Venues in the Olympic Park
67. The Olympic Park will contain five new sporting
venues: the Olympic Stadium, the Aquatics Centre, the Velopark,
a sporting arena to be used during the Games for handball and
commonly referred to as the Handball Arena, and the mixed-use
Eton Manor site. There will also be one major venue suitable for
commercial use: the International Broadcast Centre and Main Press
Centre. Different venues are at slightly different stages on the
road from concept through to construction; but all sporting venues
have been the subject of detailed discussion between LOCOG and
international and national sports bodies.[111]
68. Some of the main venues are unique in design.
As a proposition for a construction company they are, in the words
of the Chairman of the ODA, "unusual".[112]
The Institution of Civil Engineers pointed out that the 2012 Games
construction programme was being undertaken at a time of major
growth in the global construction industry, which enabled contractors
to be selective when bidding for work. As
the Committee of Public Accounts has observed, the ODA has experienced
difficulties in achieving competition for the main venues.[113]
Several contractors have withdrawn from tenders for ODA projects,
sometimes because of commitments elsewhere.[114]
Mr Armitt, Chairman of the ODA, told us that there was considerably
more competition for more standard infrastructure projects in
the Olympic Park, which constitute the vast bulk of the work and
which had generally attracted a "normal" level of interestbetween
four and six bids each.[115]
Nonetheless, there is a clear risk that where the field is limited,
or even limited to a single expression of interest which is acceptable,
the ODA will be in a weak position to strike a deal on terms which
are advantageous to the public purse.
The Olympic Stadium
69. The Olympic Stadium is the single largest venue
and the one where most progress has been made. A cost figure of
£496 million was announced on 10 October 2007; an outline
design concept has been finalised and launched; a consortium led
by building contractors Sir Robert McAlpine Ltd. has been awarded
the contract to build it; and work is expected to begin in May,
three months ahead of schedule.[116]
70. The design for the stadium was announced on 7
November 2007. It features a sunken bowl built into the ground,
accommodating the field of play and lower permanent seating, as
well as a cable-supported roof providing cover for two-thirds
of spectators, and a fabric curtain "wrapping" round
the structure, providing "additional protection and shelter
for spectators".[117]
The design has generally been well received and acknowledged as
being both practical and suited to legacy use, even if not particularly
radical.[118]
71. The intention for the Stadium after the Games
is that it should "deliver a sustainable all-year round sporting
and community legacy" and that it should be a "living
stadium" accessible to local people and communities.[119]
A commitment was made in the bid that athletics would be at the
core of the Stadium's legacy use. That commitment has been sustained,
and the Stadium will be capable of staging national and international
athletics events, as well as premier league rugby and non-premiership
football.[120]
72. Seating capacity during the Games will be 80,000;
but only 25,000 seats will remain once the Games have ended. The
decision on seating capacity was taken with the future multi-purpose
use of the Stadium in mind. 25,000 was judged to be the optimum
for athletics events, given that the biggest regular event in
the British athletics calendarthe UK Grand Prix currently
held at Crystal Palaceattracts a crowd of approximately
20,000. UK Athletics (the national governing body for the sport)
spoke of "the clear preference of athletes, broadcasters
and spectators [
] for a packed stadium, creating an inspirational
atmosphere".[121]
We note that the permanent seating capacity at the Olympic Stadium
will not be enough to allow it to host the biennial athletics
World Championships, which typically generate an attendance of
50,000 or more.[122]
73. UK Athletics told us that the Stadium "will
represent a major boost to athletics in the UK when it is delivered
in full legacy mode".[123]
It expects that the Stadium will "be the focus for an annual
programme of high quality events", including international
events and domestic competition for athletes of all ages, which
it believes can inspire future generations and maintain the profile
of the sport among young people after the 2012 Games have taken
place.[124] UK Athletics
told us that it had had to lobby "very hard" to ensure
that there was a roof above spectator seating in legacy mode as
well as provision for a warm-up track, which it viewed as "critical
for community use" and essential in enabling bids for future
major championships to be made.[125]
The Host Boroughs welcomed the decision to allow for an athletics
warm-up track in legacy mode.[126]
74. At the time that our previous Report on preparations
for the 2012 Games was published, there was uncertainty about
whether a major football or rugby club would become an "anchor
tenant" for the Stadium, thereby ensuring regular use and
providing a more secure financial future. Although discussions
with the most local Premier League football teamWest Ham
Unitedhave come to nothing,[127]
there remains the possibility that Leyton Orient Football Club
or a rugby union club might adopt the stadium as their home ground.
The Host Boroughs lamented the "missed opportunity"
to reach an agreement with a Premiership football club, a solution
which it believed would have provided a "strong financial
cornerstone" and "embedded community programmes".[128]
Business in Sport and Leisure voiced similar regrets.[129]
The Host Boroughs have nonetheless signalled their commitment
to work towards the long-term viability of the Stadium under the
proposed multi-purpose use, a solution which the Mayor of Newham
described to us as "quite an imaginative and innovative legacy
development".[130]
The Chief Executive of the LDA spoke of "serious negotiated
interest from rugby and football professional bodies" in
use of the Stadium, at a level which suggested to him that they
believed that it could work.[131]
He told us that there were expressions of interest from three
football and rugby clubs as potential anchor tenants.[132]
Only Leyton Orient Football Club has chosen to make its interest
public.[133]
75. We note that the Departments for Culture, Media
and Sport and for Children, Schools and Families have commissioned
a study to explore the possibility of establishing a school at
the Olympic Stadium site after the 2012 Games. The school would
"complement, rather than replace, the legacy use of the stadium
field of play". The panel undertaking the review is expected
to provide final advice to Ministers by June 2008.[134]
Aquatics Centre
76. A competition to design the Aquatics Centre was
won in January 2005 by Zaha Hadid Architects. The distinctive
winning design was applauded by Lord Rogers for its "exceptional
sculptural quality" and was described as "outstanding"
and "spectacular" by the then Chief Executive of London
2012.[135] In November
2006, it was announced that the design would be changed and that
Centre would be smaller, with the roof area reduced in size from
35,000m2 to 14,000m2. The ODA describes
the new design as being "just as visionary and exciting"
as the original and points out that it retains an "eye-catching
wave-shaped roof symbolising the flow of water in aquatic sports".[136]
77. On 8 April 2008, the ODA announced that Balfour
Beattythe sole remaining bidderhad been awarded
the contract to build the Aquatics Centre. Work will begin in
summer 2008 and should be completed by 2011. The ODA also announced
that the budget for the Aquatics Centre itself would be £242
million and that the budget for the land bridge which will form
part of the roof of the venue is £61 million. Figures include
contract costs, an allowance for inflation, VAT and legacy conversion
costs.[137] We understand
that Sport England will make a contribution of £40 million
to the £242 million budget for the Centre itself.[138]
The total budget for the Aquatics Centre£303 millioncontrasts
with figures cited in press reports earlier this year suggesting
that the ODA was negotiating to keep the cost of the centre to
between £160 million and £170 million rather than the
£213 million reputedly sought by Balfour Beatty.[139]
It dwarfs the $117 million/£73 million quoted in the Candidature
File.[140]
78. After the Games, the Aquatics Centre will offer
two 50 metre swimming pools and a 25 metre diving pool, allowing
a mix of elite and community use.[141]
Permanent seating capacity in legacy mode will be 2,500, with
scope for a temporary increase to up to 3,500 for events such
as the European Championships and the International Paralympic
Committee World Disability Swimming Championships. We note that
the Centre would be only a "support venue" for any World
Championships hosted in the UK.[142]
79. British Swimming and the Amateur Swimming Association
(ASA), the governing bodies representing the professional and
the amateur sectors of the sport, envisage that the Aquatics Centre
will be "the premier swimming facility in the UK" after
the 2012 Games and will be heavily used for competition, attracting
future international events. They also point out that the Centre
could provide a venue for more training of coaches and teachers,
something seen as essential if participation levels are to grow.
We note that the number of athletes from the London area who reach
international status in swimming disciplines lags behind the rest
of the UK, possibly because of the historic underprovision of
50-metre pools in the London area.[143]
There are presently only two 50-metre indoor pools in London (at
Crystal Palace and in Ealing), although a third pool is due to
open in Hillingdon in 2009.[144]
By comparison, Paris has 18 indoor 50-metre pools, Berlin has
19, and Amsterdam, with a fraction of the population of London,
has three. The disparities are also reflected at national level,
with 23 indoor 50-metre pools in the UK, ninety in France and
ninety-two in Germany.[145]
80. In evidence to our previous inquiry into preparations
for the 2012 Games, the London Borough of Newham (in which the
Aquatics Centre is to be located) told us that it believed that
it was vital that the Centre should include "leisure water"
in legacy mode if it was to be fully valued and used by the local
community. Our awareness of the limited community use of aquatics
centres in legacy mode in certain previous Host Cities (Seoul
and Athens in particular) led us to recommend in our previous
Report that the design of the London Aquatics Centre should provide
"for a mix of leisure use and traditional "lane"
swimming".[146]
Agreement has now been reached that the design of the Aquatics
Centre should include an extension to the main complex, including
dry as well as wet play facilities, "subject to finance".[147]
The London Boroughs of Newham and of Tower Hamlets have agreed
to make a capital contribution to the costs of developing and
constructing the leisure water facility, in exchange for a commitment
to its continuing operation and affordable access to the Centre
for Borough residents.[148]
We welcome the willingness
shown by all parties involved in determining the legacy use of
the Aquatics Centre and associated facilities to reach a conclusion
which is in the interests of local residents. We are, however,
alarmed that the Aquatics Centre will cost over four times more
than the forecast provided in the Candidature File submitted in
2004. The concept of the Aquatics Centre might be spectacular
and eye-catching; but the saga so far suggests it has been over-designed
and, with respect to the robustness of its legacy use, will be
an expensive way of providing facilities for water sports needed
during and after the Games. We are concerned that the ODA only
managed to attract one firm bidder for the project, who would
clearly have been aware of the huge level of contingency available
to the Games as a whole. We note that in the press release of
8 April 2008, announcing the award of the contract, the ODA stated
that "The total of £303 million has not changed throughout
the procurement process". We find this simply incredible
and call upon the ODA to provide a detailed justification of this
statement and of the cost increases at each stage from the initial
design to the signing of the contract with Balfour Beatty for
the Aquatics Centre and the £61 million "land bridge".
In our opinion, the history of the Aquatics Centre shows a risible
approach to cost control and that the Games organisers seem to
be prepared to spend money like water.
Velopark
81. No contractor has yet been appointed to build
the Velopark; but the budget is now £80 million (including
a contribution of £10.5 million from Sport England[149]
and funding from Transport for London and the Lee Valley Regional
Park Authority), as opposed to the $46 million/£29 million
cited in the Candidature File.[150]
As with the revised budget for the Aquatics Centre, the new figure
includes the contract price, allowance for inflation, VAT and
legacy conversion costs. The outline design concept has been agreed
and will consist of a stadium (the Velodrome), seating 6,000 spectators,
and a BMX track during the Games, with a one-mile road cycling
circuit, a mountain bike course and a cycle speedway course being
added for legacy use. The ODA expects to select a contractor shortly;
and construction is due to start in 2009. All legacy facilities
are to be owned and managed by the Lee Valley Regional Park Authority,
which will provide revenue funding.[151]
82. British Cycling told us that the cycling facilities
at the Velopark had "the potential to be absolutely world-class"
and that they "should be the very best anywhere in the world".[152]
There has nonetheless been a certain amount of controversy about
the extent to which the Velopark will offer a suitable replacement
for off-road facilities at the former Eastway Circuit, lost when
land was assembled by the LDA for incorporation into the Olympic
Park. The design currently proposed by the ODA for the Velopark
offers most of the facilities previously available at Eastway,
albeit in a more fragmented layout. British Cycling, despite being
supportive of the proposed design for use during the Games and
despite anticipating that, after the Games, the Velopark will
"provide a boost for cycling",[153]
initially lodged objections to the relevant planning applications
on the grounds that they did "not provide an adequate or
comparable replacement for the road and off-road facilities provided
to cycling on the Eastway Circuit". British Cycling is now
satisfied that the ODA has taken on board its concerns and that
current plans for the Velopark offer an acceptable replacement
for Eastway. The Eastway Users Group, which has campaigned for
off-road cycling facilities in the Velopark in legacy mode, remains
frustrated by the uncertainty about future provision, and it has
pointed out to us that facilities at Eastway closed before the
ODA or LDA had provided any suitable temporary alternative, causing
much of the 2007 competitive season to be lost.[154]
Limited facilities are now available at a site in London Docklands
and work is well advanced on a more suitable temporary replacement
site at Hog Hill in Redbridge.
83. It would
be perverse and wrong if the facilities available to cycle sports
in London were to be less extensive after the Games than before
them. We are satisfied, however, that plans now being proposed
for the Velopark will not only provide a stadium and facilities
of the highest quality at the Velodrome but will also offer an
adequate replacement for off-road facilities previously available
at the Eastway Circuit. We encourage the ODA to confirm the plans
currently being proposed.
Handball Arena
84. The Handball Arena will be a permanent 6,000-seat
venue, to be retained in situ in legacy mode on the western side
of the Park, to the south of the media centre. After the Games,
the arena will be converted to an indoor multi-sport centre with
a retractable seating arrangement, serving as a training and competition
venue and a regional home for a range of indoor minority grassroots
sports, with a likely focus on basketball.[155]
A "concept design" team has been appointed, and the
ODA expects to award the contract to design and build the Arena
in early 2009.[156]
No up-to-date baseline cost has been announced.
85. The Host Boroughs told us that "the range
of legacy sports identified for the Arena matched the identified
need in the surrounding boroughs", and they noted assessments
which appeared to substantiate the basis for the Arena's viability
after the Games. Anchor tenants are being sought; but the ODA
and the LDA see the local boroughs as having a key role in helping
to build a local base of community users.[157]
In our previous report on the Games, we voiced scepticism about
the future of this arena.[158]
It is too early to tell whether our initial scepticism was well-founded.
Eton Manor
86. Eton Manor, an area to the north of the Olympic
Park, will be a training base during the Olympic Games and the
venue for wheelchair tennis and archery during the Paralympic
Games. Plans for the site have changed since submission of the
Candidature File.[159]
Under present proposals, the Eton Manor site will include a hockey
arena after the Games, comprising two competition standard pitches
with seating for up to 5,000 around one of the pitches, as well
as a tennis centre with indoor and outdoor tennis courts, and
an indoor commercially-operated five-a-side football centre.[160]
The Chief Executive of LOCOG cited the plans for Eton Manor as
an example of how LOCOG and the ODA had listened to local representations
and responded accordingly.[161]
Media and Press Centres
87. The site to be developed for the construction
of the International Broadcast Centre and the Main Press Centre
lies within the London Borough of Hackney.[162]
An idea of their scale can be gained from the specification: during
the period of the Games themselves, the two media centres will
provide a combined gross internal floor area of 120,000m2
for broadcast and print media.[163]
There are two consortia on a shortlist to design, build, finance
and operate the two centres. The Chairman of the ODA described
the centres as "one of the most complex buildings" housing
"probably the largest journalistic activity which takes place
across the world every four years". He pointed out the high
cost of failing to provide the media with the wherewithal to do
their jobs.[164]
88. The ODA's view is that, in legacy mode, the buildings
housing the two media centres will "have the potential to
provide significant legacy employment and space for business which
should become the economic driver for the whole area around Hackney
Wick".[165] The
Mayor of Hackney, Jules Pipe, recognised the potential of the
media centres to change the reputation of the area and argued
that the site was "absolutely ideal" as a centre for
media and creative industries.[166]
The ODA confirmed to us that press reports that it was considering
a future for the media centres as a supermarket distribution depot
were inaccurate.[167]
No budget has yet been announced
for the Media and Press Centre and we urge the Government and
ODA to disclose this as soon as possible. In the meantime, given
the huge cost increases recently announced for other venues, we
await this announcement with trepidation.
Relocatable venues
89. Various facilities, including temporary arenas
for volleyball and basketball and pools for water polo, were described
in the Candidature File as being temporary venues which could
be demounted at the end of the Games and allocated elsewhere in
the UK "to provide a sporting legacy in the regions".[168]
Relocation might apply to the venue shell, the field of play,
courts, seating or fit-out elements.[169]
Mr Coleman, speaking on behalf of the Mayor of London, observed
that there was "a huge amount of what can appear quite incidental
but is actually very valuable equipment [
] that will be
left after the Games and which will need to be reused".[170]
90. Responsibility for brokering any relocation of
facilities and determining future use of equipment procured for
the period of the Games rests with Sport England, which has undertaken
a market testing exercise to establish what appetite for the structures
exists among national governing bodies of individual sports, local
authorities and others. In all, 72 expressions of interest were
received, from all parts of the UK. Sport England told us that
the bids were being evaluated "with a view to having further
discussion".[171]
We asked Sport England who would bear the costs of relocating
facilities. Sport England replied that "we are not at that
stage yet of looking at the financial implications with regard
to the relocation of those facilities".[172]
A week later, however, the Minister for the Olympics told us that
relocation costs would be borne by recipients.[173]
91. As a result of changes to the Olympic Park Masterplan
in January 2006,[174]
volleyball events will take place not in the Olympic Park but
at Earl's Court. There is now some uncertainty about the venue
for fencing events, with press reports suggesting that these would
be held at the ExCel Centre in Docklands rather than at a temporary
venue to be constructed in the Olympic Park.[175]
Lord Coe told us in December 2007 that final decisions had not
yet been taken but that using existing facilities as venues "has
to be a sensible way of approaching things".[176]
The ODA's Programme Delivery Baseline Report, however, states
that "as part of the review of scope, the responsibility
for delivering the fencing venue has been transferred to LOCOG"
and that "any change to the plans previously agreed with
the IOC/IPC will be subject to International Federation and IOC/IPC
approval".[177]
LOCOG is now undertaking a review of temporary, relocatable venues,
"to make sure that they remain the best option and that "where
possible, they maximise any opportunities that have become apparent
since the bid". The review is to be completed later this
year.[178]
92. The relocation
of temporary Games venuesor elements of themwas
portrayed in the Candidature File as an innovative way of sharing
some of the physical legacy of the Games around the UK. We are
concerned at signs of a creeping reduction in relocatable venues.
Every decision not to construct a temporary relocatable venue
reduces the scope for the nations and regions to share in the
physical legacy potential of the Games. We also believe that placing
a requirement upon those acquiring such facilities to cover the
costs of relocation, something which was not made clear when expressions
of interest were invited, will kill off much of the interest.
We recommend that the Olympic Delivery Authority or the London
Development Agency should cover the costs of relocation, particularly
as the alternative may be demolition or dismantling at the LDA's
or ODA's expense.
Shooting events
93. There is dispute over the merits of the proposed
venue for shooting events. The site initially selected and featured
in the Candidature FileBisley in Surreywas dropped
after the International Olympic Committee (IOC) reviewed venues
and indicated that the family of Games venues needed to be "more
compact". The substitute site is the Royal Artillery Barracks
in Woolwich, where partially enclosed shooting ranges of different
lengths will be constructed. Once competition had finished, all
facilities will be removed.[179]
LOCOG told us that the Woolwich site had been "signed off"
by the IOC, the International Shooting Sports Federation (ISSF)
(as international governing body) and the national governing body
(the Great Britain Target Shooting Federation, then chaired by
Mr John Hoare).[180]
94. The UK's national governing body for shooting
is now known as British Shooting and is chaired by Mr Phil Boakes,
who is adamantly opposed to the Woolwich site, as are all British
Shooting's constituent bodies. Mr Boakes favours instead a site
at Dartford which could provide a permanent legacy facility to
international standards. In his view, the Woolwich site is also
too small, is located in an inappropriate urban environment, and
permits only three shotgun layouts, extending the time needed
to complete the event programme.[181]
He disagrees that the national governing body "signed off"
the Woolwich venue.[182]
95. LOCOG told us that, in July 2004, it had sent
the Great Britain Target Shooting Federation plans showing how
shooting events at the Royal Artillery Barracks in Woolwich would
be staged and had invited its Chairman, Mr Hoare, to take part
in a site visit. It said that "following such consultation
and receiving no negative feedback", it had submitted plans
for use of the Woolwich venue to the ISSF, which had confirmed
its support for the site in September 2004. It added that Mr Hoare
had confirmed the support of shooting governing bodies for the
venue in February 2005. LOCOG is considering the relocation of
components of the Woolwich venue as well as assessing "what
might be sustainable on the site". It also observed that
Dartford Council had informed it of "the unsuitability of
developing Games-time and legacy facilities for shooting"
at the Dartford site proposed by Mr Boakes.[183]
96. There is considerable strength of feeling within
the shooting sports that to hold shooting events at the 2012 Games
in the Royal Artillery Barracks in Woolwich will be a lost opportunity
for shooting and will do little if anything to provide any legacy
for the sport. On the other hand, the Dartford site proposed by
British Shooting is not ideal as a Games-time venue. Events at
the Games must be presented to an audience which is wider than
the established base of enthusiasts: this is the distinction between
Olympic and Paralympic Games on one hand and national or international
championships on the other. The argument for keeping the range
of venues as compact as possible is also a strong one. We
accept that it is now probably too late to find an alternative
site for shooting events at the London 2012 Games, and we therefore
accept, with reservations, LOCOG's policy of retaining shooting
events at the Royal Artillery Barracks in Woolwich, a site which
is likely to be attractive to the general public. However, we
regard it as highly regrettable that the site chosen for shooting
events is not one which commands the support of any of the constituent
bodies of British Shooting, and we believe that more should have
been done to explore alternative sites before the decision to
select the Royal Artillery Barracks was taken. We believe that
LOCOG should acknowledge that its proposals for shooting events
at the 2012 Games offer almost no legacy outcome for the sport.
We recommend that LOCOG should work with the shooting bodies to
try to extract maximum long-term benefit for the sport and that
it should cover the costs of relocating facilities from the Woolwich
site to permanent sites for shooting sports.
Overall legacy strategy for Olympic
Park venues
97. The ODA's approach to investment in the Park's
legacy potential is set out in the Programme Delivery Baseline
Report, published in January 2008:
"The ODA investment is concentrated on providing
the maximum legacy benefit, installing infrastructure that is
a known requirement to provide the strategic backbone for future
development, whilst not restricting the freedom of the ultimate
legacy owners, operators and investors (public and private). After
the Games, much of the land will be opened up as development sites,
with the assumption that developers will contribute to the costs
of further infrastructuresocial, physical and economicthrough
planning conditions and agreements".[184]
98. There has been a major break from previous Host
Cities' practice, which was to consider legacy use of venues at
a later stage of the programme. As the Chairman of LOCOG said:
"All our thinking in terms of design of facilities
is predicated on what we use them for afterwards. The world has
changed [
] and leaving facilities in a community that, frankly,
cannot use them in any credible way afterwards is not what this
Games is about".[185]
The Chairman of the ODA made a similar point; he
observed that discussions on legacy use and design were taking
into account views on which sports were likely to take place at
a particular venue in legacy mode, what seating capacity might
be necessary and how much space might be needed for car parking.[186]
Business in Sport and Leisure acknowledged the work already
done on legacy use of facilities.[187]
99. The London Development Agency has been designated
as the "interim legacy body for the Games". It told
us that it had responsibility for:
- "Acting as the legacy
client and establishing a robust post-Games legacy structure for
the future management of the parklands and venues;
- Delivering the legacy master plan for the Games
through a legacy master planning framework process;
- Establishing and delivering a development strategy
for the land and legacy;
- Leading the legacy and business planning process
for the Olympic parkland and venues;
- Securing the socio-economic and sporting benefits
arising from the Games".[188]
100. The LDA has begun work to produce a planning
framework for the Olympic Park site after the Games. A team was
appointed in January 2008 to develop a "Legacy Master Framework",
which is to "set out the vision for the legacy of the Olympic
Park and its relationship with the surrounding communities".[189]
An Olympic Park Regeneration Steering Group has been established
to "oversee" development of the Framework. The Group
consists of the Minister for the Olympics and London, the Minister
for Housing and Planning, the Mayor of London and the leaders
of the Host Boroughs.[190]
101. The Mayor of London's Office and the LDA told
us that in taking forward its various functions, the LDA was working
closely with key partners, including the Government, the ODA,
the London Thames Gateway Development Corporation, the local boroughs
and the Lee Valley Regional Park Authority.[191]
The Host Boroughs stressed the importance of providing timely
information on site development and potential impacts on local
communities[192] and
said that "engagement is actually getting better all the
time";[193] and
they prize their membership of the Olympic Park Regeneration Steering
Group.
102. As a parallel exercise to the development of
the Legacy Master Framework, Grant Thornton and Partners has been
appointed to develop an outline business plan for the transformation
and longer-term management of the Olympic site after the Games.
The LDA told us that the objectives of the business plan will
be "to provide a robust funding and delivery model for the
Park and venues in legacy, and to ensure their use is viable and
sustainable on a long-term basis".[194]
The Chief Executive of the LDA put it another way, saying that
the aim was "a model which balances commercial delivery as
well as community and socio-economic outcomes".[195]
103. The twin processes of drawing up a planning
framework which will permit the establishment of sustainable communities
and of identifying the optimal model for ownership and operation
of venuesand the Olympic Park itselfare inextricably
linked. The Chief Executive of the LDA told us that the Legacy
Master Framework should be completed in March 2009,[196]
and he implied that announcements on both the planning and the
management aspects would be made "around spring 2009".[197]
We note, however, recent Parliamentary Written Answers suggesting
that decisions will be taken sooner, during 2008.[198]
104. A large part of the preparation of the business
plan is likely to involve a market testing exercise to assess
what scope there will be for individual venues to be self-financing
in legacy mode. It may turn out that the most robust model in
the long term would be for local authorities, perhaps as a consortium,
or for a specially constituted body with trust status, or what
the Chief Executive of the LDA described to us as a "special
purpose vehicle",[199]
to operate and maintain the Olympic Park and the various venues
as a unit. Greenwich Leisure Limited, an operator of leisure facilities
in the London area, told us that it would be "comfortable"
with the LDA or the five Host Boroughs as possible owners or operators
"in their approach as public guardians of the service".[200]
We note that the Lee Valley Regional Park Authority already owns
the land on which the Velopark will be located and that it will
own and manage the Velopark facilities.[201]
Press reports have suggested that the Authority might in due course
become the eventual manager of more of the Olympic Park than just
the Velopark.[202]
Another option might be for venues to be managed from a fund to
be established by contributions from private sector firms engaged
in developing housing in the Park.
105. Whatever the final outcome, there are certain
considerations which the LDA will need to take into account. We
set out some of these below.
Density of development
106. The expectation is that approximately 4,000
housing units (at least 30% of which will be affordable housing)
will be created from the Olympic Village, the residential complex
where athletes will be accommodated during the Games. The development
will include a school and a health centre. Approximately 5,000
further units will be created from other development parcels released
by removal of temporary venues and infrastructure.[203]
107. The Host Boroughs expressed some anxiety to
us that pressure to maximise revenue from sales of land and property
could limit the quality of space and could lead to "unacceptable
densities of housing development and/or inappropriate forms of
economic activity, undermining the ability to create sustainable
communities".[204]
Mr Coleman, speaking on behalf of the Mayor of London, clearly
recognised that Host Boroughs had "very strong interests
and desires that we ensure that the development strategies which
take place are appropriate in line with their plans and are producing
new, sustainable communities"; and he noted that this was
an issue to which the Mayor was personally committed. He stated
categorically that "there is no question of us actually adopting
an approach which says: 'We are going to maximise value come hell
or high water'". He also gave an assurance that the planning
framework would encompass a broad range of different types of
housing, 44% of which would be family housing.[205]
He acknowledged, however, that adjusting the mix of housing on
the post-Games Olympic Park site will be one of the methods by
which revenues from land and property sales might be massaged
if there was doubt that the necessary level of returns would be
achieved.[206]
108. Decisions
on the intensity of development and the nature of housing on the
Olympic Park site will have long-lasting consequences. The provision
of sustainable communities should be the top priority for the
site. Given that applications to develop land within the Park
boundaries will undergo the usual planning process, we are reassured
that the local authorities concerned will have a degree of control
over the scale and type of development in the Olympic Park after
the Games. The Mayor's Office acknowledged to us the importance
of a sustainable legacy for the Olympic Park; we urge the Government
and the LDA to respect that acknowledgement as the years pass
and the pressures to extract maximum value from sales of land
and property increase.
Economics of sporting facilities
109. The Minister for the Olympics told us that the
question of how ongoing revenue costs of venues' legacy facilities
would be met was something which "will be negotiated on a
venue by venue basis".[207]
The Chief Executive of the LDA spoke of the desire "to minimise
the revenue subsidy" for the venues, in part by maximising
usage.[208] The costs
of operating a community leisure facility can be substantial:
Business in Sport and Leisure told us that the average total subsidy
required for sports and leisure facilities in the UK was £500
million per annum; and we note that the average annual subsidy
required to operate a local authority sports and leisure facility
has been estimated at £262,000 per annum.[209]
Business in Sport and Leisure added that "it is not clear
who will meet the revenue costs for the Olympic facilities over
the next 25 years".[210]
The Host Boroughs said that "securing sufficient funding
to deliver and sustain a high quality legacy will require appropriate
capital and revenue funding";[211]
and Mr Armitt, Chairman of the ODA, warned that "sports venues,
by and large, are not particularly profit-making" and that
future commercial returns from the Park were more likely to come
from the Olympic Village and other housing.[212]
110. We suspect that some if not all of the sports
venues remaining in the Olympic Park after the 2012 Games will
need revenue funding to cover the costs of year-round operation
and maintenance. Conservative
assumptions should be made on the commercial potential of sports
venues after the Games. We note the decision
by the bodies funding the 2010 Winter Games in Vancouver to establish
a trust with a form of endowment which will generate enough capital
to cover costs of operation and maintenance for venues where there
appears to be little or no chance of self-financing or of commercial
interest. The Government
should remain open to the establishment of a trust, or similar
vehicle, perhaps with funding pooled from the Exchequer, local
authorities, the London Development Agency and others, to cover
the revenue costs of sporting facilities in the Olympic Park after
the Games have finished.
Affordability for users of facilities
111. There is a delicate balance between on the one
hand operating a leisure centre so that it provides a commercial
return and, on the other, operating a charging regime which enables
enthusiasts and potential high performers to be able to afford
to train regularly, with exclusive use of facilities when necessary.
British Swimming and the Amateur Swimming Association (ASA) warned
that many swimming clubs, many of whose members are under 16 years
of age, "lead a precarious existence, having difficulty in
obtaining access to appropriate pool time at an affordable hiring
charge". They argued that the solution lay in "sympathetic
management" but noted that commercial pressures often prevailed.
British Swimming and the ASA welcomed initiatives in certain areas
to provide access to pools free of charge for children and in
some cases for vulnerable young people; and their joint memorandum
proposed that the Government should lead an assessment of how
concessionary schemes might be made more generally available to
swimming clubs.[213]
Greenwich Leisure Limited drew our attention to the Passport Scheme
operated by the British Olympic Association and the British Paralympic
Association, which gives identified elite athletes free access
to sports facilities run by operators participating in the scheme.[214]
112. We note that the award of Lottery funding from
Sport England as a contribution towards the costs of the Aquatics
Centre and the Velodrome was subject to conditions requiring the
design to take account of legacy use. Sport England also stated
in its memorandum that it would develop funding conditions requiring
future operators of the facilities to "deliver sports development
and community participation outcomes".[215]
We recommend that contracts
to operate sporting facilities in the Olympic Park after the Games
should specify that affordable access should be provided for local
residents and for exclusive use by sports clubs.
Reflecting legacy use in design
113. It is of some concern to us that decisions are
already being taken on venue design and that contracts are being
let for construction only on the basis of a likely legacy use
and before a future tenant has been confirmed. Business in Sport
and Leisure told us that it was "essential that the LDA tender
the contracts to operate these facilities as soon as possible"
and that "without strong operator input at the design stage,
there is a real danger that the facilities will be inoperable
in legacy mode".[216]
The Institution of Civil Engineers warned of a risk that "belated
requirements" from legacy owners, once they had been identified,
could delay the design and construction process.[217]
114. We note that the stadium designed for the Commonwealth
Games in Manchester was built with a legacy tenant and use identified:
it became the home ground for Manchester City Football Club. The
Mayor of London has been quoted as saying that "it is really
inconceivable that anyone would have signed up to occupy a stadium
before they could see it";[218]
but it seems to us perfectly possible for a potential tenant or
operator of a venue to be able to draw enough information from
an outline design to be able to register interest and perhaps
become involved in negotiations, particularly if there is an opportunity
to shape the final design.
115. The Host Boroughs summed up the dilemma:
"We recognise that the design development of
the Park and key venues for the Games is now reaching critical
path decision points and that decisions must be taken to ensure
infrastructure is delivered on time for the Games. At the same
time many of these decisions will establish critical "fixes"
which will determine the scope of subsequent legacy opportunity".[219]
Jules Pipe, the Mayor of the London Borough of Hackney,
gave the IBC/MPC as an example, saying that once a construction
consortium had been appointed, it was "absolutely vital then
that that consortium and the ODA talk to the array of broadcasters
and recording industry people and others that we have put together
that we want to see as the end-users, because they are saying
to us they are not going to be interested in taking on that venue
afterwards if they have not had some input into the spec, and
it is something that they will be interested in".[220]
116. The ODA defended the principle of proceeding
with letting contracts for construction before either end-use
or legacy tenant had been confirmed. Taking the International
Broadcast Centre/Main Press Centre as an example, it argued that
"What you do not do today is decide [
] precisely how
[a] building was going to be used in 2013-14". It said that,
instead, "what you do is say: what is the nature of the use
and which of the two bidders is likely to give more flexibility
for the LDA and the local authorities to determine how best they
see the balance between accommodation, between housing, between
office use, between factory use, whatever people have in mind
for what is a very significant building?"[221]
117. We recognise
that the priority is to ensure that venues are built in good time
for the Games, and we accept that a possible six-month delay while
commitment is secured from a future tenant could introduce a serious
threat to the programme timetable. We also accept that strenuous
efforts have been made to involve sports governing bodies and
other interested parties in discussions with the ODA and the LDA
on venue design. Nonetheless, by proceeding with design and construction
withoutin some caseshaving confirmed a legacy operator
or owner, the ODA runs the risk of building structures which need
significant expenditure in post-Games conversion if they are to
be attractive to future tenants or operators.
105 The Lee Valley Regional Park Authority has leased
83 acres of land to the LDA, enabling the LDA to grant a licence
to the ODA allowing construction work to begin. See Lee Valley
Regional Park Authority Annual Report for 2006-07, page 5 Back
106
Ev 76 Back
107
Ev 89 Back
108
Q 258 Back
109
Ev 90 and Q 319 Back
110
Page 3 Back
111
Ev 40 Back
112
Q 166 Back
113
Fourteenth Report from the Committee of Public Accounts, Session
2007-08, The budget for the London 2012 Olympic and Paralympic
Games, HC 85, paragraph 25 Back
114
Ev 160 Back
115
QQ 166-7 Back
116
ODA Press Release 8 April 2008 Back
117
Ev 120 Back
118
See for example Jonathan Glancey, The Guardian, 8 November
2007; also the Times and the Financial Times, 8
November 2007 Back
119
Ev 77 Back
120
Ev 77 Back
121
Ev 4 Back
122
Ev 4 Back
123
Ev 2 Back
124
Ev 4 Back
125
Q 38 Back
126
Ev 92. The land on which the warm-up track used for the Games
themselves is sited is likely to be returned to Network Rail.
The legacy warm-up track will be built on a different site. See
ODA Programme Delivery Baseline Report, January 2008, page 39,
Back
127
The Olympic Board agreed on 7 February 2007 that the inclusion
of a Premier League football club in the legacy plan for the Stadium
would require design changes which would introduce unacceptable
delays into the timetable for its construction and completion.
See Government response to the Second Report of Session 2006-07
from the Culture, Media and Sport Committee, London 2012 Olympic
Games and Paralympic Games: funding and legacy, Cm 7071, page
12 Back
128
Ev 92 Back
129
Ev 148 Back
130
Q 333 and Ev 92 Back
131
Q 278 Back
132
Q 279-80 Back
133
Q 309 Back
134
DCMS Press Release 008\2008, issued on 29 January 2008 Back
135
London 2012 Press Release 31 January 2005 Back
136
London 2012 Press release 27 November 2006 Back
137
ODA Press Release 8 April 2008 Back
138
See Ev 107 Back
139
Building 22 February 2008 Back
140
Table 6.6.2b, Volume 1 Back
141
Ev 77 Back
142
Ev 8 Back
143
Ev 6-8 Back
144
HC Deb 8 October 2007 col. 334W and 23 October 2007, col. 211W Back
145
Information provided by British Swimming Back
146
Second Report from the Committee of Session 2006-07, HC 69-I,
paragraph 107 Back
147
British Swimming, Ev 7 Back
148
Ev 92 Back
149
Ev 107 Back
150
Table 6.6.2b, Volume 1 Back
151
ODA Programme Delivery Baseline Report, Januiary 2008, page 17;
see also ODA Press Release, 8 April 2008 Back
152
Q 39 Back
153
Ev 1 Back
154
Information from Eastway Users Group Back
155
Ev 78 and 93. See also the ODA Programme Delivery Baseline Report,
page 44 Back
156
ODA Press Release 2 April 2008 Back
157
Ev 93 Back
158
Second Report from the Committee, HC 69-I, Session 2006-07, para
111 Back
159
Ev 92 Back
160
Ev 78 Back
161
Q 177 Back
162
The site was changed following a re-appraisal of venue locations
in the light of the success of the bid. See London 2012 Press
Release 30 January 2006 Back
163
ODA Programme Delivery Baseline Report, January 2008, page 87 Back
164
Q 207 Back
165
ODA Programme Delivery Baseline Report, page 18 Back
166
Q 333 Back
167
Q 183 Back
168
Candidature File Volume 2, page 25 Back
169
London 2012 Olympic and Paralympic Games Annual Report, January
2008, published by DCMS, page 28 Back
170
Q 282 Back
171
Q 362 Back
172
Q 365 Back
173
Q 484 Back
174
Ev 64 Back
175
The Guardian, 3 December 2007 Back
176
Q 212 Back
177
ODA Programme Delivery Baseline Report, page 51 Back
178
Ev 64 Back
179
ODA Programme Delivery Baseline Report, page 56 Back
180
Q 214 Back
181
Ev 164-6 and 177 Back
182
Ev 175 Back
183
Ev 176-7 Back
184
ODA Programme Delivery Baseline Report, page 12 Back
185
Q 86 Back
186
Q 172 Back
187
Ev 148 Back
188
Ev 77 Back
189
London 2012 Olympic and Paralympic Games Annual Report, January
2008, published by DCMS, page 10 Back
190
Officials from bodies represented by Group members and from the
London Development Agency, the ODA and the British Olympic Association
also attend as appropriate. Back
191
Ev 77 Back
192
Ev 90; Q 320 Back
193
Q 320 Back
194
Ev 77 Back
195
QQ 285 and 286 Back
196
Q 276 Back
197
Q 276. See also Q 310 Back
198
HC Deb, 4 March 2008, col. 2308W Back
199
Q 285 Back
200
Q 334 Back
201
ODA Programme Delivery Baseline Report, page 17 Back
202
London Evening Standard 20 November 2007 Back
203
ODA Programme Delivery Baseline Report, January 2008, pages 15
and 16 Back
204
Ev 91 Back
205
Q 299 Back
206
Mr Coleman Q 305 Back
207
Q 483 Back
208
Q 277 Back
209
Review of national sport, effort and resources, April 2005,
page 20 Back
210
Ev 148 Back
211
Ev 91 Back
212
Q 178 Back
213
Ev 10 Back
214
Ev 94 Back
215
Ev 108 Back
216
Ev 148 Back
217
Ev 161 Back
218
Financial Times, 8 November 2007 Back
219
Ev 90 Back
220
Q 333 Back
221
Q 172 Back