as a notice of intention to withhold payment so long as it complies with the requirements of section 111.

    —  Section 112 provides that the payee may suspend performance when the amount due is not paid by the final date for payment.

    —  Section 113 prohibits contractual terms which make payment dependent upon the payer being paid.

SECONDARY LEGISLATION: THE SCHEME FOR CONSTRUCTION CONTRACTS (ENGLAND AND WALES) REGULATIONS 1998

  7.  Section 114 of the Act empowers the Minister to make by regulations a "Scheme" containing provisions about the matters referred to in the preceding provisions of Part II of the Act. Section 114(4) provides that where any provisions of the Scheme apply in default of contractual provisions agreed by the parties they have effect as implied terms of the contract. The Scheme for Construction Contracts (England and Wales) Regulations 1998 is secondary legislation.

  8.  The Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) came into force on 1 May 1998. In respect of Scotland, the Scheme is found at the Scheme for Construction Contracts (Scotland) Regulations 1998 (SI 1998 No. 687). The Scheme will apply where the construction contract does not provide for any of the matters set out in sections 108(2), (3) and (4) (provisions relating to the right to refer disputes to adjudication), sections 109(1) and (2) (entitlement to stage payments), section 110 (1) (adequate mechanism for the determination of what and when payments become due) and section 110(2) (the requirement for a payer to give a payment notice).

  9.  As a consequence of the amendments we will be making to the primary legislation, there will need to be some consequential amendments to the secondary legislation. The Welsh Assembly now has devolved responsibility for the secondary legislation in Wales. There is already separate secondary legislation for Scotland. For both Wales and Scotland, the respective administrations will be required to conduct their own consultation on secondary legislation.

BERR'S PROPOSED AMENDMENTS

  10.  Our proposed new provisions would:

    a.  Remove the requirement for the construction contract to be in writing.

    b.  Introduce a statutory framework for costs of the adjudication.

    c.  Prohibit agreements that interim or stage payment decisions will be conclusive.

    d.  Introduce greater certainty and clarity into the payment framework.

    e.  Limit the decision of the House of Lords in Melville Dundas v Wimpey to insolvency situations.

    f.  Improve the right to suspend performance.

ADJUDICATION

"In writing"

  11.  Our proposed new provisions remove the restriction of the application of the Act to contracts in writing. The Act will apply to contracts which are agreed wholly in writing, only partly in writing, entirely orally or are varied by oral agreement.

  12.  The policy objective is twofold:

    —  to allow more disputes under construction contracts to be referred to adjudication; and

    —  once the adjudication is underway, to remove the potential for one of the parties to challenge the adjudicator's jurisdiction on the grounds that the entire contract is not in writing.

  13.  The adjudication scheme will continue to be in writing. Where there is no written contractual adjudication scheme, the statutory scheme (which is set out in secondary legislation) will apply. The reason for this is that we believe it is important that there is absolute clarity about the procedure under which the adjudication is being carried out.

  14.  The notices set out in the statutory payment framework (payment notice, withholding notice and notice of intent to suspend performance) will continue to be required in writing. This is to help ensure clarity of communication.

  Stakeholders—This is seen as one of the two most important amendments we are making to the Construction Act. Adjudicators, professionals, sub-contractors are strongly in favour. Contractors are against. Some of the sub-contracting bodies would prefer it if we went further and allowed the adjudicator to decide, finally and conclusively, whether or not he had jurisdiction. We believe it is right to retain the ability to question an adjudicator's jurisdiction.

Statutory framework for the costs of Adjudication

  15.  The Construction Act currently makes no provision on the costs of adjudication. It is left as a matter for contract. The contract may provide that one of the parties is to bear all or part of the costs of the adjudication regardless of the outcome. Often such clauses are included at the behest and to the advantage of the party in the strongest bargaining position. This can be used to create a disincentive for a party to refer disputes to adjudication.

  16.  Our policy objective is therefore to:

    —  remove these disincentives.

  17.  However, at the point of referring a dispute to adjudication, the ability of a party to exercise commercial muscle has greatly diminished—the objective of the "inferior" party has changed from winning the work to getting paid. We therefore enable the parties to make any agreement they see fit after they have referred the dispute to the adjudicator.

  18.  In broad policy terms this is a relatively simple proposition. We are simply reinstating the parties' ability to make an agreement. There is however some legal complexity.

  19.  There are two types of costs in issue: the costs of a party (which typically will include the fees of others whom a party has engaged eg a quantity surveyor or an architect) and then the fees and expenses of the adjudicator. These require different treatment.

  The costs of the parties:

  20.  We are prohibiting any provision of a construction contract which would have the effect of requiring a party to the contract to pay all or any part of the adjudication costs of another party, unless it is made in writing after the appointment of the adjudicator.

  21.  The underlying legal position, if the parties do not reach agreement in writing after the appointment of the adjudicator, is that each party should bear their own costs. Where the parties have entered into an effective agreement that one party should bear all, or a proportion of the others costs, we give the adjudicator the power to disallow any unreasonable costs within the agreement.

  The costs of the adjudicator (the fees or expenses of an adjudicator in relation to the adjudication of a dispute arising under the contract):

  22.  As above, we prohibit any provision of a construction contract, which would have the effect of requiring a party to the contract to pay all or any part of the adjudicator's costs unless it is made in writing after the appointment of the adjudicator.

  23.  The underlying position is that responsibility for an adjudicator's fees and expenses will be determined by the terms of the contract which he agrees with one or both of the parties to the construction contract. Normally the adjudicator's contract will be with the party which refers the dispute to the adjudicator. Our new provisions make the parties jointly and severally liable for the adjudicator's fees for work reasonable undertaken and expenses reasonable incurred by him.

  Stakeholders—There is almost universal support for our proposal to make ineffective any contractual clause on the allocation of the costs of adjudication. Some bodies—notably those representing sub-contractors—would prefer our prohibition to be total. Others—in particular those representing main contractors—believe our proposals strike the right balance between preventing mischief and giving the parties freedom to enter into sensible commercial arrangements.

Prohibiting agreements that interim or stage payment decisions will be conclusive

  24.  A contractual practice is emerging in the industry where a decision about the amount of an interim payment can be made final and conclusive—and therefore unadjudicable. Some in the industry have suggested that this practice will increase as we tighten up other aspects of the Act. Our policy objective is simply to close the loophole and ensure that all disputes on interim payments can be put to adjudication.

  25.  We are therefore prohibiting agreements that a decision can be conclusive of the amount of a stage payment. This prohibition will not apply where agreement has been reached after the decision has been taken and communicated to the parties.

  Stakeholders—There was strong support for prohibiting final and conclusive agreements. Contrary views, such that there were, tended to favour a time limited period in which all decisions (ie including those on final payments) could be opened up and reviewed by and adjudicator.

PAYMENT FRAMEWORK

  26.  Our introduction sets out the existing statutory payment framework. The main issues uncovered over the course of the review were:

    —  The payment notice (early notification of the amount due) was frequently not issued and there was no sanction.

    —  There was a lack of clarity about the status of the payment notice.

    —  The interaction between the payment notice and withholding notice could be unclear.

    —  That "pay-when-certified" clauses could be used to circumvent the prohibition of pay-when-paid clauses.

  27.  The conclusion of our analysis of the consultation responses is these factors, individually or collectively, can make the statutory payment framework ineffective in its intention to introduce greater certainty about what will be paid and when.

  28.  Our policy objectives are therefore to:

    —  remove the statutory restrictions about which party can issue payment notices.

    —  Ensure that there is always early communication of the sum due.

    —  clarify the status of the payment notice.

    —  clarify the interaction between the payment and withholding notices.

    —  prohibit pay when certified clauses.

  29.  As a package, these amendments introduce much greater clarity and simplicity into the payment framework and its underlying interaction with common law.

Notices

  30.  Under the current framework the payer is obliged to issue the payment notice. Comment during the review was that this could run counter to common commercial practice. The underlying policy objective behind introducing the payment notice requirement in the first place was to ensure there was early communication of the amount to be paid. The notice enables early discussion of any differences with the hope that they will be resolved before the payment date. We are therefore retaining the requirement for a payment notice but removing the limitations on who can issue it. Who is responsible for issuing the notice (payer, payee or third party certifier eg architect or engineer) will be a matter for the parties to agree in their contract.

  31.  We also make it clear that the amount in the payment notice is the "sum due" for the purposes of withholding and suspension. This removes some uncertainty which had crept in under the current framework about various deductions and whether they should be communicated through the notices. For instance, you are required to issue a withholding notice when withholding money from the sum due but if the money was never due in the first place (perhaps because it was unsatisfactory) you would not need to notify it in a withholding notice.

  Stakeholders—As you would expect, this proposal is the one where opinions are sharply divided. It is also viewed by many as being one of the two key things we are proposing. Some (generally main contractors) are opposed to any changes at all to the payment framework. Others (generally sub contractors) would rather our proposals went much further. In short they want the payee's application for payment to set out the sum due. Broad consensus is at the heart of the Construction Act and our provisions therefore seek a middle path between these two views. Those with less of a direct interest in the main contractor sub contractor interface (professionals and adjudicators) tend to think our proposals strike a sensible balance between interests.

Statutory fallback provision

  32.  One of the weaknesses of the current framework is that there is nothing to ensure the payment notice is issued. There is no remedy when it is not served. We have therefore introduced a "fall back" provision. Where the contract makes provision for the payer or third party to issue a payment notice to the payee before the final date for payment and he fails to do so the payee may at any time before the final date for payment give a notice to the payer specifying the amount of the payment he considers to be due and the basis on which that amount is calculated. The amount in that notice will then become the sum due for the purposes of withholding and suspension.

  Stakeholders—This measure is popular with sub-contractors though some feel it does not go far enough. It is deeply unpopular with main contractors who object to the amount in the notice becoming the sum due. However, it is clear that the lack of an effective remedy when a payment notice is not issued fundamentally undermines the effectiveness of the Act.

Payment by reference to other contracts

  33.  We are prohibiting so called "pay-when-certified" clauses. The content and timing of a certificate issued under a superior contract may simply be invisible to those under an inferior contract yet the amount and timing of payment could be dependent on it.

  34.  The policy objective is to:

    —  ensure there is more clarity about when payments become due as well as what the sum due is.

  35.  We are therefore simply stating that a contract does not have an adequate payment mechanism where payment is conditional on:

    (a)  the performance of obligation under another contract, or

    (b)  a decision by any person as to whether obligations under another contract have been performed.

  Stakeholders—Sub contractors broadly welcome this proposal though some would like us to go further and outlaw all "conditional" clauses. Main contractors do not like the proposal as it reduces their ability to offset the risk of non payment by their customer. The original act was clear in its intent to outlaw pay-when paid clauses.

Melville Dundas

  36.  The judgement of the House of Lords in Melville Dundas vs George Wimpey raised two areas of uncertainty:

    (i)  whether the Construction Act provisions on withholding (section 111) applied only where the contract is determined (ie terminated) in cases of insolvency; and

    (ii)  whether the provisions should apply to all other grounds for withholding in respect of final payments.

  37.  In terms of the HoL judgment in the Dundas case, our policy objective is:

    —  to ensure that a withholding notice is required where the payer intends to pay less than the "sum due" except in cases of insolvency.

  38.  This limits the effects of the HoL decision to the facts of the case (in Dundas, the contract was determined upon the appointment of an administrative receiver) and prevents the payer from relying on any other ground which gives rise to a lawful right to withhold payment.

  39.  We are therefore introducing an additional subsection which provides that the only circumstances in which a withholding notice is not necessary, where the payer intends to pay less than the sum due, is where:

    a)  the contract provides that the payer may determine the contract upon the insolvency of the payee;

    b)  the payee is insolvent; and

    c)  the insolvency occurred after the expiry of the prescribed period for giving a section 111 notice;

    d)  it was not possible for the payer to give the notice before the expiry of the prescribed period.

  Stakeholders—The consultation responses supported our position.

IMPROVING THE RIGHT TO SUSPEND PERFORMANCE

  40.  We are improving (ie making more equitable) the right of a party to suspend performance of his obligations under a construction contract where he has not been paid. We are therefore providing:

    a)  that the payee need not suspend all of his obligations when exercising the right;

    b)  a statutory right for the suspending party to be compensated for reasonable losses caused by the suspension; and

    c)  an extension of time in the contractual time limits for any delay caused by the exercise of the right to suspend.

  41.  The policy objective is to ensure the costs of suspension fall more equitably.

  Stakeholders—There was strong and consistent support from almost everyone for this proposal.

2 May 2008





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 16 July 2008