Memorandum submitted by the Environment
Agency
SUMMARY
Carbon Capture and Storage (CCS) has the potential
to play a key part in the global battle against climate change.
The Environment Agency believes that significant work is still
necessary to prove CCS and the government should hedge against
any risk that a failure to deploy CCS prevents us meeting our
climate change targets.
Specifically our submission highlights:
CCS is the only option that, at present,
may bridge the gap between projections of global fossil fuel burning
and the need to reduce global emissions.
CCS is not the solution to climate
change. CCS can only be used at large point sources and, even
here, the greatest and most cost effective mitigation option remains
cutting energy demand.
CCS is not yet technically proven
at a commercial scale. The new Kingsnorth power station would
not be built if CCS was made a requirement.
Kingsnorth and any other new fossil
fuel power stations should be built carbon capture and storage
ready and this should be required under Section 36 of the Electricity
Act 1989.
The Government's proposed CCS demonstration
is an important contribution to deploying CCS. The Kingsnorth
project, if approved, seems to offer the earliest opportunity
to proceed with the demonstration.
There remain a series of barriers
to deploying CCS where more action should be taken and encouraged
by government. In particular around:
developing a framework for funding
and building CO2 pipeline networks;
further work to map and prove
the suitability of prospective storage locations;
work to understand the health
and safety risks associated with CCS; and
work to gain public confidence
in CCS.
1. INTRODUCTION
We have a range of statutory responsibilities
for protecting resources and limiting and adapting to climate
change in England and Wales.
We are responsible for the regulation of the
major CO2 point sources in England and Wales under the Environmental
Permitting Regulations[3]
and the EU Emissions Trading Scheme. These would apply to the
proposed new coal fired power station at Kingsnorth.
2. CARBON CAPTURE
AND STORAGE
2.1 Background
CCS is a potential mitigation option to achieve
the greenhouse gas stabilization pathways that would prevent the
most catastrophic impacts of climate change.
Coal fired power stations are the largest CO2
point sources combining long operating life (30-50 years) and
the highest relative CO2 emissions per unit of electricity generated.
In the UK, CCS is intrinsically linked to new coal build with
E.ON's proposals at Kingsnorth the forerunner.
We believe that whilst the decision on regulating
CCS at Kingsnorth is important, it needs to be considered in the
larger national and international context of climate change mitigation.
2.2 The potential benefits and limitations
of CCS
CCS has the potential to reduce CO2 emissions
from coal plants by up to 90% although it does increase the fuel
needs of the plant by between 10-40%.[4]
Coal will probably continue to meet a significant
and growing proportion of global energy demand until at least
2050. The International Energy Agency (IEA) suggests that coal
demand could as much as double in the 50 years from 2000 to 2050
exceeding 7,000 million tonnes of coal equivalent. In particular,
rapidly developing countries such as India and China are exploiting
abundant coal reserves. In 2006 alone, 89% of 102 gigawatts of
new electricity generation capacity in China came from coal fired
plants.[5]
CCS is the only technology that can bridge these
demand projections with the general scientific consensus that
we need to reduce global emissions by 50% from the 1990 level
by mid-century in order to avoid dangerous climate change.
However, CCS can only be used at large point
sources which are today responsible for 20-40% of global emissions
and roughly 35% of UK emissions and where there are suitable storage
sites. It can only ever be one option in a portfolio of ways to
reduce emissions.
The debate on CCS cannot be allowed to divert
attention from efforts to improve our energy efficiency and develop
renewable energy supplies.
2.3 The technological maturity of CCS
CCS consists of three distinct components: carbon
dioxide (CO2) capture where fossil fuels are burnt, transporting
CO2 most likely by pipelines, and safe, permanent CO2 storage
in geological formations.
CCS is not technically proven at a commercial
scale. Each of the elements has been shown to work, however the
full chain is not yet proven. The Table below is a summary of
the deployment of each stage in the CCS chain for coal fired power
stations.
Stage | State of Development
|
Capture | A number of small scale (few Megawatts) post combustion pulverised fuel trial plants have been established. No large scale capture plant exists worldwide.
The components for an IGCC[6] capture plant have been proven in applications in the chemical and refinery industries. No IGCC power station fitted with CCS has been constructed worldwide.
|
Transport | Transport can be via pipeline or ship. Both technologies are relatively mature. Several thousands kilometres of pressurised CO2 pipelines exist in USA and Canada. Ship transport would be similar to liquefied natural gas.
|
Storage | Storage in oil and gas fields is understood fairly well as it has been going on for 30 years to increase the oil yield by Enhanced Oil Recovery (EOR).
Other storage including saline aquifers which are common offshore from the UK are much less well understood. Large scale projects using the Sleipner aquifer in the North Sea have shown that it is possible to store CO2 safely and monitor its movement reliably. Extensive monitoring over a longer period will be necessary to demonstrate its long term success.
|
| |
The absence of experience with fully integrated commercial
projects means that cost estimates for CCS differ considerably
and have significant uncertainty attached to them (see figure
1).
In addition to this and despite the European Commission's
recent proposal for a Directive on geological storage of CO2[7]
(the draft CCS Directive) the future regulatory framework remains
uncertain.
Figure 1
COST RANGES PER TONNE OF CO2 ABATED AT £2008 PRICES.

Source: Environment Agency using IEA,[8]
Poyry,[9] IPCC[10]
and EC[11].
For all these reasons we believe that no developer would
currently risk building a new coal power plant that deployed CCS
in the UK.
For the same reasons the government must ensure that new
fossil fuel plants do not prevent us achieving the UK's medium
and long term targets to cut greenhouse gas emissions. There are
a number of ways the government can hedge against this risk. We
believe the principle ways are:
Ensuring that any new fossil fuel plant is built
so that CCS can be retrofitted in the future ie it is carbon capture
and storage ready (CCR).
Taking steps that move CCS forward so that it
can be deployed at the earliest opportunity. This includes, but
is not limited, to the UK's announced CCS demonstration project.
Providing the long term certainty that the UK
will not accept carbon "lock in" should CCS prove to
be either technically or economically unattractive. CCS will either
need to be deployed or new fossil fuel stations will face the
need to buy potentially expensive emission permits, or face domestic
regulation forcing restrictive operation or premature closure
if the EU ETS does not provide sufficient price signals.
The consideration of CCS on new natural gas plants is less
mature than for coal. It is expected that CCS can also be applied
to such plants in the future.
2.4 Carbon Capture and Storage Readiness (CCR)
We believe that CCR is an essential requirement for any new
coal fired power station. We support the recommendations of the
IEA study on CCR[12]
which has also been adopted by the draft CCS Directive.
This sets out four factors to define CCR for coal as:
sufficient space and access requirements on the
original plant to allow capture related equipment to be retrofitted;
feasibility assessments of the retrofitting of
capture equipment;
feasibility assessments of suitable storage locations;
and
feasibility assessments of suitable transport
routes to storage.
The "state of the art" for these factors will develop
rapidly in the next few years. It is important that potential
developments are subject to detailed verification to ensure they
have gone as far as is reasonable.
We estimate that the cost of making a plant CCR based upon
the above definition is modest and certainly less than 0.5% of
the overall capital costs.[13]
The draft CCS Directive proposes mandatory CCR for plants
above 300 megawatts electrical (MWe). This will not be enacted
until at least 2012 and will be too late to apply to the significant
new capacity that may receive planning consent in the UK within
the next few years.
In light of this, we believe that CCR must be made a requirement
for new fossil fuel plants in the UK by an amendment to Section
36 of the Electricity Act 1989.[14]
Section 36 consents have already been used to require CCR
conditions on new gas fired power stations.[15]
2.5 The UK CCS Demonstration Project
It is unlikely that CCS will be deployed before commercial
and technical viability has been proven through a number of demonstration
projects. The European Commission has called for twelve demonstration
projects to be built by 2015 but so far only three countries in
the world, including the UK, have committed to funding such projects.
Therefore, the UK demonstration project is an essential step
on the path to proving and deploying CCS globally. We believe
there is an urgent need to accelerate this deployment. Wide-scale
CCS deployment by 2030 is likely to be too late. We must act to
bring CCS deployment forward to 2020 at the latest. This would
create an argument for the UK demonstration project to be sited
at Kingsnorth, as it appears this is the most advanced proposal.
There remains a need for the European Commission to determine
a funding mechanism for additional CCS demonstration projects.
They could for instance be funded through the proceeds of EU Emissions
Trading Scheme (ETS) permit auction or from the EU budget. The
UK has approximately ten gigawatts electrical of new coal proposals
which have been developed to replace the nuclear and coal generating
capacity that will close between now and 2015. With the right
funding mechanism this could be a significant opportunity for
the UK to play a major leadership role in climate change.
2.6 Support for deployment of CCS
There remains a series of difficulties to the deployment
of CCS that go beyond the CCS demonstration project where the
Government can either take or encourage action.
These include:
promoting a stronger carbon market that will incentive
CCS through the EU ETS price mechanism;
developing a framework for funding and building
CO2 pipeline networks;
further work to map and prove the suitability
of prospective storage locations;
work to understand the health and safety risks
associated with CCS; and
work to gain public confidence in CCS.
3. RECOMMENDATIONS
CCS has the potential to be a key component in the global
battle against climate change. However it remains technically
unproven and has significant economic and regulatory uncertainty.
Our key policy recommendations are:
The UK's CCS demonstration project is a critical
global step. There is an argument to proceed with whichever proposal
can be developed most quickly. This seems to be the Kingsnorth
project.
The CCS demonstration project should be part of
a bigger strategy to support CCS deployment. More work is needed
from government and others in a range of areas in particular around
pipelines and storage locaions.
The government must ensure that any new fossil
fuel power station is built carbon capture and storage ready under
Section 36 of the Electriticy Act 1989.
The government must protect the achievement of
our domestic greenhouse gas targets by hedging against the failure
of CCS to be commercially deployed within an acceptable timescale.
June 2008
3
Formerly the Pollution Prevention and Control Regulations 2000
which implement the EC Integrated Pollution Prevention and Control
Directive 96/61/EC and the Large Combustion Plant Directive 2001/80/EC. Back
4
Carbon Capture and Storage, Defra Science Notes 6, March 2008. Back
5
IEA and CIAB, Clean coal technologies, http://www.iea.org/textbase/papers/2008/Clean_Coal_CIAB_2008.pdf Back
6
IGCC-Integrated Gasification Combined Cycle. Back
7
Proposal for a Directive of the European Parliament and of the
Council on the Geological Storage of Carbon Dioxide 2008/0015
(COD). http://ec.europa.eu/environment/climate/ccs/pdf com 2008
18.pdf Back
8
IEA (2006) CO2 Capture as a Factor in Power station Investment
Decisions, IEA GHG Report No. 2006/8. Back
9
Poyry, (2007) Analysis of Carbon Capture and storage cost supply
curves for the UK, Report for DBERR. Back
10
IPCC (2005) IPCC Special Report: Carbon dioxide capture and storage. Back
11
Regulatory Impact Assessment presented with reference 5 above. Back
12
IEA GHG (2007) CO2 capture ready plant, IEA GHG Report No 2007/4,
May 2007. Back
13
Draft Environment Agency Science Report on Carbon Capture and
Storage Readiness. Back
14
The Consenting Process for Onshore Generating stations above 50MW
in England and Wales. Consents are issued by DBERR. Back
15
Sections 36 consents issued for Combined Cycle Gas Turbines at
Drakelow, Barking, Newport and West Burton all contain CCR conditions.
The extent of these CCR conditions is not made clear. Back
|