Select Committee on Defence Minutes of Evidence


Examination of Witnesses (Questions 60-79)

GENERAL SIR KEVIN O'DONOGHUE KCB CBE, DAVID GOULD CB AND LIEUTENANT GENERAL DICK APPLEGATE OBE

29 JANUARY 2008

  Q60  Mr Jenkins: Therefore, things are getting better?

  General Sir Kevin O'Donoghue: They are certainly better.

  Q61  Mr Jenkins: Can you tell us what the benefits are of through life capability management?

  General Sir Kevin O'Donoghue: Through life capability management is all about bringing together all the lines of development: doctrine, manpower and training, not just equipment and equipment support. If we go down the through life capability management route properly the equipment capability area—the main building—will pull together those various strands and take account of all of them when making decisions about capability. In the past we have bought things, supported them when they have come into service, thought about the manpower needed, the doctrine, and the infrastructure to house whatever it is in a not very coherent way. There are some good examples from the past, but by and large it has not been done very coherently. Through life capability planning and management will bring all of that together in a plan owned by DCDS(EC) and directors of equipment capability and managed by the IPT.

  Q62  Mr Jenkins: So, what is the benefit?

  General Sir Kevin O'Donoghue: The benefit is that we are not wasting money by buying something that is too big for the garages or we do not have soldiers trained for it, that is, buying something that comes into service next year and we have not trained the soldiers to be ready to operate it at the same time. It is a matter of coherence.

  Mr Gould: An example is the patrol vessel HMS Clyde which we have not bought from Vosper Thornycroft. We are buying from them five years' worth of ship time. What Paul Lester at VT says is that he believes the cost of building that ship to make it reliable so he can meet the terms of the contract is probably in the region of 5% higher than it would be to sell ship time. One of the big benefits of Through Life Capability Management and through life management plans for projects is the ability to invest upfront in something that will be cheaper and easier to maintain and subsequently to modify and improve throughout its life. When you do not have a through life approach you do not have a mechanism for doing that trade which says you should invest early for long-term benefits. We also plan with our suppliers how to provide support. Therefore, on the A400 aircraft which I am sure we will return to even before the first one has been built we are looking at what arrangement we shall put in place to support and maintain that aircraft through its life rather than doing it as an add-on later in the programme. In terms of total equipment plan even for that there is an enormous benefit to come. If we also look at training, doctrine, use and so forth we shall also make sure that we get the benefit out of the equipment in military terms more quickly than we can by doing all these things sequentially which was what tended to happen.

  Lieutenant General Applegate: I think that from a user's perspective we cannot have confidence that we will be able to grow incrementally if there is no plan in place. Therefore, it would be difficult for me to say to the front line user he should trust us because what he is getting is only the first step and later on there will be improvements. He may ask me to prove it or show him how we have prepared for that. Do we have a technology road map which will identify where it is possible to introduce that? Is the electronic architecture capable of enabling that to be brought in? Do we have the necessary skills? Is the relationship with the industrial sector right or does the industrial sector even exist to do it? What do I have to do in order to confirm the requirement and when I might want it? What difficult choices might I have to make about whether to invest in the upkeep of a particular system or its replacement? I think that through life management planning is fundamental to the development of improved trust between members of the defence team rather than something which in the past was too adversarial.

  Q63  Mr Jenkins: Therefore, something like the acquisition of Apache helicopters some of which were placed into a big hangar and somebody was paid £24 million to wipe the dust off them and keep them maintained because we had not trained the pilots could never happen again?

  Lieutenant General Applegate: I would hope the chances of it happening again are hugely reduced, but I never say "never". Unfortunately, the world has a tendency to surprise one.

  General Sir Kevin O'Donoghue: It should not happen by default. In future we shall know and make decisions on what we want to do.

  Q64  Mr Jenkins: This was a great idea which came up in the defence review of 1998. Why has it taken so long to get it imbedded in the MoD?

  General Sir Kevin O'Donoghue: I think the defence review in 1998 referred to through life equipment planning and management. That was what the DPA and DLO attempted to do. I do not believe that it concerned the whole capability or all the defence lines of development. DPA and DLO were trying to do through life management planning of the equipment and its support through life, with some success in some areas. A very good example is special projects and those have been through life IPTs for a long time. With the best will in the world, with an acquisition IPT in Abbey Wood and a support IPT in Wyton for aircraft or Andover for vehicles, to create that through life equipment plan was quite a challenge. That has been enabled by putting together the two organisations and sorting out the budgets.

  Q65  Mr Jenkins: I am glad you have gone to budgets. Do you have in mind a programme that has not gone down this route and one that has? What are the financial benefits, or any other benefits, of going down this route? Can you give an example of where it has paid off?

  Mr Gould: An example of a programme that has not gone down this route is Apache. You have referred to a very good example of what happens when you do not do a proper through life plan and get the brief right at the early stage of procurement. The pressure was to spend the money to get the aircraft and then the rest of the problems could be sorted out later. That might be the right decision but it has a consequence. If you do that you know what the consequence is. A good example of through life planning and technology management, production, logistics support and constant technology refresh in response to threat changes in the area of special projects is electronic counter-measures to which General O'Donoghue referred earlier. All of that derived from work in Northern Ireland. By having a constant stream of technology work and refresh we were then able to make adjustments and do modifications or build new systems to cope with threats that emerge very rapidly in today's operations. If you do not have that long background of technology management and planning how do you manage the equipments, distribute them and get the information into the equipments that make them effective on the day? If we did not pay attention to that all through life we would not be able to do what we are doing today. Therefore, today's through life success depends on long-term equipment and technology planning from the past. I would say exactly the same thing about nuclear, biological and in particular chemical protection equipment which is a good example. What we are able to do today is the result of a very long-term technology programme that also produces projects in future.

  Q66  Mr Holloway: To pay up front to support the kit in the future sounds absolutely marvellous, but how on earth are you supposed to do that when most of your budgetary considerations are short term and everything is rather over-heated? By way of example, the carriers cost £3.9 billion. Is that the through life cost?

  General Sir Kevin O'Donoghue: No.

  Mr Gould: That is the demonstration and manufacturing cost.

  Q67  Mr Holloway: Is what you have been talking about for the past five minutes more an aspiration than what you are actually doing?

  General Sir Kevin O'Donoghue: It is an aspiration in that the Defence Acquisition Change Programme started 10 months ago, but the offshore patrol vessel (OPV) referred to earlier is a very good example of this. We need to instil this in everything we do as we go forward and to recover some of the programmes already in existence is quite difficult.

  Mr Gould: But DE&S has a very detailed through life management plan to go with it.

  Q68  Mr Jenkins: I understand that you are discussing methodology here and how systems work. While I appreciate that a big and complex programme needs this device do all programmes require it? Where is the cut-off point? When do you decide that it is not suitable for a particular programme?

  General Sir Kevin O'Donoghue: In my view all programmes need a through life management plan. The detail of that plan will vary. If it is a big, complex project, for example the carriers, it will need a detailed plan; if it is a small project it still needs a through life management plan but it could be relatively simple.

  Q69  Mr Jenkins: The MoD is now moving on to "improved through life costings using simple models, to support through life decisions". When will the improved models be developed? When will they be implemented and used? If we are to look at through life costings with the use of these models, which programmes will they be and how much do you see going towards the original manufacturer to maintain the through life programme on our behalf under the defence industry strategy approach that you are now developing? How do you see it developing?

  General Sir Kevin O'Donoghue: If I may answer the second point first, I do not see industry running our through life management programmes; I see them being done jointly. To go back to the start of a project where you are competing for a particular programme, we will have our project team and each competitor will have his project team. As soon as you go to the preferred bidder you should co-locate those project teams so that geographically they are in the same place. As soon as you sign up to a contract you should merge those teams into a joint team. The through life management plan will then be held jointly. Industry has a big part to play in it; it is not something that you hold at arm's length from industry.

  Q70  Mr Jenkins: Therefore, in future as far as the first part is concerned you do not envisage the transfer of some of these functions and therefore the nuclei of the bodies in the MoD into industry?

  General Sir Kevin O'Donoghue: Not those functions, no.

  Q71  Mr Jenkins: That is not part of the plan?

  General Sir Kevin O'Donoghue: No.

  Q72  Mr Jenkins: Does the structure and expertise you get depend on the nature and amount of the programme? If you cut the programme will it have an effect on the size and cost of the team?

  General Sir Kevin O'Donoghue: Yes.

  Q73  Mr Jenkins: Therefore, if there were eight Type 45 destroyers on the books but we had placed orders for only six would it have implications for the viability of the team?

  General Sir Kevin O'Donoghue: I am sorry; I did not understand. No. You change the numbers from eight to six. You have a through life management plan and you know when you will insert technology and when various things have to be changed either for reasons of obsolescence or to upgrade because of the threat. If you doing it to eight instead of six the cash numbers will be different but the plan in words will be the same.

  Q74  Mr Jenkins: If we have the carriers and the nuclear submarine replacement on the books and you hope to do this for both big projects how do you get the manpower and skills required in place, or what plans do you have to put it in place?

  General Sir Kevin O'Donoghue: Some of the skills we need to draw in from outside. As far as the successor programme is concerned there are not many places to draw nuclear engineers from outside. We need to train our own, and we are doing that. We are drawing in people and looking at universities that produce nuclear graduates, but some programmes come out like the carriers and other programmes diminish; they are either in steady state or the equipment is coming out of service and people can move across.

  Mr Gould: They are quite different. As you know, in the case of the carriers we have built an alliance of a number of companies to do that programme because it must be thought of as something that we do perhaps once every 50 years. It is not a continuous programme. This country has never built a 65,000-tonne warship, so it is quite unusual. We have a core team comprised of DE&S direct employees, both service and civilian engineers, but added to those most of the design work is being done by alliance partners. The production engineering work will be done by people in the shipyards which will have to augment their people while they do that phase of the project. But as one goes through the manufacturing phase into final assembly and introduction into service those numbers will diminish. We will have a small core team that continues and around that alliance partners will change over time. Submarine building, whether it is for SSNs or SSBs—ballistic firing or attack submarines—is a specialised business both for us and industry. It includes not just nuclear engineers but engineers who have familiarity with and main knowledge of submarine building. It is quite unlike anything else. In that area I have to plan on the basis that we will keep a group of submarine people in the cluster—the people who build all the submarines—at pretty much a constant level. That will be a group of several hundred people who have long-term expertise, memory and training and new people will come in; and the same is true in industry. They need to keep a core workforce of about 3,500 at Barrow which is our specialised yard. It must be tuned to that; you cannot allow it to vary too much or you will literally forget how to build a submarine and when you start to try to do it again you get into big trouble.

  Q75  Chairman: That depends on orders, does it not?

  Mr Gould: It does. You take a very big risk if you have erratic submarine orders.

  Q76  Chairman: You do not know what the orders will be, do you?

  Mr Gould: But I have a very good plan. We now have three contracts on the Astute class; we have a fourth where initial contracts are already being placed. We have a design for cost reduction contract and long lead items on the reactors for the fifth boat. We need to keep going at that rhythm to use the Astute learning to build into the successor programme to make sure we do not lose those skills and collective memory as we go through.

  Q77  Robert Key: I want to turn to costs. In our report on the MoD annual report and accounts published yesterday we noted that the Defence Procurement Agency had met all its key targets in 2006/07 for the second consecutive year, which was very good news. Do you expect that the DE&S will meet the former DPA targets for 2007/08?

  General Sir Kevin O'Donoghue: We will meet the cost and performance targets but I do not think we will meet the time target, for which there are good reasons that I can go into if you wish.

  Q78  Robert Key: The MoD Autumn Performance Report stated that the major programme showing cost growth at present continued to be Nimrod MRA4. What is going on with that programme?

  Mr Gould: We have something which usually happens on aircraft programmes, that is, an overlap of production with flight trials. As you know, we have let the production contract for MRA4. The flight trials are going well but what happens is that you finally discover some things that need subsequent modification as you go through the production programme. There has been a problem of pitch on the aircraft, which is not unusual; it happened also on the MRA2, but the MRA4 has much bigger wings and more powerful engines. We cannot solve it in the same way and so we will have to make a stability modification on the production aircraft to deal with that problem. That accounts for about half of the cost growth referred to in the interim report. The other half is the cost of converting the three trial aircraft. There are three prototype aircraft doing the trials and the plan is to convert those to the production standard. The total we are talking about is £100 million which is just a little less than 3% of the total programme cost.

  Q79  Chairman: You say it is not unusual. If it happened with the earlier version this was predictable?

  Mr Gould: It was predictable, but you cannot do any kind of system or flight trial test, or the test of any sophisticated equipment, until you have built the prototype; that is the first time you can test it against reality. I am quite sure that all sorts of simulations, wind tunnel tests or anything else you can think of were gone through in this programme and the problem was not identified at that point. Therefore, although it occurred on the MRA2 it would have been a low probability. Unfortunately, low probability but high impact risks occur during testing.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 27 March 2008