Select Committee on Business and Enterprise Minutes of Evidence


Examination of Witnesses (Questions 520-539)

ODA

15 JANUARY 2008

  Q520  Mr Weir: That was my next question, that we would like to see the evidence of that, and I think we all appreciate the confidentiality of it. Why is it that there was only one eventual bidder for the Olympic Stadium contract and the Aquatic Centre?

  Mr Shiplee: There are two very different reasons. As far as the stadium is concerned, it was the first major venue that had been out to the marketplace and I think at that time, some 16 months ago now, our own plans were just being formalised, we had really only just been constituted as a board and most of us came to the ODA at or about that time in terms of the current management team. I think, frankly, the industry simply looked at it and took a vote not in any darkened room, but they simply voted with their feet. I have talked to the chief executives of many of the companies who we would have thought would have bid and the general response I have received, and did receive, was, "Well, just look at who's bidding. The company that is bidding or one of the companies is the company that has just finished what has been seen to be an incredibly successful major sporting venue, so why should we bother getting into this competition? That's the best team, they've done it before. You're taking on a designer and a contractor at the same time, so why reinvent the wheel? We'll go and spend our money on bidding for something somewhere else". That is the fact of it.

  Q521  Mr Weir: That seems a rather timid response from the construction industry. There is a widespread belief apparently within the industry that the Olympics presents a massive opportunity for the sector, but what you are describing seems to be a rather timid approach to it if they are not prepared even to bid for the large contracts.

  Mr Shiplee: Well, if I could spin it round the other way for you, and I am making no comment about Wembley whatsoever other than the fact that the industry did not appear to be terribly excited about it, it is interesting that the contractor that got it and successfully completed it, which is, I think, a tribute to them, it was the first project in this country for a contractor which had not operated in this country before. I do not want to see contractors coming and saying, "We're really very good and are going to take on huge risk", but what we are looking for is confidence in the capability of delivery, and people have recognised risk and have taken a view. If that was their business judgment that they did not wish to participate, there is not a lot that we can do about it. However, just to complete it, the second one where we finished up with a single bidder, and I should just give you the background to that and say that those are the only two and in many other areas we have had very substantive and effective bid lists from industry where industry has obviously decided that it is appropriate to bid, we have also learnt because one of the things we do now on every one of our bids is that we hold industry days and we talk to industry way in advance of going out to tender both to explain to them what is coming up and to hear their views about whether it is attractive to them and, as a result of that, we have found ourselves in a generally much better position. The second area is the Aquatic Centre and we have learnt from the stadium and we went through a process and had a very solid bid list. We, however, finished up with three bidders actually commencing the bid process. Of those three bidders, one dropped out because during the process they were simply not prepared to accept our terms and conditions, they wanted an alternative set of terms and conditions which we felt were unacceptable, so we said, "We're not going to adjust on this one", another one was very simple, that during the process, they are an international company, not from the UK but Europe, and they came in and said, "We're very, very sorry, but we've just been awarded some huge, multi-billion dollar contracts in the near and Far East. They're sucking up huge amounts of resource and, rather than give you half a job or a sham, we're going to tell you that we're withdrawing. We're very sorry about it and we're sorry that we've taken it to this position, but we're withdrawing", and we said, "Thank you for being honest about it", and it left us with a one-horse race. We have worked hard in that and what is important is that the form of contract that we have been using allows us to have discussions with contractors so that we do not finish up in a stand-off position, nor do we become a hostage to fortune, so in both of those contracts we have worked our way through negotiating with the contractors to conclude arrangements which are within our budgetary arrangements and which, we believe, provide value for money.

  Q522  Mr Weir: Was the cost of actually quoting for the main stadium, for example, a factor, do you think, in companies being unwilling to move forward and actually put in a bid in the first instance?

  Mr Shiplee: I think there is always a debate about cost, about the cost of bidding, and I think substantially that comes out a lot in PFI areas where it is exceptionally expensive to bid. We have tried to make it such that it is not an expensive operation. We still require a considerable amount of input and, after all, if people are not prepared to make the investment, then they do not deserve to get the job, but we are trying to ensure that we can, if you like, take some of the risk out of it, so in a number of areas, once we have got a contractor into the state of progressing forward through negotiations, we have on occasions agreed with one or two contractors that we will actually fund some of their early design work, as long as of course we have the intellectual property rights for that work and we may use it as we see fit, to try and reduce what are seen as the potential loss costs of tendering so as to align contractors with a desire to get on board with us and to start the process of building a relationship, and the new engineering contract is a helpful way of doing that as well.

  Q523  Mr Weir: Given obviously that the Olympics is different from many construction projects in the sense that it has to be finished by a specific date and you cannot afford to have much slippage in that date, I would suspect, can you tell us what the risks are associated with having just one bidder for these prime contracts and do you foresee any problems with that? You have mentioned before that you were not in a stand-off situation with one bidder, but surely, if you have got one bidder for a contract and they know they are the only bidder, which I presume they did by that point, then they are in a much stronger position in dealing with you than if they were in a competitive situation.

  Mr Shiplee: I think that must be right to some extent, but I think there is a balance in that debate. When talking with contractors who are bidding and have bid to us or wish to bid, one of the strong issues that they put forward is that of reputation and, after all, I do not think it behoves any contractor to feel that they have endeavoured to take advantage of a situation and what we have seen is in fact proposals coming forward to us which do not indicate that anyone is taking advantage of us. Some of these projects are complex projects, they attract a price and we have been through those prices, we have been through issues like overheads and profits, and we believe that in the circumstances they are reasonable, so we do not believe that we are being taken to the cleaners by the construction industry; quite the contrary.

  Q524  Mr Weir: You presumably will say you are, but are you satisfied that the contract you have is tight enough that we are not going to get massive overrun in cost in the run-up at speed to finish this prior to the Games commencing?

  Mr Shiplee: The answer is yes, but I think it is important to give you some background as to why I say it is yes so firmly. We started the discussions and negotiations with the contractor on the main stadium actually 16 months ago. That 16 months that we have spent now working together has not been spent on negotiating a contract, but it has been spent on actually creating the design for the stadium. When they were appointed, what we had was the broad brief as to what we required, but we went through a long period of iterations while we established the optimum design for the stadium, and what I think we have got now is quite a revolutionary approach to the stadium delivery. We have also great clarity of what that scope is and the scope has been backed up and agreed with LOCOG who will be the prime user and, ultimately, with various organisations who will collect it in the legacy, so we have created a very large element of certainty in this so that, when we start the construction, and I can report to you that the site officers, whom I think you saw when you came round a week or two back, are going up on site, our integrated team, with us as client, the contractor and the design team and now some of their specialist sub-contractors, will be moving on to the site as an integrated team within the next six weeks and with the level of certainty where we have identified very clearly what we want, how much it is to cost, and the big issue is that we must not change our minds.

  Mr Weir: I hope you are right and we will watch with interest.

  Chairman: I must remind myself and you and the Committee that we are trying to learn the lessons for the whole construction sector of what you are doing with the Olympics, so that is why it is very helpful that you drew the parallel, for example, with PFI contracts earlier on, so do feel free to draw on experience from elsewhere as well in answering the questions.

  Q525  Mr Binley: So 500 companies, which surprises me as I would have thought it would have been more, involved in the Olympics, you might correct me if my figures are wrong, and about 24,000 people in total; a sizeable project. On how many of the main projects to date has the construction team been identified and have they been involved in the early design process, and what you said intimates they have, and how much has that whole process involved sub-contractors who are a vital element of this operation?

  Mr Wright: A significant number of contracts have already been placed.

  Q526  Mr Binley: Can you be more specific than "significant"?

  Mr Wright: I would guess at around ten, and I am talking about construction contracts. Clearly there are many other kinds of procurement, including, for instance, stationery and all that sort of thing which I do not get too much involved with, but major orders have been placed in the utility market and for the initial venues clearly we are in the midst of procurement, so, when you say, "Have orders been placed?", it is a question of what stage of the process you include.

  Q527  Mr Binley: When I was a salesman, I always thought an order was when I got a signature on a piece of paper.

  Mr Wright: Well, quite, but European procurement has a number of steps to it.

  Q528  Mr Binley: I understand that.

  Mr Wright: In all of those procurements, we have engaged with a supply chain at an early stage, including, for instance, on the energy network where we are at preferred bidder stage, so the order is placed and the contract is being finalised. It is a design-build-finance-and-operate procurement and we have engaged with the private sector to invest in the long-term regeneration of the Park, so this is an energy centre not just for the Olympic Games, but for the long-term development of the site post-Games. They have put a significant amount of their own capital into the project, or they will be, on the basis that they achieve the income from selling energy.

  Q529  Mr Binley: If I can cut you short, I want to be specific with this question, if I might. We are talking about a defined number of projects.

  Mr Wright: Yes.

  Q530  Mr Binley: How many defined number of projects are there in relation to my question and for how many have you already got construction teams identified and early design work started upon?

  Mr Wright: Early design work has started on all of our projects.

  Q531  Mr Binley: But how many? I want to get a grip on this. You started on ten, but how many major construction projects have you got in total and how many have you got signed up for?

  Mr Wright: There are around 25 to 30 major construction projects. On all of those projects, design has commenced.

  Q532  Mr Binley: So that means you have signed contracts on every one of them?

  Mr Wright: For design.

  Q533  Mr Binley: And you are buying that design, irrespective of whether people get the contracts or not?

  Mr Wright: We are. In these projects, they all require an initial design, design consultant, an architect, engineer—

  Q534  Mr Binley: Okay, so you have signed up ten of those 25/30?

  Mr Wright: No, all of those contracts have designers signed up for them.

  Q535  Mr Binley: No, my question was: for how many of the major projects to date has the construction team been identified?

  Mr Wright: That is a different question.

  Q536  Mr Binley: It was my first question.

  Mr Wright: I beg your pardon if I misunderstood. We have initial design teams and, when we move, by and large, we move to a design-and-construct contract, so the initial design teams take the project through to a scheme stage or an initial design stage so that we can get planning permission and that type of permit. We then will tender it into normally a design-and-construct form of contract and, for any new engineering contract, that is very often the form of contract that we use. Of those larger number that I mentioned, 35-odd, something significantly less than that, eight to ten, are at a point where we have a design-and-construct contract identified.

  Q537  Mr Binley: Thank you, that is very helpful too for my other questions. In terms of the process at this stage, are we at too early a stage to be talking to prime contractors about sub-contractors?

  Mr Wright: No, we are not at too early a stage and there are discussions held with the tier ones, the prime contractors, during the tender process about who they will engage as their tier twos or prime sub-contractors. We are very interested in those and we want to understand who they are going to be putting forward and that we consider them to be appropriate organisations and then we will work with them. Often, they will carry out the design in the detailed stages, so it is very important that we engage with tier ones, as we are, in the earlier stages so that we can work with them together to ensure that the designs are locked in and effective.

  Q538  Mr Binley: Thank you for that; I now have a clearer view. How many of the projects currently under way use project bank accounts or project insurance and how much work have you done there?

  Mr Shiplee: Let us just pick up project insurance first. We are working on the basis of project insurance, so we insure all of the works, and the only insurance that the contractors have to carry is for their own liability in terms of their employees and their own plant and equipment. For the work itself and all the risks associated with the work, we have blanket policies and we have found that to be the most appropriate; again more learning. I think one of the important issues, and I think it was mentioned by my colleagues from T5, is the whole issue of recognition from the insurance industry that, when you perform effectively and efficiently, and I think Mr Wolstenholme said that accidents are expensive and this is absolutely true in every respect, the industry reflects that in the premiums that we are charged if we can demonstrate good performance, and I think that is a very important issue for the future. In terms of project bank accounts, looking down the construction commitments and many things, it is the one area where we have taken a view that project bank accounts, as proposed, are not something that immediately springs out as appropriate for us. The reason is that the project bank account approach works if the client is holding all of the contracts and, therefore, is the person who is actually paying and is administering the contracts. In our case, in the vast majority of cases the prime contractors will hold their relationship with the supply chain and we expect them to administer both the payments and the contractual administration of that supply chain. However, we do expect to be intrusive in wishing to know that, when we are paying properly, that is reciprocated by the tier one contractors and below also paying properly, so we are not simply turning a blind eye. The other point on this is that, if we in fact had areas, for instance, the link Mr Wolstenholme mentioned earlier of the portfolio approach to the different types of contract, and indeed that is exactly what we are doing, we have different forms within the contracts, as you have heard, some very clear about scope and price, others involving private-sector funding. If we found a situation, say, where we thought it appropriate to execute some work through a construction management route, then I would have no compunction whatsoever, where all of those contractors are directly engaged to us within that project, of in fact taking on a project bank account approach.

  Q539  Mr Binley: Good, because I do not need to say to you that (a) the construction industry is a bit prone to seeing bankruptcy on occasions, and (b) we are now running into a situation where credit is becoming more difficult to get from banks. Equally, I do not need to tell you that, if a cog in the wheel comes to an end, you have some problems on a very limited time-frame project.

  Mr Shiplee: I agree entirely.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 16 July 2008