Select Committee on Culture, Media and Sport Written Evidence


Memorandum submitted by the Institution of Civil Engineeers (ICE)

INSTITUTION OF CIVIL ENGINEERS

  1.  The Institution of Civil Engineers (ICE) is a UK-based international organisation with over 75,000 members ranging from professional civil engineers to students. It is an educational and qualifying body and has charitable status under UK law. Founded in 1818, the ICE has become recognised worldwide for its excellence as a centre of learning, as a qualifying body and as a public voice for the profession.

  2.  The Institution has chosen to focus its comments only on the issue of the preparation of the venues for the Games.

PROGRESS IN PREPARING VENUES, BOTH WITHIN THE OLYMPIC PARK AND ELSEWHERE

PROGRESS IN DELIVERY

  3.  The ODA has been tasked to deliver the infrastructure for the 2012 Olympics at a time of major growth in the global construction industry. This activity has impacted on the both the cost of materials and labour globally and will inevitably effect the costs of delivery of the venue. New Civil Engineer magazine has reported that construction inflation in the London region is likely to remain at around 6.5% in the period up to 2011 when the majority of work on the venues will be complete.[5]

  4.  High growth in London, the UK and the rest of the world has already led to several contractors withdrawing from tenders for ODA projects. For example Hochtief withdrew from the tender process for the aquatics centre and gave the public explanation that this was due to their having taken on significant work abroad. Given the current circumstances this reduction in competition can be expected to continue. It can also be anticipated that engineers, with expertise in the delivery of major projects, including sports venues will be receiving opportunities for work on many other prestigious projects.

  5.  It is noted that the ODA has tightly controlled the budget for the delivery of venues and infrastructure and that other projects may appear to be more profitable and carry less contractor risk. The requirement for transparency from consortia and their supply chain as to their costs must be enabled by the chosen procurement/contractual approach. This will help in ensuring more certainty in the final delivery costs for the project. There must also be a fair distribution of risk.

  6.  The ODA has chosen to package the tendering of the games into projects that are manageable by only the largest organisations in consortia. This may impact on the London2012 aims of delivering a legacy in local integration as contractors opt for surety over uncertainty of supply.

  7.  In addition it is understood that some key venues still do not have "legacy owners". When they are on board, the ODA must guard against the risk that their belated requirements may delay the design and construction process.

  8.  ICE remains confident that, through the use of the NEC contract to procure the games, the venues and infrastructure will be delivered to the timescale indicated. However, lead times for materials and plant are currently increasing and so early start dates will reduce the risk of any overruns.

INCLUSIVENESS

  9.  The ICE has a positive approach to equality and diversity and has been working in London to broaden the inclusion of those involved in London2012. The original aim was that Londoners across the spectrum would build the Games. This has yet to be realised.

  10.  As the design phase for the venues and infrastructure draws to a close we do not believe that there has been any discernible change in the composition of gender, ethnicity or disability within the design teams. It is therefore more likely that any legacy will be delivered in the supply chains of those companies constructing the games. However, at present the mechanisms for the delivery of this are fragmented and unfocused on delivering broader inclusion. ICE is encouraged by the commitment of Crossrail to the same legacy goals and would encourage the DCMS to support an organisation to coordinate this.

November 2007







5   More Cash, Less Spend, New Civil Engineer, 17 October 2007. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 30 April 2008