|
| Date | The event and subsequent mobilisation
| Recovery of Mythe WTW and service
restoration
|
|
| 20/7 | STW issues emergency weather warning to works managers, triggering the normal operational response.
| |
| 21/7 | River levels rising. Flood emergency procedures implemented.
| |
| 22/7 | Controlled shutdown commences (0145 hrs).
Mythe WTW flooded.
Site evacuated (0600 hrs).
Tankering operations commence.
Sourcing/deployment of bowsers commences.
| Site flooded.
Preparations for return to site commencecontacting contractors, sourcing of required equipment (pumps, sandbags, spares) etc.
|
| 23/7 | 70,000 properties without water and a further 70,000 under threat.
250 bowsers deployed.
150,000 litres of bottled water being given out.
| Site still flooded (18" of flood water on site).
Preparations for return to site continue.
|
| 24/7 | 140,000 homes properties without water.
400 bowsers deployed.
3 million litres bottled water sourced per day.
| Access to Mythe regained. Visual assessments made, pumping out of floodwater commenced and temporary flood defences erected.
|
| 25/7 | 900 bowsers deployed.
4 million litres bottled water sourced per day.
| Full access to Mythe regained.
Work commences on drying and replacing electrical equipment, replacing and checking control equipment, industrial cleaning and disinfecting all tanks/sumps on site.
|
| 26/7 | "Hub and spoke" approach to refilling bowsers implemented, improving the use of artic tankers and small rigid tankers.
Plan to refill bowsers at least 3 times per day introduced.
1,100 bowsers deployed.
| Key equipment off site for repair.
Industrial cleaning and disinfection of tanks continuing.
Preparations commence to review start up procedure.
|
| 27/7 | 1,200 bowsers deployed, 200 damaged (net 1,000).
5 million litres of bottled water sourced per day (confirmed up to 1 August).
| 10,000 properties brought back into supply using water supplied via Strensham ("do not drink").
Testing of equipment commences.
Key motors returned to site following repair and installed.
Work on semi permanent flood defences commences.
|
| 28/7 | 1,500 bowsers deployed, 300 damaged (net 1,200).
Bowser fill rate of 3 times per day being achieved.
Bottled water stocks maintained to meet demand.
| Plant checks and repairs complete.
Mythe starts pumping operations and commences refilling service reservoirs.
|
| 29/7 | Level of bowsers (net of damaged) maintained at approx 1,200, with a refill rate of 3 times per day being achieved.
| Semi permanent flood defences primarily complete (minor additional bolstering work required).
|
| 30/7 | Level of bowsers (net of damaged bowsers) and refill rate of 3 times per day maintained.
Reconnection of properties resulting in a reduction of use of bowsers25% of bowsers now full when visited.
Bottled water stocks maintained to meet demand.
| Site resilience being builttesting of standby units.
65,000 properties reconnected ("do not drink").
|
| 31/7 | | 70,000 properties reconnected by 0600 hrs ("do not drink").
|
| 1/8 | 67% of bowsers now full when visited.
| 137,000 properties reconnected by 0600 hrs ("do not drink").
|
| 2/8 | | All properties reconnected by 0545 hrs ("do not drink").
|
| 3/8 | | Customers given "boil water" notice.
Ozone and Granular Activated Carbon Unit brought back on line.
|
| 4/8 | Bowser retrieval process commences.
| |
| 5/8 | | |
| 6/8 | | Full automatic control of Mythe regained.
|
| 7/8 | | Customers given "safe to drink" notice.
|
|
Severn Trent Water Limited
August 2007
| | |