Select Committee on Environmental Audit Minutes of Evidence


Supplementary memorandum submitted by BERR

Is a shadow carbon price used to take decisions in relation to consents for new build power stations?

  Economic and commercial considerations are matter for the developer. Thus a shadow carbon price is not a factor in determining a section 36 decision. Similarly, the fact that a renewables project may benefit from the Renewables Obligation is not a factor taken into account in determining such projects.

Why is the shadow price of carbon used by the Government so much lower than that recommended in the Stern report?

  The Shadow Price of Carbon (SPC) used by the Government is consistent with the Stern report analysis. The SPC the UK Government has adopted (£25/ tonne of CO2) is based on the social cost of carbon associated with a 550ppm CO2 stabilisation scenario, as estimated in the Stern Review. As such it makes assumptions about future atmospheric concentrations. The main arguments that have lead the UK to adopt this SPC, based on the Stern Review calculations, are:

    —    it is sensible to assume the world will take substantial action towards an upper stabilisation goal limit of 550 ppm CO2;

    —    using an SPC consistent with the atmospheric concentrations above 550ppm CO2 would lead the UK, or any individual country, to do "too much" relative to other countries and to the goal, would not reflect progress made from business-as-usual, and would ignore the evidence that the optimum range is 450-550 ppm; and

    —    adopting an SPC consistent with concentrations below 550 ppm might lead us to do too little, given current uncertainties.

Information on closure dates of oil wells in the North Sea; the costs of re-opening an oil-well compared to using EOR on an existing oil well

  During the session on 4 June, the Committee invited the Energy Minister to provide further information on what is known about the closure dates of oil wells in the North Sea and the relationship with the timescale for the development of CCS; whether there is information on the cost of reopening an oil well as against using an existing well; and whether the access routes for taking CO2 offshore are constrained by the inward flows of oil and gas.

  The Department gathers annual projections from oil and gas operators on future production levels and the likely dates for closure of every field. The individual projections are supplied on a confidential basis and the information is used to inform the Department's understanding of the timescale for activities on the UK Continental Shelf. The projections must be treated with caution because of uncertainty in the underlying geology and performance of the reservoirs and the timing of field closures is heavily dependent on the oil price. The Department also encourages the extension of the life of oil and gas fields through a number of initiatives and a joint forum with the industry known as PILOT and expects to approve many new field developments over the next decades.

  The closure of an oil or gas field is subject to an approval process and the department must be convinced that the field is no longer economic. The decommissioning of the facilities and wells on the field is then subject to a further approval process where the abandonment programme is examined and companies are required to consider possibilities for re-use ahead of recycling or disposal. The Department has had discussions with several companies which are developing concepts for CCS, are identifying possible oil or gas reservoirs and are discussing them with the current owners. The regulatory procedures are being amended to facilitate such a change of use which could involve Enhanced Oil Recovery in the first phase, under a Petroleum Licence, followed by a pure CCS phase under a CCS licence when the hydrocarbons are depleted.

  The economic viability of re-using facilities and wells for CO2 storage will depend on a number of factors including their location, suitability and the costs of refurbishing or upgrading. Reusing existing oil facilities for EOR and CCS would also require the installation of new equipment to deal with gases from the produced oil for re-injection back into the reservoir; otherwise the injected CO2 will escape from the reservoir when oil is being produced. The costs of drilling a new well will vary dependent on several factors but could be as much as £25 million. Re-using an existing well may be much less costly although the existing well materials may need to be enhanced to provide long term storage integrity. It is unlikely to be cost effective or practicable to re-open a well which has been fully decommissioned and sealed. CCS is unlikely to need facilities on a platform as complex as those required for oil and gas and it may be more cost effective to close down an existing production platform and replace it with a simpler seabed facility purely for injection.

  Although the number of pipelines from the oil and gas fields to onshore terminals is limited there are no proposals to decommission any of these lines and it is apparent that the owners are aware that these trunk lines have potential for re-use on projects including import of gas from outside the UK and storage of hydrocarbon gas to match seasonal demand as well as for disposal of CO2.

Information regarding the capture ready conditions built into the consents given for the gas fired power stations last year

  Section 36 of the Electricity Act 1989 requires any organisation wishing to construct, extend or operate a generating station with a capacity of more than 50MW to gain the consent of the Secretary of State—known as a "section 36 consent". Section 36 consents can impose conditions on the development. If the developer does not comply with any condition of a section 36 consent, the developer is liable to prosecution.

  In the Energy White Paper last Spring, Ministers committed to consult, by the end of 2007, on the principle of, and what was meant by, "carbon capture ready". We delayed publication of this consultation to enable us to ensure that the proposals we were expecting from a planned EU Directive on the storage of carbon dioxide could be taken in to account.

  Drawing on recent International Energy Agency and Intergovernmental Panel of Climate Change studies, we thought it likely that the most significant minimum requirement would be for a power station developer to show that they had enough land at the proposed power station on which to site a carbon capture plant. Discussions with the developers indicated that they too were anticipating this.

  Using past experience of handling provisions for the retrofitting of flue gas desulphurisation plant at power stations, the Department drafted the following condition:

    "The layout of the Development shall be such as to permit the installation of such plant as may reasonably be required to achieve the prevention of the discharge of carbon and its compounds into the atmosphere."

  This condition was voluntarily accepted by the developers of 3 gas-fired power station consented last year.

  The draft EU Directive on the storage of carbon dioxide, published in late January, includes an Article (32) on carbon capture readiness which defines it by four factors. The government is consulting shortly on the principle of CCR, the meaning of the Commission's four proposed factors (space, technical feasibility study of retro-fitting, transport and storage assessments), the combustion stations to which they might apply, and how it might be implemented in England and Wales.

  We would expect that, when a developer wishes to install the carbon capture plant at a later date, as with extensions to power stations now, a further section 36 consent (or in time the appropriate replacement legislation under the Planning Bill before the House this session) would be required.

28 June 2008





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 July 2008