Select Committee on Business and Enterprise Fifth Special Report


Appendix 1: Government response


RESPONSE TO THE BUSINESS AND ENTERPRISE COMMITTEE REPORT FUNDING THE NUCLEAR DECOMMISSIONING AUTHORITY.

1. The purpose of this memorandum is to provide a response to the Business and Enterprise Committee's report, "Funding the Nuclear Decommissioning Authority", which was published on 7 April.

2. We welcome publication of the Committee's report and have noted the detailed conclusions and recommendations. The report makes a number of pertinent and constructive comments and asks the Department to produce additional work to address several issues. In a number of cases, these are issues which the Department had already identified as needing further work, and we have already begun discussing with the NDA and Treasury.

3. Attached to this response is a report, "NDA Budgeting Shortfall 2007-08 - Lessons Learned Report", commissioned by the Permanent Secretary and referred to in his evidence to the Committee.

Waste Substitution Income

We emphasise that none of the issues raised in this short report should have any consequences for the construction of new nuclear power stations. Separate special funding arrangements are being developed for their decommissioning. (Paragraph 7)

4. We welcome the Committee's recognition that none of the issues raised in the report should have any consequences for the construction of new nuclear power stations.

Shortfall in the NDA's Budget

The National Audit Office (NAO), in its January 2008 report into the NDA, identified uncertainty as to whether the waste substitution income budgeted for would actually be forthcoming in the 2007/08 period. It seems that this uncertainty has been resolved and the money has been raised; we are therefore surprised that the NDA was suddenly told by the Treasury that—owing to a technical accounting issue—it might not be able to spend it. (Paragraph 12)

We believe this issue could and should have been addressed earlier. The nature of waste substitution income has been known since the 2004 consultation, if not earlier, and we find it unlikely that the relationship of these contracts to the original reprocessing contracts became clear only immediately before contracts were finalised in December 2007. (Paragraph 13)

5. In Autumn 2006 the Department recognised that there was uncertainty about waste substitution income, a significant element of the NDA's commercial income for 2007/08. As noted in the National Audit Office's report, The Nuclear Decommissioning Authority: Taking Forward Decommissioning (para 3.18) the possibility that there would be a £400 million shortfall in commercial income in 2007/08 led to a review from November 2006 of how that shortfall could be managed, including through finding offsetting savings and the deferral of work on sites owned by the NDA.

6. In February 2007 when notifying the NDA of their budget allocation for 2007/8 the Department and the NDA recognised that there was still a significant degree of uncertainty remaining in relying on income from the waste substitution contracts.

7. The waste substitution contracts and underlying waste reprocessing contracts are exceptional and are highly complex, reflecting both the nature of the activities performed and individual variations between customers. The contracts themselves have been in the process of negotiation for a number of years and the detailed terms of the contracts were not finalised until December 2007.

8. As the terms of the contract were being finalised, the Department, the NDA and its advisers and the NAO looked at the detail of the budgeting and accounting treatment of waste substitution income. As these discussions developed between NDA, BERR, Shareholder Executive and HMT, it became clear that there were doubts about whether the proceeds could be applied in total and immediately to expenditure

9. At the time of the Spring Supplementary, the Department took a prudent position on the NDA's budget, based on the information available at the time having taken into account advice from NDA's advisers. This indicated that on the basis of analysis conducted up to that point, there would be a requirement to recognise the revenue over the life of the original reprocessing contracts rather than being able to apply the proceeds immediately and in full in 2007/8. Therefore, at this stage the prudent course of action for the Department was to submit a bid to cover the shortfall in NDA's budget that would then result.

10. On 21 April 2008 the NAO submitted their final paper setting out their opinion on the proposed accounting treatment of WSI. Their conclusion is that the NAO considers the NDA's proposed accounting treatment to recognise all of the WSI in 2007/8 is reasonable. With the accounting treatment confirmed, the budgeting treatment usually follows suit. This will allow the Reserve Claim and additional funding provided by BERR at the Spring Supplementary to be repaid.

NDA Derogation

The previous existence of a derogation allowing the NDA to recognise the income from some long-term contracts upon receipt suggests that the NDA, the Treasury and the Department should already have been alert to the fact that the accounting treatment of long-term contracts might need to be considered. We are therefore surprised and disappointed that when this issue reappeared, albeit in a different context, everyone appears to have been caught unawares. (Paragraph 16)

11. The response to this is addressed in detail in the accompanying report, "NDA Budgeting Shortfall 2007-08—Lessons Learned Report."

The 2005/06 derogation could have been the basis for a solution that would not have involved spending £256 million of the Department's accumulated EYF and claiming on the reserve. We would like to know if this was considered as an option once the issue came to light and, if it was rejected, for what reason. Given the references to the derogation in the Estimate Memorandum we would like to know whether any party wrongly assumed that the derogation still applied and if not—as seems likely from the evidence we received—why the Estimate Memorandum made reference both to the derogation and the date of its expiry in April 2006. (Paragraph 17)

12. Reinstating the derogation was rejected as an option for funding the shortfall in the NDA's budget as it would have the same cost for Government as providing additional funding through End Year Flexibility and from the Reserve and would also be less transparent.

Spring Supplementary Estimate Memorandum

The Spring Supplementary Estimate Memorandum did not give an entirely accurate picture of the situation. Accuracy in such documents is always essential, but for such a large request for additional funding at such a late stage in the financial year, this is particularly regrettable. These differences between the Memorandum's version of events and what we were told in evidence suggest poor communication between the Department and the NDA, which might have played some part in the situation occurring in the first place. We expect that future Estimates Memoranda will be drawn up after close consultation between the parties involved. (Paragraph 21)

13. The Memorandum on the Spring Supplementary Estimate was prepared by the Department on the prevailing understanding of the issue at the time—i.e. that the need to recognise WSI under the principles of long-term contract accounting had resulted in a potential shortfall in NDA budgets in 2007/8 which needed to be addressed through the use of End Year Flexibility and a Call on the Reserve. This was essentially a snapshot during a time of intense co-operative work between BERR, NDA, HMT, the NAO and external advisors to determine the correct accounting treatment for the complex waste reprocessing contracts and the substitution contracts. BERR, NDA and HMT also worked closely together to prepare evidence for the Committee hearing. The Department accepts that it is crucial that all parties involved communicate fully on issues around the Estimates Memoranda.

Impact on the Department

We recognise that, due to the provision in the Spring Supplementary Estimate, there has been relatively little impact on the NDA, despite the sums of money involved. We are concerned, however, that accounting uncertainty had the potential to impact drastically upon the NDA's funding of decommissioning of existing nuclear liabilities. We urge the Government to resolve this issue as soon as possible in a way which will not delay future spending on decommissioning. (Paragraph 25)

14. The waste substitution income contracts are highly unusual in that they combine significant complexity with very high value (hundreds of millions of pounds). As a result, the question of whether the income could be recognised in 2007/8 had a very substantial impact both on the Department's and the NDA's budget.

15. The Spring Supplementary Estimate process ensured that the NDA's decommissioning expenditure commitments were safeguarded. However, for commercial income contracts of such complexity it is inevitable that there will be some degree of uncertainty over income levels until the NAO sign-off the accounts.

16. The Department will continue to work with the NDA and its advisors and the NAO to ensure that any areas requiring accounting judgements are highlighted and well understood in order to minimise levels of uncertainty at year end.

Sir Brian told us that the precise sequence of events that led up to the requirement for an additional £303 million is the subject of a review within the Department, HM Treasury, the NDA and the Shareholder Executive. We look forward to receiving the Permanent Secretary's promised note outlining its findings and any action to be taken. In particular, we would like to know exactly when and how this issue came to light, what advice the Department gave to the NDA, what advice the Treasury gave to the Department, what grounds there were for the Treasury's apparent insistence on spreading this income over several years and what action will be taken to ensure that such issues are identified sooner in future. (Paragraph 26)

17. The points in paragraph 8 of the conclusions and recommendations in the report are addressed in the accompanying report, "NDA Budgeting Shortfall 2007-08—Lessons Learned Report."

Funding the NDA

Public funding for the NDA will almost certainly have to increase significantly in the coming years over and above current plans. If nuclear decommissioning is going to be carried out as planned this has major implications for the Department for Business, Enterprise and Regulatory Reform, which already spends over 40% of its Departmental Expenditure Limit on the NDA. (Paragraph 31)

18. Government spending on the NDA will increase by over £0.8bn in the Comprehensive Spending Review 2007 (CSR07) compared with Spending Review 2004 settlement; this is equivalent to annual average real growth of 4.9%, reflecting the Government's commitment to ensure the UK's civil nuclear liabilities continue to be managed safely, securely and cost effectively. The level of public funding for the NDA will be reviewed in future Spending Reviews, recognising the need to strike a balance between what is desirable and what is affordable, while ensuring site safety.

19. We have issued formal budget allocations for 2008/9 and indicative budget allocations for the remainder of the CSR period that reflect the Department's settlement and are unaffected by the action taken on the NDA in the Spring Supplementary Estimates.

We welcome the assurance given by the Permanent Secretary that the Department's budget will be insulated from the NDA for 2008/09 and subsequent years and look for further specific assurances from Government that NDA funding requirements will not impact on other areas of the Department's work. Government departments that have experienced funding problems in one area of their activities have often had to make reductions in other unrelated areas. The scale of the NDA as a proportion of BERR's overall budget makes such a prospect completely unacceptable in this case. (Paragraph 32)

20. The NDA's budget is ring-fenced within BERR's budget. Current arrangements are that all BERR budgets (including the NDA) are managed within the overall Departmental Expenditure Limit. As such, should additional funding be needed for the NDA in future years BERR will first look to non-ringfenced budgets to make good the shortfall: this is a standard budgeting arrangement and ensures resources are allocated as efficiently as possible within the department and across Government and better enables the Government to manage its total finances.

We believe the NDA's funding model is unsustainable. We note the Department's assurances that a solution has been found for the current Comprehensive Spending Review period. However, in view of the volatile—and declining—nature of the NDA's commercial income we are sceptical about how watertight such an assurance can be. Nuclear decommissioning is too important to be left to the mercy of changing priorities in the Treasury and uncertain commercial income; as the Permanent Secretary acknowledged, a new system of funding is needed, and work on this needs to begin urgently. (Paragraph 37)

21. The NDA was set up to deliver the Government's commitment to dealing with the nuclear legacy, which was not being sufficiently addressed by either BNFL or UKAEA, neither of which had decommissioning as a priority.

22. The NDA is funded by a combination of Government funding and commercial income. This duality of funding provides an incentive for NDA to optimise the returns from its commercial assets but does present a challenge as a number of these assets are ageing and therefore operationally unpredictable. Since the NDA was created the amount being spent on decommissioning and liabilities management has very significantly increased year on year. The NDA's total spend was £2.4 billion in 2005/06; £2.6 billion in 2006/07; and is forecast to be around £2.7bn in 2007/08. Government funding has increased proportionately more at £1.2 billion in 2005/06, £1.5 billion in 2006/07 and £1.8 billion in 2007/8. Commercial income is volatile and over time is declining as sites progressively close and move into the decommissioning phase.

23. The funding model was originally selected because it incentivises NDA to make the best use of its existing assets for revenue generation, minimising decommissioning costs for the taxpayer, whilst providing ring-fenced funding from BERR's budget.

24. Government has agreed that it will consider whether there are changes that could be made to the NDA funding model to better enable its funding to be managed effectively while maintaining the right incentives and controls. It has been agreed that these options will be considered by HMT in advance of the next spending review.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 21 July 2008