Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by Sir Adrian Stott Bt

BRITISH WATERWAYS

SUMMARY

  1.  British Waterways (BW) has withdrawn from the Cotswold Canals Partnership with respect to the restoration to navigation of the Stroudwater and Thames & Severn navigations.

  2.  This action was taken due to funding constraints on BW, aggravated if not fundamentally caused by unexpected reductions by DEFRA in BW's annual grant.

  3.  This withdrawal has done significant damage to the restoration projects, and to BW's relationship with voluntary waterways organisations in general.

  4.  Two lessons should be learned from this episode:

  5.  (a) By government, that it is essential that BW have a source of funding for the gap between the revenue it can obtain directly from users and the cost of running the waterways, that is secure, sufficient, and consistent every year. This cannot be provided by a variable annual grant. The most appropriate alternative funding is a substantial one-time capital endowment, to allow BW to enlarge the investment real estate portfolio from which it now gains significant income.

  6.  (b) By BW, that it needs a better method of ranking the capital projects it participates in, so that it can rationally cut from the bottom of the list when cuts are necessary, in a manner that will not surprise its partners.

INTRODUCTION

  7.  The following discussion is organised under the following headings:

  8.  The cancellation of BW's participation in the Cotswold Canals Partnership

    —  The cause of the cancellation

    —  Issues raised by the cancellation

    —  Lessons to be learned from this episode

      —  Funding

      —  BW priorities

1.  THE CANCELLATION OF BW'S PARTICIPATION IN THE COTSWOLD CANALS PARTNERSHIP

  9.  BW has often become involved in projects to restore derelict navigations. These are always long-term (multi-year) schemes, requiring the application of substantial capital, much of which must generally be raised by third parties. The lead in such projects is generally taken by parties other than BW, typically nowadays a partnership of public, private, and charitable organisations.

  10.  BW was a member of the Cotswold Canals Partnership on this basis, with the aim of restoring two waterways. Not only was the Partnership depending on BW's financial (and other) contributions to the scheme, but also BW's contribution was key to securing other funding.

  11.  BW abruptly withdrew from the project, cancelling its commitment to provide further funding.

2.  THE CAUSE OF THE CANCELLATION

  12.  BW has made it clear that it would have preferred not to withdraw. However, it feels that the decision was forced on it due to its own financial situation.

  13.  BW had been presented by DEFRA with an unexpected, significant, and ongoing reduction in its annual grant. This had already reduced its net revenue to a level some £25 million/year below its estimate of the cost of maintaining its waterways in a steady state, and placing a substantial strain on its ability to provide financial support to waterway restoration projects.

  14.  A significant breach on the Brecknock & Abergavenny canal, which itself may be attributable to maintenance arrears, resulted in the need for BW to allocate capital to repairs. BW felt that the most appropriate source of that capital was money it had previously earmarked for the Cotswold projects.

  15.  It is clear that BW's withdrawal is a direct result of the grant reductions. Without them, it could, although with difficulty, have handled the Welsh breach without the need to pull money back from the Cotswolds.

3.  ISSUES RAISED BY THE CANCELLATION

  16.  Two principal issues are raised by this cancellation.

  17.  First, BW does not have the financial resources even to maintain its assets. It certainly does not have sufficient or secure enough financing to make long-term capital commitments to external parties.

  18.  If BW's financial support cannot be remedied, the obvious conclusion is that it should enter no more such commitments. Although BW has the potential, and the history, of being of major benefit as a participant in restoration projects, the current incident shows that being an unreliable partner is worse than not being a partner at all.

  19.  Second, the shock caused to the Partnership by BW's abrupt departure shows that the partners were unaware of the fragility of BW's funding, and of how BW would act in a financial crisis.

  20.  This is unfair and damaging to such partners, and to BW's reputation.

4.  LESSONS TO BE LEARNED

4.1  Funding

  21.  Operating, maintaining, and restoring waterways are long-term liabilities.

  22.  It is a core principle of finance that income should match liabilities. Yet the government is keeping BW in a mismatch.

  23.  BW cannot cover its costs through charges on its users. It must have funding to close the gap between the revenue obtainable from those charges and the cost of its waterways maintenance and operation. The public benefits that the waterways provide are very much larger than their fully-funded costs, so the provision of this funding by government is justified. The amount required is known, despite the government appears reluctance to acknowledge this.

  24.  The only question remaining is how best to provide this funding. The method required must securely produce sufficient revenue every year.

  25.  As I have discussed previously, the most appropriate means of providing this funding is probably through a capital endowment to BW. This would allow BW to increase substantially its investment real estate portfolio, which already provides it with significant income.

  26.  Replacing the fundamentally unsatisfactory grant approach with real estate income would give BW the adequate and long-term financial security it clearly requires, but currently lacks.

4.2  Priorities

  27.  BW's reaction to its funding predicament appears to have been ad hoc, with no plan for such an eventuality. The path chosen may not have been optimum. It certainly caused substantial, but avoidable, distress to the Partnership.

  28.  BW has on two occasions established priorities among projects for restoring, enhancing, or creating waterways. The more recent was the 2004 Waterways 2025 exercise. However, this document was based on a poor methodology, and was produced with inadequate consultation. The priorisation it produced was clearly not optimal.

  29.  Since then, BW has been reluctant to update this "vision", or to remedy the serious flaws in it. Now, it apparently has assigned no priorities among the projects in which it participates.

  30.  This means that when cutting back becomes unavoidable, there is no understanding as to which projects should be cut, or how. There is thus no planning for minimising the damage done by the cuts that may have to be made.

  31.  Moreover, in the absence of any understood priorities, BW's Cotswold partners appear to have been unaware that there was any significant risk of BW's withdrawal. This resulted in unnecessary upset and damage to them, and represents unacceptable disrespect and discourtesy to them on behalf of BW.

  32.  As a result, BW should immediately begin work on a replacement for Waterways 2025. The process should include open consultation with all interested parties. This should first be with respect to the criteria to be used for evaluating the priority of projects, and then, once a set of criteria has been chosen, with respect to the application of these criteria to each project to determine its priority.

  33.  Once this priorisation is complete, BW should revisit it annually to update the evaluations where characteristics of projects have changed.

  34.  It should be made clear to all those with whom BW has commitments with respect to projects on the list that, if funding to this aspect of BW's activities must be cut, the cuts will be always be made from the bottom of the list.

  35.  This approach will provide a rational scheme for allocation of the funds BW does have available for such projects. It will allow BW, and those it works with, to plan for the withdrawal of funds where this becomes necessary. And it will give all concerned a clear understanding of the risk of withdrawal for each project.

  36.  This is a relatively elementary approach, and it is regrettable that BW has not been following it. To have done so would have prevented a lot of heartache.

CONCLUSION

  37.  It has been clear for too long that BW's current funding is inadequate in among and inappropriately insecure for the task. It is therefore no surprise that an incident such as the Cotswold withdrawal occurred.

  38.  The solution to providing appropriate funding to BW is known. Despite some ill-advised comments with respect to BW's attempts to generate more revenue, such as criticisms of its move towards market pricing (which, ironically, is a requirement of the government) and of its increased dependence on income from real estate, such attempts are clearly a worthwhile path to follow, as I explained in my previous submission.

  39.  The longer the government refuses to acknowledge the problem, and to adopt the appropriate solution, such problems are bound to arise.

  40.  How long does this have to be?

Sir Adrian Stott Bt

March 2008






 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 1 July 2008