Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Supplementary memorandum submitted by the Department for Environment, Food and Rural Affairs (BW2008 121a)

  The Committee asked me to provide a note on how British Waterways prioritises its investment in restoration projects, with particular reference to the external benefits arising from regeneration.

  I attach a note produced by British Waterways on their process, including the considerations they take into account in seeking approval for investment from the BW Board. I believe this should answer the Committee's questions.

  I will update the Committee on the work of the Inter-Departmental Group on the inland waterways in the summer—its next meeting is planned for June.

Jonathan Shaw MP

Parliamentary Under-Secretary of State (Marine, Landscape & Rural Affairs)

Department for Environment, Food and Rural Affairs

April 2008

PRIORITISING BRITISH WATERWAYS RESTORATION PROJECTS

  British Waterways' overall strategy seeks to expand the waterways network, although not at the expense of the existing waterways in its care.

  Therefore British Waterways uses its revenue resources to maintain the existing canal network using its "Steady State Model" as the basis for prioritisation/allocation of expenditure. Its commercial capital is used to generate commercial revenue that feeds into the overall BW resource mentioned above. Commercial returns are made from a variety of different sources but regeneration involving property development of brown field sites adjacent to the water is an important one.

  Canal restoration may sometimes create opportunities for British Waterways to invest commercial capital on adjacent land to create commercial returns. However, the actual canal restoration is never commercially viable and has to be supported almost entirely by public or volunteer funding. In many cases canal restoration creates increased, albeit marginal, future maintenance costs for BW.

  British Waterways' policy is that it does not in principle contribute capital or revenue to restoration projects. That is because the main benefits, both financial and non-financial, accrue to local organisations and people in the private, public and voluntary sectors. It is therefore right that projects should be driven by local enthusiasm and local priorities.

  In practice, regional development agencies, local authorities and other potential funders including canal societies and lottery funders decide on prioritisation through their willingness (or unwillingness) to provide funds.

  In reality, it is rarely possible for major projects to proceed without any funding input from British Waterways, particularly as more detailed due diligence of schemes tends to realise greater risks than were originally identified in outline proposals. Most funders fix their contribution up front before the full risk assessment is complete.

  Consequently, British Waterways tends to act as funder of "last resort" deciding how much to put in on a practical assessment of a scheme's benefits to British Waterways and to the wider community, its deliverability and the likely risk (of cost overruns etc) involved. There is a three stage formal approval process for making decisions to participate in waterway restoration projects. This process was agreed by the British Waterways Board in June 2005 and is attached as Appendix A.

  Currently British Waterways is having to contribute funding to every restoration project in progress. These contributions are not planned to exceed £2m for any project although the risks involved may eventually require more input than this. This £2 million figure is seen as an upper limit on expenditure and reflects the Board's priorities and current appetite for risk. The Board's appetite for risk will change from time to time reflecting its assessment of external conditions. In this context, the Board's willingness to commit up to £6 million to the Cotswold Canals project reflected a strong commitment on British Waterways' part to help the project go ahead if at all possible.

  BW is currently involved in five waterway restoration schemes, the Olympic-related Bow Back rivers, the Droitwich Canals, the Manchester, Bolton & Bury, the Liverpool Link and the Helix project in Scotland. As already stated in British Waterways' submission to the Committee (in Appendix B),[3] BW's potential contribution in the three restoration projects currently being constructed is in excess of £7.3m (from a total partnership investment of over £53m). In addition, construction work on the £11.5m Droitwich Canals will commence shortly adding a further £2m to BW's total investment.

  This contribution to restoration projects over a three to four year period is in the Board's judgement affordable and justifiable, given the public benefits delivered through canal restoration. This will be kept under review but further commitments would be difficult to justify given current pressures on network spend.

Appendix A

PRIORITISING BRITISH WATERWAYS RESTORATION PROJECTS

1.  INTRODUCTION

  This process is to be introduced so that:

    (i)   Our commitment to expanding the network is better understood.

    (ii)   To provide clarity, consistency, openness and rigor so that we are seen to be effective and efficient.

    (iii)   British Waterways' commitments are clearly understood internally and externally, and they are proportionate to the scope and deliverability of the project.

  1.1 This paper outlines the proposed process.

2.  SCOPE

  This process relates to long term, major canal restoration and new build projects. It is not intended to cover projects such as towpath improvement schemes funded by Local Authorities and Regional Development Agencies.

  It is particularly intended to cover projects where BW could be required to accept new liabilities as it expands the network.

3.  LOCAL SUPPORT

  3.1 General Managers (GMs) may contribute a maximum of £50k (total—not per annum) to support local initiatives to restore the canal network. There will be no separate funding for this and the GM will need to justify this cost against all other demands.

  3.2 Operating Directors may approve a further £50k expenditure at BU level (total £100k per restoration project—not per annum). Again, no separate funding available.

  3.3 All the above is BWs net contribution, to be on a minimum basis of 25% BW, 75% other parties. For avoidance of doubt, if BW contributes £25k, total project expenditure would be £100k or more. These amounts to include staff time as well as cash contribution.

4.  STAGE 1 APPROVAL

  4.1 For expenditure in excess of the above or where BWs proportion is greater than 25%, Stage 1 approval is needed.

  4.2 This approval is from the Chief Executive and Finance Director and one other Director, in accordance with delegated authorities.

  4.3 A detailed proposal will be required setting out the proposal and reasons for BW support, a timetable and budget funding.

  4.4 Maximum authorisation under this procedure is BWs expenditure of £250k in total over 5 years (including funds already authorised under section 1 above).

5.  STAGE 2 APPROVAL

  5.1 If BW is to participate in a restoration programme as partner or contractor, it will need Stage 2 approval before any formal funding applications are made.

  5.2 Stage 2 approval is from the Board. The proposal will require:

    1.   Justification for BW involvement.

    2.   Benefits to BW and network—quantified and quality.

    3.   Wider public benefits.

    4.   Anticipated project cost—construction and work up costs.

    5.   Potential funding and contributions for capital.

    6.   Analysis of potential self sufficiency and alignment with BW ventures and growth.

    7.   Economic appraisal.

    8.   BW contribution in cash and staff time, both capital and future maintenance.

    9.   Project timetable.

    10.   Risk analysis.

    11.   Letters of support in principle from partners and funders.

    12.   Provisional list of conditions BW would set for achieving Stage 3 approval.

  5.3 Stage 2 approval only allows BW expenditure to develop in detail the feasibility of the project both technically and financially. It demonstrates in principle support but no commitment to undertaking the project.

  5.4 BW will set out clearly its requirements for Stage 3 approval.

6.  STAGE 3 APPROVAL

  6.1 When the project team has 95% certainty on the cost of delivery and commitments from all funders, as set out in Stage 2, the project can be submitted for Stage 3 approval.

  6.2 This will be from the Board.

  6.3 Partners and the project team will need to demonstrate that they have met the criteria set out at Stage 2 or give explanation as to why they have not or will not be met.

  6.4 The report will be of similar content to the Stage 2 report, but with committed figures, evidence of funding, etc.

  6.5 Stage 3 approval enables BW to participate in the project to completion.





3   Ev 4. Back


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 1 July 2008