Supplementary memorandum submitted by
Specialist Engineering Contractors' Group
INTRODUCTION
The Specialist Engineering Contractors' (SEC)
Group forwarded its submission to the Trade & Industry Committee's
inquiry into the UK construction industry on 16 May 2007. This
paper provides additional explanation for the issues raised in
that submission and is updated to include matters which have arisen
since.
At the end of each section we have distilled
the issues to provide some focus for the Committee's deliberations
and, to help the evidence-gathering process, we have also listed
questions that could be asked of witnesses. Against the suggested
questions we have identified the government departments to whom
the questions could be put.
As in our submission the overriding theme of
this paper is that the industry remains bedevilled by poor and
outdated practices that hold it back from becoming a modern and
efficient industry, having more in common with the 20th century
than the 21st century. As a consequence many investors still give
the industry a wide berth. It continues to struggle to attract
high calibre professionals within the fields of engineering and
project management. Above all else traditional procurement and
delivery processes are wasteful and inefficient. This, in turn,
has an adverse impact upon capacity and productivity.
The key issues which need to be addressed are:
1. We should now put in place "drivers"
to achieve greater integration of the delivery process especially
the early involvement of the supply chain as part of the design
team.
2. Action is now needed in the areas of payment,
insurance and contracts to remove barriers to integrated teamworking
as well as to facilitate it.
3. The Construction Act requires amendment
to strengthen its payment and adjudication provisions to reflect
the intention of Parliament when passing the Act. Such amendment,
therefore, should enhance payment certainty and ensure that adjudication
continues to be inexpensive and accessible.
4. In order to promote a sustainable industry
that delivers value for money, public sector procurers should
insist that only competent firms are engaged on public sector
works (whether as contractors or sub-contractors). However, we
need to have in place a means for recognising competence (which
are acceptable to procurers) whilst, at the same time, rationalising
competence schemes and reducing the burden on SMEs of myriad third
party vetting processes.
5. Public sector procurers should be more
proactive in improving the treatment of SMEs engaged on public
sector works contracts.
In each section we have listed recommendations
which we believe, if taken up by the Select Committee, will help
create a sustainable industry in which the potential of all firms
in the industryespecially SMEsis exclusively engaged
in delivering improved value to customers. As a result the industry
will be better placed to improve upon its current low levels of
profitability.
We wish to commend the (now re-named) Business,
Enterprise & Regulatory Reform (BERR) Committee for its decision
to launch this inquiry and look forward to assisting the Committee
in its work.
1. CREATING A
MODERN AND
EFFICIENT INDUSTRY
Background
1.1 Construction works are traditionally
procured by engaging architects and engineers to carry out the
design which is then put out to competitive tender to main contractors.
Tendering main contractors will, in turn, invite bids from sub-contractors
who may also invite bids from sub-sub-contractors and suppliers.
Main contractors will, then, submit lump sum bids.
1.2 Sub-contractors and suppliers will be specialist
contractors such as foundations specialists, cladding and structural
steelwork contractors, engineering services contractors and fit-out
specialists. Over 85% of the value of the industry's output is
delivered by such specialists together with their suppliers and
manufacturers. This includes a significant amount of design work
as well as construction or installation works. They are also responsible
for the repair and maintenance of the delivered product.
1.3 But, as the supply chain, they have
little or no influence over the procurement process especially
the initial decisions affecting the planning of the project, the
design, the management of the risks involved and the costs. It
is these decisions which will determine whether the completed
building or structure will represent value for money. This factor
alone represents the major fault line in the delivery of construction
works in the UK.
1.4 The traditional delivery process is
fragmented and disintegrated. There is very little (if any) dialogue
on design solutions between architects, consulting engineers and
key specialist contractors such as engineering contractors, the
latter often carrying out a substantial amount of design work.
1.5 Specialist contractors and suppliers
are frequently having to convert design concepts into practical
and coordinated design solutions whilst at the same time absorbing
most of the risks associated with the delivery process (including
any shortcomings in the design they have inherited). As a result
out-turn costs are usually much higher than the initial lump sum
bid.
1.6 The diagram below shows the traditional
procurement process:
 |
Customer: with help of consultants/lawyers develops project/design brief for tendering on lump sum – but
design usually incomplete.
Main Contractor: Manages construction delivery; usually under-capitalised and needs cash from customer to pay
sub-contractors
Sub-Contractors: Specialist contractors that deliver the bulk of the detailed design and construction and absorb
most risk (eg. original design not working)
|
Traditional Procurement: Key Features
— Poor communication
— All risk transferred along supply chain
— Adversarial relationships and disputes
— Lowest price
— Retentions
|
— No integrated working—everybody operates within “silos”
— Hierarchical & sequential appointments
— Many interfaces
— IneYcient delivery (eg re-design and re-work)
— Out-turn cost exceeds original budget (sometimes many times over)
|
TRADITIONAL PROCUREMENT - THE COST OF FRAGMENTED DELIVERY |
The bulk of Wembley (in terms of value) was designed and built by specialist contractors; eg. foundations, steel structured, engineering services and fitting out. They had no say in the early design decisions and cost plan |
 |
|
* Not including the cost of myriad disputes, adjudications and court cases! |
1.7 There are other consequences of having
a fragmented delivery process:
(a) Planning and design decisions often overlook
health and safety issues arising in the construction (or production)
process.
"Of all fatal accidents on construction
sites, as many as 60% can probably be attributed to choices made
before the work on site began."
Foresight Consultation Document
Published by DTI, August 2000
(b) Sustainable construction becomes impossible;
there is much waste:
a delivery process based upon hierarchical
and sequential appointments generates needless transaction costs.
a focus on lump sum, lowest price
tendering ignores whole-life costs, eg. maintenance and energy
consumption over the lifetime of the building or structure.
there is a large amount of waste
arising from duplication at all the different levels of delivery.
waste also arises through much re-design
and re-work.
(c) Above all else quality suffers. This
is largely due to:
i. the initial design solutions not being
"bought into" or "owned" by those delivering
the product;
ii. a combination of the lowest price culture
and ease of entry into the industry which deter reputable and
established firms from investing in training and technology;
iii. too many interfaces;
iv. firms (particularly SMEs) absorbing a
disproportionate amount of risk.
"Many construction problems are caused by
poor design because designers often have insufficient information
about the performance of the product in use. Design-based defects
are a major cause of customer dissatisfaction . . . because of
the complexity of modern buildings, rising expectations of building
performance are exposing the inadequacy of traditional design
approaches."
1.8 In 1998 the [then] Deputy Prime Minister
appointed Sir John Egan to chair a Construction Task Force to
consider the scope for improving construction efficiency. Sir
John's key recommendation was that the industry must integrate
its delivery processes to remove waste and, thus, provide added
value to customers. Sir John further recommended that the public
sector should take a lead in bringing about the necessary change.
Traditional procurementthe cost of
fragmented delivery
Construction Defects and their Causes
1. Unclear / missing project informationpoor
communication
4. No co-ordination of design
6. Designer not understanding materials
"Quality Control on
Building Sites": 1981 Building Research Establishment Study
of
27 building sites involving
public sector projects valued between £100k and £12m
Integrated Delivery
1.9 What is integration? It is the bringing
together of all the processes involved in construction deliveryespecially
design and constructioninto a seamless whole. This involves
a flatter delivery structure with greater collaboration between
the delivery teamconsultants, project managers, specialist
contractors, facilities managers and suppliers. The focus is on
identifying the customer's requirements or value criteria (relating
to matters such as functionality and usage) and the appointment
of the team best suited to deliver against such criteria. Needless
to say, the team should be appointed and actively involved at
the outset of the procurement process to agree the design solutions,
cost plan and risk allocation before construction begins.
"The most successful enterprises do not
fragment their operationsthey work back from the customers'
needs and focus on the product and the value it delivers to the
customer."
Rethinking Construction:
Sir John Egan, 1998
1.10 The public sector responded to Egan's
challenge with the launch of the Achieving Excellence programme
in March 1999. This became a five year programme to overhaul construction
procurement by government clients. The Office of Government Commerce
(OGC) was given responsibility for implementing the programme.
In it's Procurement Guide 6, the OGC stated: "An integrated
project team should be appointed to carry out the project."

1.11 Government clients responded enthusiastically
to Achieving Excellence. Procuring staff were trained to become
better informed about construction; new procurement strategies
were introduced in an effort to engage the supply chain in key
decisions affecting planning and design. There was a clear commitment
to move from the lowest price syndrome to best value comprising
whole life cost.

1.12 But, unfortunately, bad practice has
become difficult to dislodge. In its 2005 report, Improving Public
Services through better construction, the NAO concluded that government
clients still had much more to do to involve the supply chain
(ie. the delivery team) in the key decisions affecting project
outcomes. Alongside other best practice measures such involvement
would help contribute towards overall annual savings of £2.6
billion.
1.13 The NAO's view was echoed in our own
survey in 2005. This was a survey of specialist engineering contractorsoften
delivering up to 50% of the value of the projectwhich had
worked on government projects. The results were very disappointing.
Very few firms had been involved on a regular basis in the early
design decisions or had been part of partnering or collaborative
working arrangements. Consequently, progress in achieving integrated
delivery has been slow and patchy despite a growing accumulation
of evidence of the benefits of integration.


1.14 In 2002 Sir John Egan launched Accelerating
Change which identified measures to drive and facilitate integrated
delivery. This report set a target of 50% of construction projects
(by value) to be undertaken by integrated project teams by the
end of 2007. We are nowhere near meeting this target!
We should now put in place "Drivers"
to achieve greater integration of the delivery process especially
the early involvement of the supply chain as part of the design
team.
Our Recommendations
1.15 A very effective driver would be to
make funding conditional on delivery by integrated project teams.
This can be introduced progressively. This was supported in Accelerating
Change (referred to at paragraph 1.14) which was endorsed by the
[then] Department of Trade & Industry.
Consitionality of funding
"It is important that the public sector
demonstrates that it is a best practice client which consistently
secures the best whole life performance that the construction
industry can offer. The public sector can be helped to achieve
this by ... linking government funding of construction projects
to the application of `Rethinking Construction' principles."
(Para.4.10 Accelerating Change:
Sept 2002)
Further support for such conditionality of funding
was implicit in the 2005 NAO report "Improving Public Services
through better construction".
Conditionality of funding
"... despite all departments' formal committment
to embedding the principles of Achieving Excellence as a matter
of Government Policy, public funding for construction is not always
conditional nor does it contain the right incentives to embed
the principles of the Achieving Excellence methodology."
(para.2.29 Improving Public
Service through better construction: NAO 2005)
1.16 The Housing Corporation is now making
funding of housing association construction works conditional
upon compliance with the 2012 Construction Commitments. The Commitmentslaunched
last year by the Secretary of State for Culture, Media & Sportare
best practice requirements for Olympic construction but they are
now regarded by the OGC as generally applicable to public sector
works.
1.17 An alternative approach is to make
funding conditional upon evidence of compliance with the OGC's
Common Minimum Standards. They are a list of key minimum procurement
standards that are mandatory across central government departments
and executive agencies (including the non-departmental public
bodies for which they are responsible). The first and "General
Standard" refers to adherence to the OGC's "Achieving
Excellence in Construction" initiative. This has as its overall
theme the procurement of integrated project teams involving all
the key suppliers at the outset.
1.18 Three further measures are suggested:
(a) A "champion" to promote integrated
project teams on public sector construction
It is suggested that Treasury appoint a high
profile individual from the private sector to champion project
team integration. Such person could compliment the work of OGC
in creating an understanding of the benefits of integration amongst
public sector clients. The appointed person could also monitor
progress, identify barriers to progress and help in providing
solutions to overcome them.
(b) The best value review process for local
authorities should assess their progress in procuring construction
through the use of integrated project teams.
This should not be used as a "stick to beat"
local authorities but rather as a means of encouraging local authorities
to recognise that procuring construction works in this way is
far more likely to achieve best value. This will also help to
identify local authorities which are in need of support in making
the necessary progress.
(c) In conjunction with the Regional Development
Agencies (RDAs) and Constructing Excellence BERR should establish
a network of independent construction advisers (or "integration
facilitators") to assist customers on sourcing, assembling
or appointing integrated project teams.
About 95% of the construction industry's customers
are one-off or occasional clients. The RDAs (working with Constructing
Excellence, a best practice body) are best placed to identify
construction professionals who can help customers develop their
strategic briefs (listing their user requirements) and put together
the appropriate team. The adviser or facilitator would not have
a direct participation in the delivery process and, in this sense,
would be akin to an independent financial adviser.
Questions
1.19 (a) At the heart of the Achieving Excellence
programme launched in March 1999 was a commitment to procuring
construction projects through integrated project teams. What progress
has been made? [Treasury/OGC]
(b) In view of the fact that Accelerating
Change in 2002 and, more recently, the NAO have favoured making
funding conditional on the use of integrated project teams, what
steps have the Government taken (as the leading public sector
client) to bring this about or what steps (if any) does it intend
to take? [Treasury/OGC]
(c) Would the Government have any difficulties
linking funding to compliance with the 2012 Commitments or the
Common Minimum Standards? [Treasury/OGC]
(d) What, if any, lead-in time would be
required before conditionality of funding can be put in place?
[Treasury/OGC]
(e) What options are there for driving integrated
procurement and delivery across government construction bearing
in mind that progress, to date, has been very slow? [Treasury/OGC]
(f) Will the Treasury appoint a high profile
"Champion" to drive integrated procurement and delivery
in the public sector? [Treasury/OGC]
(g) As part of the best value review process,
would you support district auditors progressively insisting on
the use of integrated project teams to deliver local government
construction? [BERR/DCLG]
(h) Would you agree to the Regional Development
Agencies (working with Constructing Excellence) establishing a
network of independent construction advisers to assist customers
on sourcing or assembling and appointing integrated project teams?
[BERR]
SUMMARY OF SEC GROUP'S RECOMMENDATIONS
1.A | The Treasury to progressively make funding of government projects conditional upon evidence of compliance with the OGC's Common Minimum Standards or with the 2012 Construction Commitments.
|
1.B | The Government to appoint a high profile "Champion" to drive the integration agenda.
|
1.C | The Audit Commission (and Audit Scotland, the Wales Audit Office, Audit Office Northern Ireland) to insist that evidence of integration and collaborative working be a major part of the best value review process.
|
1.D | BERR should invite the Regional Development Agencies (working with Constructing Excellence) to establish a network of independent construction advisers (or "integration facilitators") to guide and assist customers on sourcing, assembling and appointing integrated project teams.
|
2. PUTTING IN
PLACE MEASURES
TO FACILITATE
TEAMWORKING ON
PROJECTS
2.1 Since close collaboration within the delivery team
is vital if we are to achieve value for money delivery, measures
should be in place to facilitate such collaboration. We consider
that the following measures are necessary for successful teamworking:
(a) project bank accounts;
(b) collaborative contracts;
(d) phasing out the practice of retentions on public sector
projects.
Together these measures, if implemented, would provide the
necessary degree of trust and align the behaviours of team members
which are crucial for genuine and, therefore, successful collaboration.
Project Bank Accounts
2.2 Generally payment for the supply chain has to pass
through many "pockets". Along the way its passage is
often impeded; those that have the cash have an immediate incentive
to produce excuses for holding on to it before releasing payments
to the supply chain.
2.3 The majority of the major UK contractors are under-capitalised
but, nonetheless, "farmout" most of their work to sub-contractors
and suppliers. They do not have the means to pay their supply
chains until they have been put in funds by the customer. In the
meantime they depend upon their supply chains to finance the works.
Moreover, many developer clients are "shell" companies
without assets and, therefore, are simply conduits for transferring
onwards the cash received from their funders or investors. Special
Purpose Vehicles specifically set up for procuring construction
works as part of PFI/PPP projects are in a similar position.
2.4 The UK construction industry, therefore, continues
to be funded "bottom-upwards" which is inefficient.
Furthermore the supply chain is at constant risk of insolvencies
further along the chain without an effective means of accommodating
this risk. Consequently, the costs of UK construction are substantially
enhanced by poor payment practices which include:
(a) multi-layered payment systems;
(b) payment abuse and disputes;
(c) making payments conditional on factors arising under
other contracts; and
(d) lengthy payment periods.

Poor payment practices are a major barrier to teamworking.
[The subject of payment is also raised in the next section on
the review of the Construction Act.]
2.5 The NAO recommended that public sector procurers
should consider project bank accounts. This was supported in the
2012 Construction Commitments and recently endorsed by the Public
Sector Construction Clients' Forum which (through the OGC) has
published guidance and documentation for operating project bank
accounts. The guidance advises that project bank accounts (together
with a new Fair Payment Charter) will produce significant savings
for the public sector purse. It recommends that public sector
clients progressively introduce project bank accounts as from
2008.
Project bank accounts: NAO's view
"Departments need to provide specialist small and medium
sized suppliers with greater certainty that they will be paid
on time to reinforce the trust that should exist between all parties
for collaborative working to operate effectively. If this trust
does not exist in the supply chain then specialist suppliers,
who can significantly influence the value for money obtained on
a project, will have little incentive to innovate. Considerable
losses can also be incurred over payment disputes which will ultimately
feed their way back into the costs for the client. The use of
a single project account is one way to provide greater certainty
of payment to specialist contractors and suppliers further down
the supply chain from the main contractor."
(Para 3.33 NAO Report, "Improving
Public Services though
better construction", 2005)
"Over time, as confidence in the system increases, the
use of `Fair Payment' Charters and Project Bank Accounts will
become more widespread and further overhead and risk savings could
be realised, increasing savings to over £750m." (emphasis
added)
2.6 Rider Levett Bucknall, a leading firm of construction
consultants, has developed a training package to support client
organisations and supply chains intending to use project bank
accounts; it has experience of using such accounts. The Bank of
Scotland and Barclays Bank have developed specific banking documentation
to facilitate the setting up of the account. Contract producing
bodies are also developing project bank account provisions for
their contracts. The OGC has set up a monitoring process to gauge
progress. Therefore, everything is in place to enable procuring
organisations to set up and use project bank accounts from January
2008.
How a Project Bank Account works

2.7 Last year SEC Group carried out a survey of firms
in its member associations to inquire into the extent to which
their costs would be reduced by having project bank accounts.
65% of respondents thought that their costs would be reduced;
the majority of respondents believed their costs would reduce
by up to 5%. A significant number stated that their costs would
be reduced by up to 10%. The survey results were audited by David
Langdon.
"There is very good alignment between the mechanism of
Project Bank Accounts and the principles of fair payment, and
it is recommended that public sector clients should progressively
specify use of Project Bank Accounts where practicable and cost
effective. Where they are used, clients should give a written
committment to a payment period linked to a PBA. Their use generates
the confidence in both the supply chain and the lead contractor,
reducing their risks and prices by providing real surety of cash
flow for all parties."
(Para.18. Guide to Best `Fair Payment'
Practices, OGC Report: August 2007)
Collaborative Contracts
2.8 Contractual arrangements should be transparent throughout
if we are to achieve genuine teamworking. Government procurers
should insist on the use of collaborative contacts throughout
the supply chain; furthermore, lead contractors' bespoke sub-contracts
should be outlawed on public sector works.

2.9 Our 2005 survey of engineering contractors working
on Government projects (as sub-contractors) indicated that only
38% of firms were content with the contractual terms on offer
on the majority of projects. The supply chain construction contracts
for government projects are generally bespoke contracts generated
by lead contractors. Our attention has often been drawn to the
fact that at government client-lead contractor level the contracts
are even-handed but, below the lead contractor, there is a disproportionate
allocation of risk to the supply chain. This undermines the efforts
of government procurers to encourage greater teamworking within
the delivery team.
"Forms of contract should aim to improve the quality
and cost-effective delivery of clients' projects through . . .
[allocating] each risk to the party who is best able to manage
it."
(Procurement Guide 6, Procurement and
Contract Strategies, OGC)
2.10 This provides an opportunity to raise another issue
relating to contracts on government construction projects. There
are a vast array of construction contracts used by Government
procurers for various procurement methods and building types.
Often the contracts are unnecessarily complicated and lengthy.
Whilst there has been progress in developing longer-term relationships
with the industry through framework agreements, standardisation
of contracts has not been achieved. Instead there is now a proliferation
of contracts with a variety of payment and risk/reward mechanisms.
2.11 This, of course, adds substantially to the costs
of bidding for government construction works and of administering
the contracts. In principle, all contracts and sub-contracts for
government works should be standardised or, at least, their core
provisions should be standardised. The only attempt at standardisation
has been the Treasury's standard project agreement for PFI arrangements
(SPOC4). But the construction contracts and sub-contracts let
under PFI arrangements are not standard. The easiest solution
would be for Treasury/OGC to insist upon the use of the available
collaborative contracts as recommended by the NAO in its 2005
report Improving Public Services through better construction.
"The use of standard forms of contract helps to reduce
both tendering and contract administration costs. Bespoke or amended
standard forms require clients and tenderers to seek additional
and frequently costly legal advice and this increases the risk
of disputes arising from unfamiliar terms."
(Procurement Guide 6, Procurement and
Contract Strategies, OGC)

Use of collaborative contracts: view of NAO
"Modern forms of contract can support clients in developing
closer, more collaborative, longer-term working relationships
with suppliers. The Engineering and Construction Contract . .
. is one example of a contract written in plain English that embeds
the principles of good project management in its procedures and
promotes role clarity. It encourages early issue resolution, and
contains options onto the choice of procurement route. It is non-adversarial
in its tone and spirit, and as such, many clients have adopted
it for use in long-term collaborative working arrangements . .
. More recently Collaborating for the Build Environment (Be) has
developed a collaborative form of contract. This has widespread
support from the industry and is now starting to be used on projects
in the UK . . . Some contracts are still written in the traditional
more adversarial approach and are not suitable for modern collaborative
ways of working. The Office of Government Commerce is currently
working to reduce the number of standard forms of contract being
used in the public sector.."
Project Insurance
2.12 Traditional insurance arrangements in the industry
are aimed at protecting the individual rather than the team. This
is a major barrier blocking the way to greater teamworking. There
is an acute need to develop a policy of insurance that underwrites
the whole team.
2.13 The Public Sector Construction Clients' Forum has
agreed that government procurers should identify suitable projects
for piloting "single project financial loss insurance".
A number of brokers and insurance companies are interested in
supporting pilot projects. It is now urgent that Government procurers
come forward with projects for piloting. In the meantime, both
SEC Group and the OGC have been funding work on developing a suitable
policy. It is expected that the first projects for piloting project
insurance will be underway in 2008.

"[Departments should] ... seek opportunities to pursue
the case for project-wide insurance, not only to reduce costs
through bulk buying, but also to align behaviours with the principles
of integrated team working."
(Para.3.5, "Improving Public Services
through better construction",
NAO Report, 15 March 2005)
Phasing Out the Practice of Retentions
Retentions: do they make a difference?
"Holding retention is intended to incentivise contractors
to repair defects in the defects liability period on traditional
contracts. In reality there is little evidence to show it actually
encourages contractors to produce defect-free properties. If anything
holding retentions encourages contractors and sub-contractors
to increase their prices accordingly because they will not necessarily
receive their retention."
2.14 The Trade & Industry Committee has already carried
out an inquiry into the practice of retentions: The Use of
Retentions in the UK Construction Industry (Second Report
of Session 2002-03). This was followed by a further report, Retaining
Retentions? (Fifteenth Report of Session 2002-03) which was
the Trade & Industry Committee's commentary on the government's
response to the initial report.
2.15 The Committee concluded that the practice of retentions
was out-dated in a modern, professional industry. The evidence
presented to the Committee indicated that the practice had more
to do with the provision of interest-free cash than providing
security against defects. The deduction of cash retentions (usually
5% of due payments up to practical or substantial completion of
the works) was "part and parcel" of the lowest price
culture.
Some local authorities regard retentions as convenient
interest-free loans
"Reduces borrowing and aids cash flow" (Aberdeenshire
Council)
"Retentions are not put to any `use' as such. Budgets
are allocated on the basis that retentions will be deducted so,
indirectly, retentions are used to finance capital schemes".
(Salford Council)
"Held in capital project accounts" (Strabane District
Council, Northern Ireland)
"Invested" (Poole Borough Council)
"Held in capital programme." (Barrow Borough Council)
The above quotations are extracted from
a SEC Group report,
The Use of Retentions in Local Authority Construction
Procurement published in 2004
(available at www.secgroup.org.uk)
2.16 Moreover retentions are the antithesis of teamworking
and collaboration:
(a) they indicate a lack of trust: if a firm is considered
incapable of carrying out defect-free work it should not be selected
in the first place;
(b) the practice is divisive: retentions are not deducted
from other members of the team such as consultants and manufacturers;
(c) there is never any mutuality in the practice: those
deducting retentions do not offer concomitant security for performance
such as payment bonds.
"The retention system developed as a means of ensuring
that contractors delivered work to the standard expected by the
client, and its continuation is an indication of the degree of
distrust between clients and the industry. It is also a very considerable
burden upon the industry, especially small and medium sized companies
that make up the bulk of contractors in the construction sector.
The Specialist Engineering Contractors' Group (SECG) has estimated
that SMEs are funding £3.25 billion of cash retentions every
year. Furthermore, it is a burden on the taxpayer . . .. the cost
to the public purse of such a practice could be as much as £750
million a year".
2.17 The results of a recent survey published by the
Building Services Research & Information Association (BSRIA),
a private sector research body, demonstrate the adverse impact
that retentions have on the industry. Outstanding retentions account
for 3% of the turnover of the mechanical and electrical contracting
sector. If this figure is projected across the industry's turnover,
a total of £3 billion of retention monies is outstanding!
It is difficult to conceive of any other industry in the UK that
would be prepared to tolerate such a burden of outstanding debt;
such burden weighs most heavily on small businesses.
2.18 In its survey BSRIA invited firms to indicate the
uses to which they would put retention monies in the event that
the retentions system ceased to exist. 160 firms responded to
this question as follows (some gave more than one use):
Better cash flow/stability | 37%
|
More investment in training | 20%
|
Employ more operatives | 14%
|
More IT investment | 13% |
More investment in new equipment and tools |
10% |
Fewer people in credit control | 1%
|
Status quo would remain | 5%
|
BSRIA 2007 Survey: impact of retentions on capacity
An interesting result in the BSRIA survey is that 14% of firms
would employ more operatives. There are over 50,000 firms in the
M&E sector. If each of these firms employed an additional
operative, there would be available work for almost 7,500 people.
If these statistics were projected across the industry (which
comprises approximately 180,000 firms) there would be employment
for an extra 27,000 people! This, in turn, would enable the industry
to significantly increase its capacity.
2.19 We believe that significant progress still has to
be made on the complete abolition of retentions on government
works. Even where government procurers have outlawed retentions,
the evidence is that they are still being deducted by lead contractors
from their supply chains. We invite the Business, Enterprise &
Regulatory Reform Committee to insist on compliance with its recommendation
that retentions on government works should be phased out "as
soon as possible". Since this recommendation was made four
years ago it should by now be implemented without further delaygiven
that government procurers are committed to collaborative working.
Retentions: the trade & industry committee's recommendation
"Given the annual cost of retentions to the construction
sector and to their public sector clients, it is obviously in
the interest of all parties that they are phased out as soon as
possible. The Government has insisted that this be done by the
successful introduction of best procurement practice so that the
retentions system is rendered obsolete, rather than by direct
action to remove retentions provisions from government contracts.
We do not accept that these actions are mutually exclusive, as
the Government appears to believe, especially as some departments,
such as the Highways Agency, have already indicated that removing
retentions provisions would be feasible by 2007, as we had suggested".
Action is now needed in the areas of payment, insurance and
contracts to remove barriers to integrated teamworking as well
as to facilitate it.
Our Recommendations
2.20 (a) Given the support and guidance that is now available
for setting up project bank accounts, we invite the Committee
to recommend that all government procurers introduce such accounts
on new projects commencing in 2008, where practical and cost effective.
Local authorities should be encouraged to consider them for new
projects starting in 2009. Initially, we would suggest that they
should be applied to projects over £3 million (although this
should not prevent public sector clients applying them to lesservalue
projects if they so wish).
(b) Given the support for integrated project insurance
from the NAO and Public Sector Construction Clients' Forum, further
encouragement should be given to government procurers to identify
projects suitable for piloting this type of policy. The project
value should be between £20 million and £30 million.
We suggest that the Committee invites the OGC to contact all government
procurers to establish whether they can offer at least one pilot
project.
(c) We suggest the Committee invites the OGC to set targets
for government procurers to standardise construction contracts
for all procurement routes by insisting on the use of standard
collaborative contracts for the whole delivery team. This should
involve the outlawing of bespoke contracts throughout the supply
chain.
(d) The Committee has already proposed the elimination
of retentions on government projects to take effect "as soon
as possible". It originally recommended 2007 as the target.
We suggest that the end of 2008 should now be considered as the
target for phasing out this practice.
Questions
12.21 (a) Given that project bank accounts are recommended
by the Public Sector Construction Clients' Forum, the OGC and
the National Audit Office (and are also recommended in the 2012
Construction Commitments), will the Treasury/OGC now insist that
they are introduced on all government projects commencing in 2008
where practicable and cost effective? [Treasury/OGC]
(b) What would be the most effective way of encouraging
local authorities to establish project bank accounts on local
authority construction works? [DCLG]
(c) Can we work together to set an achievable target
(say 2009) for local authorities to introduce project bank accounts
for all new projects commencing in that year? [DCLG]
(d) What measures will be taken to ensure that there
is standardisation of contracts across all government procurement
routes? [Treasury/OGC]
(e) The easiest solution, presumably, would be to insist
on the use of standard collaborative contracts for all government
procurement routes allowing for a fair allocation of risk within
the supply chain? [Treasury/OGC/Individual Government procurers]
(f) If Treasury/OGC and individual procurers were to
insist on the use of standard collaborative contracts will bespoke
contracts and sub-contracts be outlawed? [Treasury/OGC/ individual
government procurers]
(g) Will OGC take responsibility for drawing up a list
of future government project(s) valued between £20 million
to 30 million that could be adopted as pilots to trial policies
of project insurance? [OGC]
(h) To what extent has the practice of retentions on
government works been outlawed:
i. between clients and lead contractors; and
ii. between lead contractor and sub-contractors? [Treasury/OGC/
individual
government procurers]
(i) In the case of those government departments and agencies
which still require retentions, what are their reasons for doing
so and when will they cease the practice? [Treasury/OGC/ individual
Government procurers]
SUMMARY OF SEC GROUP RECOMMENDATIONS
2.A | All government procurers to introduce project bank accounts where practical and cost effective for all projects commencing in 2008. All local authorities should be encouraged to consider them for new projects commencing in 2009.
|
2.B | OGC to contact all government procurers to encourage them to offer at least one project (value between £20-30 million) for piloting project insurance.
|
2.C | Government procurers should insist upon the use of collaborative contracts for the whole delivery team and that bespoke contracts and sub-contracts are outlawed. OGC should set targets by which these actions should be completed.
|
2.D | The end of 2008 to be the target for outlawing the practice of retentions on all government projects (including retentions applied along the supply chain) following a recommendation of the Trade & Industry Committee in 2003 that "Government departments . . . eliminate the practice of retentions as soon as possible".
|
3. REMEDYING THE
WEAKNESSES IN
THE CONSTRUCTION
ACT
Background to Review of the Act
3.1 The priority for the overwhelming majority of contracting
firms in the UK construction industrymainly SMEsis
payment security. Over the years studies have consistently shown
that payment delays and abuse are far more widespread in construction
than in other UK industries. Payment abuse embraces a variety
of behaviours from failing to pay without providing reasons to
delaying payments for spurious reasons connected with, for example,
the value of works carried out or alleged payee defaults. Following
a recommendation in Sir Michael Latham's report in 1994 "Constructing
the Team", Part II of the Housing Grants, Construction &
Regeneration Act (generally known as the "Construction Act"
and called the "Act" in this document) was introduced.
It came into force on 1 May 1998.
"Two words . . . the gatekeepers to any real progress
. . . These words are `trust' and `money'. They are totally interlocked.
Too little trustand not enough money. A mighty machine
which requires oil in its engine to drive it, has grit instead."
3.2 Most firms in the industry would acknowledge that
the Act has helped to improve payment certainty. In particular,
the provisions relating to the right of suspension for non-payment,
the limited ban on pay when paid clauses and adjudication (for
dealing quickly with payment disputes) have been of great assistance
in helping to eradicate poor payment practices along the supply
chain. But experience over the past nine years shows that:
(a) Weaknesses in the Act have become apparent and exploitation
of these is rife;
(b) Most firms have difficulties in establishing whether
their contracts are Act compliant;
(c) Payment abuse and delays remain a significant problem;
and
(d) Adjudication has now become an expensive process which
deters SMEs from using it. (An explanatory note in Schedule I
at the end of this document summarises the Act's provisions and
its major weaknesses.)

3.3 Consequently the (then) Chancellor announced a review
of the Act in his 2004 Budget Statement. The DTI (now BERR) was
given the task of carrying out the review. Sir Michael Latham
was appointed Chairman of the Review Panel. Working groups on
payment and adjudication were established to identify the issues
on which the industry should be consulted. Sir Michael reported
to the [then] Construction Minister on 17 September 2004.
Announcement of review of act
"Following concerns expressed by the construction industry
on unreasonable delays in payment, the Government will review
the operation of the adjudication and payment provisions in the
Housing Grants, Construction and Regeneration Act 1996 to identify
what improvements can be made."
(March 2004, Budget Statement)
3.4 In March 2005 the DTI initiated a three month consultation
on issues arising from Sir Michael Latham's review. However, some
issues had either been diluted or excluded from the consultation.
(The issues raised in Sir Michael's review and progress to date
are set out in Schedule 2.) A second three month consultation
(Improving Payment Practices in the construction industry) was
launched in June 2007 with proposals that bore little resemblance
to the issues in Sir Michael Latham's 2004 report.
"Is there a need for improvement in payment practices?
This was the million dollar question last March. The short answer
from the consultation is `yes' we do need to improve payment practices."
Amending the Payment Provisions
3.5 In summary BERR's proposals for amending the payment
provisions were:
(a) The payer must issue a notice to the payee informing
him of the payment which is due;
(b) The payer can revise that amount in a subsequent notice
to the payee;
(c) If the payee wishes to challenge the original (or
subsequent) notice he can do so by referring the matter to adjudication;
(d) If the payer does not issue a payment notice the payee
can make a claim: the claim will, instead, be the amount due but
it will be subject to a payer's notice withholding monies (the
statutory fall-back provision);
(e) The statutory right of suspension of work for non-payment
will be bolstered;
(f) Pay-when-certified clauses will be outlawed.
3.6 The fundamental issue in amending this legislation
is to ensure that the payee is certain as to the date of payment
and the amount to be received on that date; this, after all, was
Parliament's intention in passing the Act. Furthermore, the statutory
provisions for achieving this must be clear, simple and reflect
commercial logic and practice. BERR's proposals [at 3.5 (a) to
(d)] for amending the payment provisions do not achieve these
aims:
"The legislation requires that payment should be defined
in terms of amount and date" (emphasis added)
Lord Lucas in House of Lords debate
on 26 February 1996
(a) It is illogical for the payer to commence the payment
process by, in effect, issuing the payee with his version of the
payee's bill;
(b) The proposals are complicated and inhibit early communication
to resolve differences since the payer can issue another noticeperhaps,
some weeks latermaking deductions from the amount in the
first notice;
(c) The proposals prevent definition of what is to be
paid at the payment date because any challenge to the amount in
the payer's payment notice may have to be referred to an adjudicator;
in the meantime nothing is paid and the payee cannot exercise
his statutory right of suspension of his contract for non-payment
(this position often forces firms into insolvency);
(d) It is not commercially practicable for the payee to
go to adjudication every time he disagrees with the amount the
payer states he intends to pay; adjudication has now become an
expensive process.
3.7 The proposal to ban pay-when-certified clauses in
contracts (enabling a main contractor to delay payments to sub-contractors
until he has received an architect's or engineer's certificate)
does not go far enough to prevent abuse:
(a) Clauses will be drafted to avoid the ban (for example,
payments will not be made until the work has been valuedrather
than certifiedby an architect/engineer);
(b) The ban does not extend to the outlawing of those
pay-when-paid provisions (currently sanctioned by the Act) which
enable a main contractor to avoid paying subcontractors when a
third party payersuch as the clientgoes into insolvency.
An analysis of 100 sub-contracts revealed that 96% made payment
conditionalas to time/entitlementon the issue of
a main contract certificate or some other event.
(Analysis carried out by SEC Group in
2000)
3.8 Furthermore, BERR has not addressed a number of issues
raised in Sir Michael Latham's 2004 report:
(a) Outlawing cross-contract set-off (the practice whereby
a payer will hold back monies because of alleged shortcomings
by the payee on otherunrelatedcontracts);
(b) Ensuring that payments commence from date of contract
rather than from the date of work on site which could be many
weeks later (after which a substantial amount of assembly or manufacturing
may have taken place);
(c) Protection for SMEs against insolvencies up the supply
chain (EU countries, the US and Australasia have statutory insolvency
protection for SMEs engaged on construction works).
"That this House believes that security of payment in
the construction industry especially for small and medium sized
businesses is a prerequisite to achieving trust and collaboration
in the industry; therefore, urges the Secretary of State for Trade
and Industry to use the opportunity presented by the current review
of Part II of the Housing Grants, Construction and Regeneration
Act 1996, initiated by the Chancellor of the Exchequer, to amend
the Act to ensure that there is a statutory mechanism for defining
the amount to be paid at the date for payment, that all conditional
payment provisions and cross contract set-off are outlawed, that
progress payments start from commencement of contract and that
the Act provides effective protection for firms in the supply
chain from `upstream' insolvencies. That this House believes that
payment security will be a major factor in the successful delivery
of the construction projects for the 2012 London Olympics."
(Signed by 185 MPs in 2005-06 Parliamentary
Session)
Amending the Adjudication Provisions
3.9 Statutory adjudication was introduced as a "stop-gap"
process to enable payment disputes to be dealt with quickly and
cheaply. Disputes could be referred to an impartial third party
who would have four weeks in which to reach a decision. In the
House of Lords debate on the Act in 1996 the late Lord Ackner
explained that it came under the rubric of "pay now argue
later".
3.10 When the Act came into force SMEs could use adjudication
to unlock their cash without having to go to arbitration or the
courts. The dispute could be re-heard later in arbitration or
litigation. This immediacy of adjudication coupled with the speed
and relative cheapness of the process meant thatinitiallyit
was highly successful. Small firms were given greater equality
of bargaining power by not being at risk for the other side's
costs if the decision went against them.
3.11 Unfortunately this picture has significantly changed.
In its June 2007 consultation document BERR indicated that the
average cost of an adjudication (including the adjudicator's fee
and costs) was £20,000 per adjudication. It also revealed
(in the same document) that almost half of all adjudications involve
claims of £50,000 or less. Therefore 40% of the value of
an adjudicated dispute is absorbed in its costs. On the basis
that adjudication is only intended to provide a "stop-gap"
decision, this hardly represents value for money.
3.12 A number of factors have contributed to the increasing
costs of adjudication:
(a) There are a plethora of bespoke adjudication procedures
which are primarily aimed at undermining the statutory adjudication
provisions; this, in turn, provokes arguments about whether the
procedures are compliant with the Act;
(b) There is a common bespoke arrangement that requires
the weaker party to pay all the other side's legal costs in an
adjudication irrespective of the outcome (such provision has been
upheld by the courts);
(c) The jurisdiction of adjudicators isinvariablychallenged
which increases legal costs because there are usually technical
legal arguments involved.
Consequently there is a real risk that the use of adjudication
will decline unless these issues are addressed.
3.13 BERR's proposals are summarised as follows:
(a) Two types of bespoke contract clauses will be outlawed:
(i) clauses making decisions on amounts of interim payments
"final and conclusive" (such agreements could prevent
parties disputing interim payments in adjudication), and
(ii) clauses requiring a party to re-imburse all the
other party's costs irrespective of the outcome of the adjudication.
(b) the restriction in the Act that it only applies to
contracts in writing will be removed (this requirement provided
a fertile source of challenges to the adjudicator's jurisdiction).
3.14 BERR's proposals will not reduce the costs of adjudicating;
on the contrary there is a likelihood that they will increase
such costs:
(a) BERR is only outlawing two types of adjudication clauses
but there remain myriad onerous provisions aimed at frustrating
access to adjudication;
(b) The outlawing of final and conclusive decisions relating
to interim payments will give rise to definitional arguments (and
therefore, more costs) regarding the meaning of "interim".
Moreover the Act makes clear that all disputes arising under the
contract are referable to adjudicationthese should, therefore,
include disputes relating to the amount of the final payment.
There are many more disputes relating to final payments than interim
payments.
(c) The proposal for outlawing onerous cost provisions
are undermined by the fact that the parties can agreefollowing
referral of the dispute to adjudicationthat one side pays
all the other side's legal costs (or that the adjudicator can
have power to require a party to pay the other's costs). Contractual
provisions will be routinely drafted to secure such agreements.
3.15 There is a more fundamental objection to the proposal
concerning costs. It shows a lack of understanding of the concept
of adjudication. The process, unlike arbitration or litigation,
is not concerned to establish which party is right. Parliament
intended that it should be a "rough and ready" process
for facilitating the flow of cash. Therefore the rule that "costs
follow the event" (that the "losing" party pays
the "winners" costs) is wholly inappropriate to adjudication.
The Melville Dundas v. Wimpey Case
3.16 Melville Dundas v. Wimpey is the first legal case
on the Act to be considered by the House of Lords. In April 2007
the House of Lords held (by a majority of 3 to 2) that a contractual
provision enabling a payer to withhold payment from an insolvent
payee overrode the statutory requirement that a withholding notice
be issued before the payment is withheld. BERR appears to support
an amendment to the Act that a withholding notice need not be
issued where the payee is insolvent. But, very often, the withholding
of monies is the cause of insolvency! The statutory requirement
that a withholding notice is required wherever monies are retained
should be left intact. More importantly, the Act should be amended
to make clear that its provisions cannot be overridden or modified
by contrary contractual provisions.
The Construction Act requires amendment to strengthen its
payment and adjudication provisions to reflect the intention of
parliament when passing the Act. Such amendment, therefore, should
enhance payment certainty and ensure that adjudication continues
to be inexpensive and accessible.
Our Recommendations
3.17 (a) To ensure certainty of amount and timing of
payment, the payee should be enabled to make a claim which, in
the absence of a withholding notice (or fraud), must be paid on
the payment date;
(b) All conditional payment provisions should be outlawed;
(c) BERR should re-consider its decision not to amend
the Act to outlaw the practice of cross-contract set-off; to provide
for the right to interim payments to start from commencement of
the contract and to require adequate security for firms in the
event of insolvencies upstream of the supply chain (eg direct
payments from clients to sub-contractors or the provision of payment
bonds or bank guarantees by the payer as security for payment);
(d) With the exception of the proposal to abolish the
requirement for written contracts, BERR should replace its proposals
on adjudication with the following amendments (which will obviate
the need to continually outlaw specific onerous provisions):
(i) provide a single adjudication procedure to apply to
all adjudications and,
(ii) increase the powers of the adjudicator so that he/she
can decide whether there is a dispute (and, if so, its scope);
whether there is a construction contract under the Act and whether
he/she was validly appointed.
(e) The Act should be amended to ensure that its provisions
cannot be overridden or modified by contrary contractual requirements.
3.18 Questions
(a) Would BERR accept that the lack of payment certainty
continues to be a major concern for the majority of firms in the
industry?
(b) Does BERR agree that there should be a statutory mechanism
(excluding adjudication) that clearly defines the amount that
is due on the date for payment?
(c) Why doesn't BERR, therefore, amend the Act to enable
the payer to make a payment application which will become the
due sum unless, in the meantime the payer has validity withheld
monies (in which case the difference becomes due)?
(d) BERR wants to ban pay-when-certified clauses but won't
this encourage pay-when-valued clauses as an avoidance mechanism?
(e) Why doesn't BERR simply outlaw all clauses making
payment conditional upon an event under another contract?
(f) Why doesn't BERR amend the Act to make clear that
the statutory right to interim payments takes effect on the making
of the contact (rather thanas usually happensfrom
the date of work starting on site)?
(g) Does BERR accept that construction SMEs have little
or no protection against the risk of insolvencies upstream of
the supply chain?
(h) Why doesn't BERR address this issue in the Act, especially
when other countries in Europe, USA and Australasia have already
introduced construction specific legislation to provide insolvency
protection?
(i) Why can't BERR, for example, require (as French legislation
requires) that the payer provides a bank guarantee to the payee
as security for payment in the event of insolvency?
(j) Does BERR agree that for most SMEs adjudication is
becoming an inaccessible and expensive process?
(k) Wouldn't it be easier and cheaper for everybody to
have one adjudication procedure (as they have in similar legislation
in Australia and New Zealand)?
(l) Does BERR accept that a major component of costs in
adjudication relates to challenges to the jurisdiction of the
adjudicator?
(m) Why doesn't BERR increase the jurisdiction of the
adjudicator to reduce these challenges?
(n) Why can't the adjudicator give a binding decision
on whether there is a dispute or on whether he was validly appointed?
SUMMARY OF SEC GROUP RECOMMENDATIONS
3.A | There should be a simple statutory procedure to enable the payee to claim payment and such claim should be the due amount unless, before the payment date, a withholding notice has been issued (in which case the difference between the amount claimed and the amount withheld should be the due amount).
|
3.B | All conditional payment provisions should be outlawed.
|
3.C | It should be clarified that the statutory right to interim payments starts from commencement of the contract.
|
3.D | The Act should now include a measure of insolvency protection so that a payee can require a payer to provide adequate security for payment such as bank guarantees or payment bonds or, alternatively, the client may pay sub-contractors directly.
|
3.E | The statutory adjudication provisions require amendment to restore the original statutory intent which was to provide SMEs with a cheap and speedy process for dealing with payment disputes. Therefore:
|
(i) | the Act should have a mandatory adjudication procedure to apply to all adjudications, and
|
(ii) | the jurisdiction of the adjudicator should be increased so that he can decide whether a dispute exists and (if so) its scope, whether there is a construction contract under the Act and whether he was validly appointed.
|
3.F | Other than the proposal to abolish the requirement for written contracts (as a condition precedent to using the Act) BERR should abandon its other adjudication proposals.
|
3.G | The Act should make clear that the statutory provisions cannot be modified or overridden by contrary contractual provisions.
|
4. ACHIEVING A
SUSTAINABLE CONSTRUCTION
INDUSTRY
4.1 A sustainable construction industry is one that invests
in training, regularly upgrades its skills, invests in new technologies
and places health and safety at the top of its priorities. All
these factors are crucial in delivering consistent quality and
service.
"Effective procurement and contracting strategies require
. . .. clients to use their considerable leverage and influence
to only select suppliers who have a proven track record in, and
commitment to, developing the skills of their workforce, collaborative
working, health and safety and sustainable development."
(Page 67, Improving Public Services through
better
construction, NAO, March 2005)
4.2 Public sector procurers have a critical role to play
in promoting a sustainable industry by only selecting competent
firms as contractors or sub-contractors on public sector works.
At a minimum competence involves objective proof that a business:
(a) is technically proficient and sufficiently resourced
to deliver the services it provides;
(b) is of sound financial standing; and
(c) has procedures in place for ensuring health and safety.
4.3 Confining selection to competent firms on public
sector works would have the following consequences:
(a) It would create a "level playing field"
since all firms would have been identified as competent prior
to any competitive bidding process;
(b) Competent firms would be more likely to achieve stable
and predictable margins which would enable them to invest in those
resources necessary to improve quality;
(c) Teamworking arrangements are likely to be successful
where members of the team have demonstrated their competence.
Proliferation of Schemes
4.4 The absence of a widely-accepted means of identifying
firms as competent has led to a plethora of vetting processes,
pre-qualification requirements (relating to an assessment of fitness
to tender) and approval processesespecially in the public
sector. In addition, main contractors have their own vetting processes
for sub-contractors. Public sector clients and main contractors
(in respect of their sub-contractors) often rely upon third partiesusually
private sector firmsto carry out the vetting or approval
process. There is no evidence that such third party accreditation
has helped bring about improved value for money for the public
sector. Instead it has imposed a substantial burden upon the industry,
especially SMEs.
4.5 This state of affairs was investigated by the OGC and
Small Business Service (SBS) following a statement in the 2005
Budget Statement. The investigation was carried out by Merlin
Consultancy which reported to OGC and SBS at the end of 2005.

An SME who provided services to a District Council and was
an approved supplier received a letter from the Council to inform
him that the Council was compiling a new directory of suppliers
that would be managed by a third party. In order to be included
in this directory there would be an annual charge. Failure to
join the system would mean that a company would not be considered
for any future Council contracts.
The SME in question was being asked to pay £225 per year
when the Council had only spent £3,057 with them over an
eighteen month period. Calculated over a year the sum charged
was over 10% of the money he had received in payment for services,
which significantly ate into profits thereby making it uneconomical
for him to continue to trade with the Council.
Extracted from the Third Party Supplier
Accreditation Study, Merlin Consultancy;
Report presented to OGC and the Small Business
Service, December 2005
The Merlin report made a number of points:
(a) The plethora of third party accreditation schemes
is a major barrier to SME participation in public sector works;
(b) Such third party assessment is usually a desk-based
process that checks availability of certain policies and procedures
such as insurance and health and safety, and, also, referencesthe
quality of the product or service is not assessed or inspected;
(c) On the other hand trade bodies have "quality
mark" assessment involving the auditing of members' work
through site visits and inspections.
Unfortunately there has been no follow-up work to this report
and (to our knowledge), no further action has been taken.
An SME with up to 100 employees which provides mechanical
and electrical services to local government, housing associations,
utilities and police/fire services paid £3,190 in direct
fees to be accredited on five separate lists. The SME declined
to join two further lists, one for the local authority sector
where the fee was £520 pa plus £100 for each additional
council, and one for the utility sector where the annual fee was
£605. The SME had over a period of time been on over one
hundred council/housing association approved lists. There was
no mutual recognition between lists and the SME considered that,
"this has got completely out of hand", because in addition
to the direct fees there was an associated overhead burden in
terms of responding to the differing questionnaires and in particular
where some of the questions "have no bearing on our line
of business".
Extracted from the Third Party Supplier
Accreditation Study, Merlin Consultancy;
Report presented to OGC and the Small Business
Service, December 2005
4.6 In addition to the plethora of accreditation schemes
there are also various statutory requirements relating to competence.
Many of these are to be found in the Building Regulations and
other related regulations (such as the Gas Regulations, Fire Regulations
and Water Regulations) which are often illogical and contradictory.
There is a need to harmonise and rationalise these requirements.
4.7 In recent years SEC Group's member associations have
made a substantial investment in developing qualification and
registration schemes comprising stringent requirements relating
to firms' technical proficiency and financial standing (as well
as health and safety performance). Compliance with these requirements
is regularly audited and monitored. Nonetheless, firms belonging
to these schemes are frequently required to belong to other schemes
or be accredited by other organisations. There should be a means
of recognising membership of a registration or qualification scheme
as a reliable indicator of a firm's competence. This should also
allow for mutual recognition of schemes so that membership of
one scheme would also satisfy the requirements of others.
4.8 As far as health and safety is concerned there are
now core criteria in the Approved Code of Practice issued alongside
the 2007 Construction, Design & Management (CDM) Regulations
for determining the competence of a firm (either individually
or through membership of a registration or licensing scheme).
Where a firm is compliant with the core criteria it should not
have to be accredited under any other scheme that is similarly
compliant.
4.9 In recent years there has been the introduction of
competent persons schemes. These schemesquite rightlyacknowledge
the fact that the industry possesses the necessary expertise and
experience to determine whether standards are being adhered to.
They allow for greater self-regulation by allowing firms to self-certify
compliance with the Regulations. The industry has developed schemes
to provide firms with the facility to self-certify but, again,
there is a need to rationalise or harmonise these schemes to reduce
the burden on industry. Furthermore, it should be considered whether
these schemes could embrace other competence requirements in the
Building Regulations and related regulations.
In order to promote a sustainable industry that delivers value
for money, public sector procurers should insist that only competent
firms are engaged on public sector works (whether as contractors
or subcontractors). However, we need to have in place a means
for recognising competence (which are acceptable to procurers)
whilst, at the same time, rationalising competence schemes and
reducing the burden on SMEs of myriad third party vettng processes.
Questions
4.10 (a) Is there any objection to the principle that
only firmswhether contractors or subcontractorswhich
have demonstrated their competence (perhaps, through membership
of reputable qualification/registration schemes) should be engaged
on public sector works? [Treasury/OGC/DCLG]
(b) Is it accepted that there are too many vetting procedures
on public sector works contracts which are time consuming, repetitive
and exceptionally costly for SMEs? [Treasury/OGC/BERR/DCLG]
(c) Do you accept that the majority of vetting procedures
simply involve a "desk-top" assessment of whether a
firm has the relevant paperwork in place rather than an assessment
of technical proficiency and resourcing involving visits to the
firm and inspection of standards of work? [Treasury/OGC/BERR/DCLG]
(d) How should we assess whether a firm is competent?
[Treasury/OGC/BERR/DCLG]
(e) Is it accepted that only firms that have complied
with the core criteria in the Approved Code of Practice issued
under the 2007 CDM Regulationsindicating that they are
competent in relation to health and safetyshould be engaged
on public sector works? [Treasury/OGC/DCLG]
(f) Is it accepted that core criteria for technical proficiency
and financial standing could be developed as a means of "badging"
competent firms (either individually or as members of a registration
scheme) and also to facilitate mutual recognition of schemes that
comply with the criteria? [Treasury/OGC/DCLG]
(g) Would you accept a single badge for "competent
person" schemes under the Building Regulations so that membership
of one scheme may suffice without the need to join other schemes
or similar schemes under other regulations? [DCLG]
(h) Could membership of a "competent person"
scheme also help in demonstrating compliance with other requirements
relating to competence in the Building Regulations and related
regulations? [DCLG]
Our Recommendations
4.11 Public sector clients should take a lead in ensuring
that only firms complying with the core criteria in the Approved
Code of Practice to the Construction, Design & Management
Regulations are appointed on public sector works. This requirement
should extend to all members of the supply chain. It is suggested
that a lead-in time is provided to enable firms to become compliant
with the core criteris. Ideally such lead-in time should be, at
least, one year.
4.12 In collaboration with the industry the OGC should
be invited to develop core criteria relating to technical proficiency
and financial standing for recognisingas competentfirms
in membership of registration or qualification schemes (and also
for similarly recognising firms not in membership of such schemes).
The DCLG may wish to be involved because of its responsibilities
for local authorities. Once the core criteria are in place all
procurers of public sector worksincluding supply chain
membersshould only select firms in membership of schemes
that have been badged as compliant with the core criteria (or,
alternatively, individual firms that have demonstrated compliance
with the core criteria). Again, a suitable lead-in time for the
industry to become compliant would be required.
4.13 Our proposal is that the DCLG should develop a single
identifiable badge for competent persons schemes together with
common standards of accreditation for such schemes. Having a single
identifiable badge will mean that a firm which is a competent
person under a badged scheme will also qualify as a competent
person under other schemes and, possibly, also comply with other
requirements relating to competence under the Building Regulations
and/or other related regulations.
4.14 The vision is that at some point in the future we
will simply have one badge of competence showing that a firm is
compliant with core and essential criteria relating to technical
proficiency, financial standing and health and safety.
SUMMARY OF SEC GROUP RECOMMENDATIONS
4.A | It is suggested that the Committee recommend that all procurers (including supply chain members) of all new public sector works commencing in 2009 will only select firms that have (either individually or as a member of a qualification scheme) complied with the core criteria in the Approved Code of Practice issued under the 2007 Construction Design & Management Regulations. It is necessary that the Government makes an announcement to this effect as soon as possible to enable the industry to have sufficient time in which to become compliant.
|
4.B | In collaboration with the industry the OGC should be invited to develop core criteria in relation to technical proficiency and financial standing for recognising membership of registration/licensing/qualification schemes as a reliable indicator of competence (or for recognising individual firms as competent).
|
4.C | Once the core criteria (at 4.B) have been developed it is suggested that the Committee recommends that the OGC and DCLG (following a suitable lead-in time for the industry to become compliant with the criteria) advise all procurers of public sector worksincluding supply chain membersonly to select firms in membership of schemes of qualification that are badged as complying with the core criteria (or individual firms that have demonstrated such compliance).
|
4.D | We suggest that the Committee invites the DCLG (and other interested parties) to work with the industry in developing a single identifiable badge for "competent persons" schemes so that membership of one scheme may suffice for membership of other schemes and, possibly, also satisfy other requirements relating to competence under the Building Regulations and other related regulations.
|
5. RELEASING THE
POTENTIAL OF SMES

5.1 The burden of poor procurement and contractual practices
is generally borne by SMEs. They comprise the overwhelming majority
of firms in the construction industry; most are sub-contractors.
They are responsible for delivering most of the industry's output.
5.2 A high proportion of the overheads of SMEs is wasted
in dealing with adversarial tendering and contractual practices
that are primarily aimed at transferring all risks to the SME.
This burden upon SMEs is significantly enhanced by poor payment
practices which we have already discussed at some length. All
this has a detrimental impact on investment in training, technology
and, ultimately, on capacity and productivity.
"Evidence suggests that small firm productivity is a
key contributor to the overall productivity gap. This is especially
important to the UK given the long and often in-efficient supply
chains in construction: many smaller firms contribute to key elements
of major projects."
(para. 5.9, 2005-15: Construction
Demand/Capacity Study, Deloitte, 2007
(Report to the OGC)
5.3 In 2003 the Better Regulation Task Force and the
Small Business Council recommended that public sector clients
should become proactive in improving the commercial treatment
of SMEs. In its 2005 report, Improving Public Services through
better construction, the NAO made a similar recommendation.
Although the Public Sector Construction Clients' Forum and OGC
has published a Fair Payment Charter there is a need for a broader
charter that addresses a number of barriers to SMEs becoming fully
engaged in public sector works. At Schedule 3 we have included
a draft best practice SME Charter for public sector construction
procurement. This should be endorsed by the OGC (and its counterparts
in Scotland, Wales and Northern Ireland) and applied to all public
sector works contracts.
Extract from letter dated 29 March 2006 from Carillion
to sub-contractors/suppliers following acquisition of Mowlem,
"I am writing to you to request your agreement to payment
terms of net 65 days monthly account on all future subcontracts
and orders. Please be aware that, whilst it is accepted that not
everyone will be able to comply, preference must necessarily be
given to Companies offering the most advantageous terms."
[NOTE: The Government's standard period
for discharging payments is 30 days.]
Public sector procurers should be more proactive in improving
the commercial treatment of SMEs engaged on public sector works
contracts.
Question
Would there be any objection in principle to public sector
clients adopting a best practice construction charter for SMEs
and ensuring that such charter is adopted and implemented on public
sector works? [Treasury, OGC, DCLG]
SEC GROUP RECOMMENDATION
5. | We invite the Committee to recommend that the OGC (and its counterparts in Scotland, Wales, Northern Ireland) endorse the draft best practice SME Charter attached at Schedule 3. Following such endorsement they should be invited to take steps to ensure that the Charter is adopted and implemented by all procurers of public sector works. Further, its use should be monitored and it should be understood that non-compliance with the Charter could result in a failure to obtain public sector works contracts in the future.
|
SCHEDULE 1
EXPLANATORY NOTE ON PART II OF THE HOUSING GRANTS, CONSTRUCTION
AND REGENERATION ACT 1996 ("the Act")
The Act introduces a number of statutory rights:
(a) A right to progress payments.
(b) A right to a withholding notice before deductions
can be made from sums due for payment.
(c) A right to suspend one's contract for non-payment.
(d) A right to refer disputes to adjudicationintended
to be a stop-gap process for dealing with disputes rapidly and
inexpensively.
In addition the Act:
(e) Requires that construction contracts contain an adequate
payment mechanism for determining what is to be paid and
when; this is fundamental to the operation of the Act.
(f) Requires construction contracts to ensure payer notifies
payee of the amount of interim/final payment [he] intends to pay.
(g) Imposes a limited ban on pay when paid provisions;
they can still be relied upon by a payer where his own payer has
gone into insolvency.
(h) Requires construction contracts to contain certain
provisions relating to adjudication.
(i) Introduced the Scheme for Construction Contracts
comprising fall-back provisions in the event that contracts
do not comply with the Act.
WEAKNESSES IN
THE ACT
The weaknesses in the payment provisions can be summarised
as follows:
(i) Contracts are required to have an adequate mechanism
for payment. In practice, they are drafted to enable the payer
to delay payment by spurious challenges to a payment claim or
by simply ignoring the claim, thus forcing the payee to go to
adjudication (and, thus incur significant costs).
(ii) Although the Act requires the payer (by virtue of
an imposed contractual obligation) to notify the payee of the
amount it intends to pay; such notice is rarely given because
of the lack of sanction. This means that more often than not a
payee will not know the amount it can expect from the payer.
(iii) It is unclear when the right to progress payments
actually arisesas a result payment usually starts sometime
after arrival on site. Many firms will have incurred vast expense
(eg on design, manufacture and assembly) prior to such arrival
and this is a significant drain on resources, particularly for
SMEs.
(iv) Pay when certified or pay what is certified
provisions are commonplace; they are an attempt to avoid the [limited]
ban on pay when (what) paid.
(v) Deductions from monies due often consist of claims
alleged to exist under other unrelated contracts (cross-contract
set-off).
(vi) Withholding notices are only required to state the
amount(s) withheld and the reason(s); in practice this enables
the payer to state, for example, "£1,000 is deducted
for delay" without providing any detail.
(vii) By legitimising pay when/if paid provisions (enabling
a payer to refuse payment where his payer has gone into insolvency);
the Act has increased the exposure of SMEs to the risk of upstream
insolvencies.
The weaknesses in the adjudication process:
(i) there are myriad bespoke adjudication procedures aimed
at undermining the statutory provisions;
(ii) the cost of adjudication has been significantly increased
by habitual challenges to the adjudicator's jurisdiction; and
(iii) many bespoke contractual adjudication procedures
seek to impose upon a party an obligation to meet the other side's
legal costs. This is inappropriate to a procedure which is only
a stop-gap and not determinative of the parties' rights.
SCHEDULE 2
ISSUES RAISED IN SIR MICHAEL LATHAM'S REVIEW OF THE ACT
AND PROGRESS TO DATE

Footnote:
* The working group examining the adjudication provisions
provided Sir Michael Latham with a lengthy "shopping list"
of issues; we have highlighted the key issues.
SCHEDULE 3
A BEST PRACTICE SME CHARTER FOR PUBLIC SECTOR CONSTRUCTION
PROCUREMENT
THE AIMS
OF THE
CHARTER
This Charter sets out best practice principles
on procurement and contracts to encourage the involvement of SMEs
on public sector works. It is intended to be applied along the
supply chain from the public sector client to sub-contractors
(unless the Charter indicates that a certain requirement(s) applies
to a particular party).
Lead contractors and their supply chains will
be expected to sign the Charter prior to undertaking public sector
works contracts. It is intended that compliance with the Charter
will:
help deliver best value in construction procurement
to the public sector;
improve the capacity of SMEs in the construction
industry; and
improve profit margins for SMEs engaged on public
sector works.
PRE-QUALIFICATION
Wherever possible and subject to the Public Sector
Contracts Regulations 2006 procurers will seek to use local contractors.
Procurers will seek to use contractors registered
with reputable schemes of qualification that verify technical
competence, health and safety performance and financial standing.
Contractors who are registered with reputable
schemes of qualification would automatically qualify for all public
sector works contracts unless there are requirements that are
highly specific to the nature or type of work involved.
Procurers will use standard pre-qualification
documentation developed by the Office of Government Commerce (OGC).
SELECTION AND
APPOINTMENT
Partnering or collaborative working arrangements
will be inclusive of the supply chain.
Contractors should be appointed as early as possible
in the procurement process, preferably as part of the design team
(in which case they should be paid a fee for their design input).
Bids should always be assessed on best value (embracing
whole life performance and sustainable solutions) rather than
on lowest price; the best value criteria together with the respective
weightings should be available to all tenderers.
Lead contractors and sub-contractors should list
members of their supply chains when tendering and such lists should
be adhered to.
When bidding all contractors should provide evidence
of their payment performance in respect of their supply chains.
MONITORING QUALITY
& PERFORMANCE
Public sector clients will seek to institute mid-project
and post-project reviews of performance to provide feedback to
the whole supply chain that will include progress against Key
Performance Indicators thereby promoting continuous improvement.
Suppliers will work together as a team to manage
out defects as work progresses.
CONTRACTS
The suites of contracts used by the public sector
client will be adopted (unamended) by the supply chain provided
they achieve a fair and proportionate allocation of risk.
PAYMENT
All payments will be discharged within a period
not exceeding 30 days from the date on which payment becomes due.
Public sector clients will announce targets for
phasing out the practice of retentions and, where they do not
use retentions, this policy will be followed through the supply
chain.
Where retentions are deducted they shall be ringfenced
for the whole supply chain in a trust account.
Where a contractor deducts retentions from members
of his supply chain he must offer mutuality of security such as
a payment bond.
Public sector clients to put in place project
bank accounts unless it is demonstrated that they would not be
cost effective to set up.
All final accounts will be agreed within a period
of 30 days commencing from completion of the contract.
NON-COMPLIANCE
WITH THIS
CHARTER
Complaints concerning non-compliance with this
Charter may be made by clients or by individual firms or by a
trade association acting on a firm's behalf.
In the event that a complaint is not resolved
between the relevant parties it may be submitted to the OGC to
be considered in accordance with the suppliers' complaints procedure.
The OGC will report to the relevant parties (and
the public sector client if the client is not a relevant party)
on whether there has been a failure to comply with the Charter.
The OGC will produce an annual report on the extent
of compliance with the Charter.
Repeated non-compliance with this Charter by a
client could affect future funding of projects instigated by that
client.
Repeated non-compliance by a contracting firm
could affect its future selection for public sector works.
NOTE:
References to the OGC include its counterparts in the rest
of the UK; the Scottish Executive, Welsh Assembly Government and
the Northern Ireland Procurement Directorate. The provisions of
this charter do not conflict with the OGC's Fair Payment Charter
launched on 19 September 2007.
|