Select Committee on Communities and Local Government Committee Second Report


Conclusions and recommendations


1.  We recommended last year that details of the new partnership agreements CLG is forging with the stakeholders responsible for delivery of its policy goals should be set out in the Annual Report so that we might judge their scope and effectiveness. This has not been done. We repeat the recommendation for future Annual Reports. (Paragraph 4)

2.  The Department needs urgently to tackle persistent concerns about its ability to deliver across the range of policies for which it is responsible and its ability to influence its strategic partners. (Paragraph 7)

3.  The Department must continue to expand its analytical capability and to ensure that its staff possess the full range of skills its arms-length delivery chains require. Negotiation, brokering and persuasion are not the traditional levers of a Whitehall delivery department, and nor are they easy skills to find or to measure. The Secretary of State recognises that those skills are essential to the success of her Department and its ability to meet its public service agreements. The Department's stakeholders remain to be convinced that they are sufficiently embedded in its staff and culture. We share their doubts. (Paragraph 9)

4.  We commend the work CLG has done with its partners on the Decent Homes programme, which is indeed an example of outstanding local government delivery. We express deep disappointment, however, that the Department proved unable to co-ordinate the work required down its delivery chains sufficiently to achieve its initial target of bringing all home up to decent standard by 2010, and we seek a clear indication of what will be done to improve those homes which will not be upgraded by then. (Paragraph 12)

5.  Slower response to fires is a worse service. Even if 80 per cent of fire deaths occur before an emergency call is made, speed of response still matters in the remaining 20 per cent of cases, to those who may be injured by fire and to the owners of property on fire. We recommend that research into the impact of traffic on response times be extended to consider means of achieving quicker response. (Paragraph 17)

6.  We welcome the introduction of a new, sharper PSA for community cohesion as part of the 2007 CSR process. However, we are concerned that performance in this area is being measured entirely against perceptions of cohesion, and not against more objective criteria of disadvantage such as rates of employment, educational attainment or housing standards. In addition, the new performance indicators focus on the national picture, and we recommend that CLG look beyond the precise terms of its high-level PSA target to seek to influence change in local areas where cohesion is in question or where new threats to cohesion arise. (Paragraph 21)

7.  The fact that CLG wrongly reported itself as being on course to meet its Equality PSA target is not only unacceptable but a further indication of confusion about precisely what the Government wants to do in this area, what mechanisms it means to employ, and how urgently it needs to act. (Paragraph 22)

8.  Responsibility for gender equality rested with the Department for Communities and Local Government for little over a year before passing to the Government's new Equalities Office. During the three-year period of the PSA targets set in 2004, responsibility also rested at times with a Women's Unit within the Cabinet Office and with the Department for Work and Pensions. We welcome both the new Office and the creation of a new PSA as part of the CSR 2007 process. We recommend strongly that responsibility for achieving the targets set under that PSA remain with a single body throughout the period of their existence to enable the maintenance of a continued, coherent focus on their achievement. (Paragraph 23)

9.  In 2005, we criticised the Department for overstating its achievements in its Annual Report. Simply omitting to mention failures such as the troubled implementation of HIPs is no less unacceptable. (Paragraph 25)

10.  For the Permanent Secretary to suggest HIPS could not be introduced because there were not enough inspectors is casuistry. There were not enough inspectors because CLG first watered down and then repeatedly delayed the introduction of HIPs. (Paragraph 26)

11.  CLG's failure to engage effectively early enough with stakeholders is both one of the principal reasons why HIPs were delayed and a further example of the Department's inability to build the relationships it needs if it is to succeed in taking partners with it across the whole range of policy. (Paragraph 28)

12.  The long and tortuous process of introducing Home Information Packs signals another failure of delivery on CLG's part, and the reasons for that failure lie in poor preparation and a retreat by the Department's ministerial team. (Paragraph 32)

13.  We can only conclude that decisions to delay the introduction of Home Information Packs and then to phase them in for homes of different sizes across a period of months were taken on political rather than economic grounds, owing more to a failure of nerve in the face of vocal opposition from the press and others than to the general conditions prevailing in the housing market itself. (Paragraph 32)

14.  The fact that FiReControl is progressing towards completion is, of course, to be welcomed. However, the fact that the Department cites a project two years behind schedule and 50 per cent over its initial IT budget as an example of how it is improving its delivery mechanisms highlights the persistent challenge that CLG continues to face. It needs urgently to establish what the NAO calls "a reputation amongst its partners for having enough strategic influence to solve problems within Whitehall that are creating obstacles to local success." (Paragraph 36)

15.   We commend Mr Housden for ensuring that this year's Annual Report was produced on time and those in his team who have produced a report to a far higher standard than has been the case in previous years. (Paragraph 37)

16.  The Report would benefit further from a consolidated table pulling together the information set out individually in separate chapters on each Public Service Agreement target. (Paragraph 38)

17.  We recommend that relevant information from the Technical Note on PSA target achievement be included in future Annual Reports to enable easier checking of progress. (Paragraph 38)

18.  Our adverse comments on the Department's provision last year of full and clear information to Parliament and the public have led to significant improvement in its provision of information, particularly in the answering of Parliamentary Questions, the clarity and detail of the Annual Report, and the much more informative estimates memoranda provided to Members of Parliament. We urge the Department to continue to seek and implement such welcome improvements. (Paragraph 43)

19.  We remain concerned about the perceived existence of bullying, harassment and discrimination. Two years of work has brought no appreciable improvement, in spite of the time and money spent on courses and the clear desire of senior managers in the Department to solve a chronic problem. Nor can the Department or the Permanent Secretary be complacent on the grounds that other Departments perform just as badly. We recommend that CLG review the effectiveness and value for money of its actions over the past two years with a view to refocusing its efforts (Paragraph 46)


 