Select Committee on Business and Enterprise Written Evidence


Supplementary evidence submitted by the NSCC

SELECT COMMITTEE INQUIRY INTO THE CONSTRUCTION INDUSTRY

1.  CLIENT DRIVERS FOR USING INTEGRATED SUPPLY CHAINS

Q354 Mr Weir:   It does not sound to me like there is an awful lot of drivers for anybody to actually push this forward in any way, the contractors or the clients, from your explanations

  The majority of clients do not understand that the industry operates in such a fragmented manner and they presume that when talking to their preferred main contractor that he will bring a "team" with him and will advise his client on issues such as a project bank account if they were appropriate. This does not happen as the tier 1 or main contractor (for reasons outlined during our evidence session) has his own reasons for not implementing an integrated team and a project bank account does not benefit him directly he is unlikely to recommend is use.

  We believe that as the majority of clients are unaware of how beneficial a transparent payment process is and that by reducing disputes over payments which ultimately lead to delays, overruns in programme and budget, they and their project will benefit.

  Essentially if clients really want their project to meet their expectations in terms of quality, performance and construction programme, they need to ensure that members of the supply chain (those that actually build the project) are paid for the work carried out when they should be. Many clients do not recognise that it is the supply chain that carries out the actual construction work, are not made aware of this by their main contractor and are not equipped to, or have no wish to, get involved in supply chain management.

  However, the implementation of a project bank account is a good way for the client to facilitate a fair payment procedure. Payments are transparent which means it can easily be seen if a particular contractor has been paid for his work or if the fact that he has not been paid is actually causing a delay or dispute. The real issue is that the industry has not yet demonstrated visibly to clients that by establishing a project bank account the client is better able to manage their project. This work is in progress and we are confident that the very real and tangible savings realised by the use of project bank accounts will be demonstrated, showing that they result in a better value project which is on programme and on budget.

  Some case studies of how poor integration can lead to problems are detailed below.

Case Study 1—Incomplete design

  A main contractor took on a project at a guaranteed maximum price (GMP) with an incomplete design and proceeded to subcontract out the specialist work packages on a similar basis.

  The piling contractor gave a GMP based on a fixed scope of work. The piling contractor then prepared the foundations design based on building loads provided by the Consulting Engineer but was unable to get value engineering proposals agreed through lack of time.

  One week into the piling work construction drawings were issued by the Consulting Engineer which showed a 30% increase in the loading of the building. The piling contractors GMP was no longer applicable as the design had changed requiring an increase in materials and labour leading to a cost escalation of 30% in the piling package and a substantial increase in programme as the work would now take longer.

  As a result of design changes across the project similar increases affected the majority of the specialist trade contractors on the job with varying implications depending upon the work to be carried out.

  The piling contract was originally £7.5 million; a 30% increase is £2.5 million. Now multiply that across the project and add in the increased programme time required in all areas . . . . . .

Case Study 2—Misunderstanding of Specification and Prices

  A steelwork/cladding contractor tendered for a contract to erect the steelwork and fix the cladding. The total package was priced at £150,000. The client looked at the two elements of work separately and compared the price to other tenders submitted. The client liked the cladding price from the original contractor but thought the steelwork package too expensive so he let the packages separately.

  The steelwork was erected by another contactor who completed his work and handed it over to the main contractor. The cladding contractor arrived on site to fix the cladding and asked when the purlins for fixing the cladding to would be attached to the steelwork.

  The client in his drive for lowest cost had compared the steel and cladding contractor price for the steelwork with other tenders without looking at the specification or asking some critical questions. The original £150,000 quoted was for the complete package with the purlins included in the steelwork. The other tendering contractors had quoted for stand alone steelwork with no purlins, so their prices, when compared, were lower.

  The purlins had to be retro-fitted to the now erected steelwork resulting in the steelwork and cladding costing in excess of the original £150,000 quoted. In addition the work:

    —  exposed workers to unnecessary work at height;

    —  required welding on site;

    —  increased the programme time;

    —  gave a lower quality finish making the fixing of the cladding more difficult and time consuming;

    —  incurred storage costs of the cladding; and

    —  increased the impact on the environment as the cladding was transported to two different locations rather than straight to site.

  Understanding the tender pricing at the beginning would have eliminated all of these extra risks; at the very least holding a meeting between the appointed steelwork and cladding contractors would have identified the missing purlins up front and the problem solved at design stage eliminating the extra risks and costs incurred.

Case Study 3—Attempting to Cut Costs

  A contractor was requested to lay expensive terazzo flooring and as part of the specification the terrazzo contractor required 150mm depth of isocrete on which to lay the terrazzo. Another contractor was appointed by the main contractor to provide the isocrete; no interface between these two contractors was facilitated.

  Shortly after the terazzo was laid it began to "fail". Water began to seep through the terrazzo and pushing up the joints causing an uneven floor surface. The specialist terrazzo contractor was called back to site and investigated the reasons for the floor failures. They appointed an independent surveyor to take core drilling samples of the floor. The main contractor stated that 40mm core samples would be sufficient but the terrazzo contractor requested 150mm core samples. The samples showed only 40mm of isocrete and then 90mm of latex underneath and not the 150mm isocrete that was within the terrazzo contractor's specification.

  Further investigations identified that the main contractor had changed the specification to save money without understanding the implication of amending the specification and without consulting the terrazzo contractor. The expensive terrazzo had to be lifted, the 40mm isocrete and 90mm latex removed and the complete job redone.

Case Study 4—Ignoring Specialist Advice

  A major infrastructure client required over 1 million m2 of tiling and spent substantial sums on identifying the tiles they wished to use. The design team selected and then specified the tiles to use on the entire project. The tiles were expensive, £90/m2 and made by hand using an "old fashioned" method.

  A number of specialist tiling contractors were approached for the project as it was a "big job". On learning of the tiles specified the majority of the contractors said they were unsuitable for the purpose, would not fix effectively to the curved surface as required and would not be suitable for the wear and tear likely to be experienced. The client and architect chose to ignore the advice given by the specialist tiling contractors and retained the specification of the selected tiles.

  The contractors fixing the tiles raised the same problems with the main contractor and the client stating that they were not fit for purpose. The contractors were instructed to continue with the selected tiles. The tiles continued to fail and the client and architect are now reviewing their continued usage for the remainder of the project and it may be necessary to remove all the tiles already fixed.

2.  RETENTIONS

  Q367 to Q374 relate to the issue of retentions and a number of responses were made which are not quite correct in respect of NSCC Specialist Contractors.

  In many cases NSCC Specialist Contractors do not employ sub-contractors so any withheld retention and the cost of financing that retention is actually borne by them; there is no one to pass it on to (and if there is they are likely to be even smaller SME's that are even less able to bear the cost). This means that it is the contractors that NSCC represents that have the 2.5%-5% retention withheld from them for a period of up to one year after the project completion date.

  In order to demonstrate our commitment to the removal of retentions, the JCT (Joint Contracts Tribunal) sub sub-contract (the only contract which NSCC can change without agreement of main contractors) does not contain a retentions clause.

3.  IMPLEMENTATION OF CSCS

  At paragraph 5c(e) the NSCC evidence states: The NSCC is working towards achieving a fully qualified workforce by 2010. Clients in the public and private sectors have committed to using contractors that hold CSCS carded workforces, yet this is still not happening in practice, which is causing consternation amongst the Specialist Contractors that have invested in qualifying their workforces.

  Q367 to Q374 are questions from Mr Lindsay Hoyle MP on this statement and the following is relevant supplementary information.

    —  The number of CSCS cards obtained by workers is constantly increasing with over one million CSCS cards issued to date.

    —  Specialist contracting companies are committed to obtaining CSCS cards for their workforce and many now have a fully carded workforce.

    —  Members of the Major Contractors Group (MCG) have publicly committed to a fully qualified workforce and regularly carry out audits on their sites.

    —  The Office of Government Commerce (OGC) has published common minimum standards which state: Clients are to include a contract clause requiring that all members of their supply teams who are workers on or regular visitors to a construction site are registered on the Construction Skills Certification Scheme (CSCS) or are able to prove competence in some other appropriate way.

  All of this clearly demonstrates a commitment from all parts of the industry to CSCS.

  However, the commitments made by some clients and contractors are not actually being followed through. Contractors that have not committed to CSCS, or are not obtaining CSCS cards are still invited to tender for projects, and are then awarded contracts on private and public sector funded projects. Workers are allowed onto sites without a CSCS card or with inappropriate cards (ie a card that does not reflect their actual occupation) even where it is a contractual requirement for all workers to hold CSCS cards. This frustrates Specialist Contractors that have expended (often substantial) resources to achieve a qualified workforce when they see contracts awarded to `lowest price' contractors that do not meet the stated criteria ie a CSCS carded workforce.

15 January 2008





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 16 July 2008