Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Examination of Witnesses (Questions 660 - 679)

WEDNESDAY 9 JANUARY 2008

MS PAMELA TAYLOR, MR PHILL MILLS, MR BRUCE HORTON, MR JIM MARSHALL AND MR RICHARD VENTERS

  Q660  Mr Drew: --- Secondly, how you are advising individual water companies and, thirdly, what you need to do in the future to re-evaluate the scale of the events of last year and how individual water companies will be able to respond.

  Ms Taylor: Because of the work that we have been doing at the moment we felt that it was essential that we should get together as a water industry and learn the lessons very quickly and share those lessons, which we are doing and we are continuing to do. We are also updating ministers on that information. However, water and sewerage undertakers have to comply with the Security and Emergency Measures Direction (SEMD) and that is about co-ordinating, planning and so on. It was quite obvious from the events of last year that although the plans exist and although those plans are rehearsed with many different bodies and different organisations that in fact, when it came to an event that people had not foreseen, then although the plans worked element-by-element, when you added it up to the whole they could not cope. As far as we are concerned now, we are looking for these plans to be shared more rigorously, if that does not sound too silly. In other words, that people should not just do desk exercises and computer exercises and so on but should do real old-fashioned exercises, and these should be co-ordinated through local resilience forums. We should also be learning the real lessons from what happened and making sure that we are prepared for the future. Any scenarios that people had in their minds, we have now got to up those, and the research that we referred to earlier is helping us to do that.

  Mr Mills: Companies are already looking at their critical infrastructure, the water treatment works—and a lot of them are near rivers anyway because this is the source of the water—but they are re-evaluating their resilience and looking at flood protection or increased flood protection measures for them or improving the security of supply so that they will be able to get water supplies from alternative sources. Companies are obviously doing that now and they will be putting proposals to the regulator as part of their business plans because we are now getting into the periodic review cycle when Ofwat looks at companies' submissions and looks at what the investment programmes will be and what the price limits will be from 2009 onwards.

  Q661  Mr Drew: Is Ofwat the final gatekeeper when it comes to the individual companies' plans in terms of the resilience of those contingency plans?

  Ms Taylor: The financing of it, yes.

  Q662  Mr Drew: Or is it basically left to the companies themselves to decide this is an area they need to spend much more attention and money on?

  Mr Mills: Companies get guidance from Defra and from the security services and they have to work to that guidance provided, but they will put forward their business plans because they are the ones that understand the assets that they own and operate.

  Q663  Mr Drew: That is Ofwat who will do that?

  Mr Mills: Ofwat will decide whether the public are going to fund that particular improvement or that programme.

  Mr Horton: Ofwat have been quite clear there is no blank cheque for updating infrastructure or assets and any case needs to be made and well-justified on an economic basis by companies and judged against the other investment requirements that companies are expected to make as well.

  Q664  Mr Drew: A final point, if there is unhappiness over a very specific piece of critical infrastructure, is it possible to say to a water company, "You have got to move that? That is just too high a risk. Sorry, it has got to be moved out of the flood plain and we might be able to give you some help to so do"? Is that a possibility or is that one of the things, Pamela, that you would allege actually falls between all these different bits of legislation?

  Ms Taylor: Sadly, I think the answer is both in that when you are analysing risk you cannot just take the water industry on its own. You have to look at the impact on other utilities such as electricity. Power cuts are a worse threat usually than flooding and flooding of course can be linked to power cuts, so we have to look at it across the piece. I think that it is fair to say though that water companies err on the side of asking for what it is they think is right and regulators will err on the side of saying, "Can you justify that financially?" I do not think there is any need for anyone to say to a water operator, "You are not looking at this risk properly; you are not asking for sufficient funding; you are not looking at resilience sufficiently," and so on. If you like, the balance is the other way around, that the water operator would obviously ask, and then it is a question of whether the economic regulator would say that that was right and justified or not.

  Mr Horton: In response to that specific question, it would be one of the options, but moving a water treatment or waste water treatment works a significant distance is going to be extremely expensive, and there are other things that you could do probably that may be cheaper or more cost-effective such as localised flood defences or improving connectivity within the region so that you are not isolated and you are not over-reliant on one works.

  Q665  Chairman: The only thing that bothers me about what you say, Pamela, you say you are going to improve your business resilience, you are going to do all this, as if to say this is a new discovery. I would not imagine that there is one water company that does not have a backed up IT system because it realises in this day and age that if it does not its business processes are totally vulnerable, and yet in the case of this summer it seems to have come as something of a surprise—and we say this with the benefit of hindsight—that certain assets were suddenly found to be vulnerable or eventually overwhelmed.

  Ms Taylor: I think it is fair to say that they were found vulnerable or overwhelmed in ways that nobody, not just the water operators but everyone else who is involved in the planning, had foreseen, so, yes, companies are always looking at resilience. Where the economic regulator has refused the financing for example, going back to the previous point, then companies have used their own money, ie shareholder money, in order to improve the resilience of their infrastructure. The need is there, the need is recognised and the need had been being met, but last year was different of course.

  Q666  Chairman: I want to move on to talk about the design of sewers, but obviously sewer capacity is pretty expensive stuff. If you decide that sewers are not able to cope, then ripping up streets and building new sewers is seriously expensive stuff. Just before I get into the design issue do you believe that the current model of determining the payment structure for water is a correct model and a correct basis to take into account the implications of more extreme weather? I ask this question against the background that when bathing water standards for example were to be improved, particularly in the South West, individual users' bills went up very steeply because there was a big bill and not many people to pay it. It has occurred to me as to whether in fact the current user-pays-all-expenses model is correct when there are extreme weather conditions of an unpredictable nature, not the fault of the water company but they are now becoming a consequence of climate change. We deal with that on a national, European and international basis, so I come back to my central question: in responding to some of the pressures which may be associated with climate change, is the current water pricing investment and payment model the right way to deal with it?

  Ms Taylor: The answer is that we are asking the same question and we do not yet know the answer. It is certainly something that we are aware of and our regulators are aware of as well, so it is something that certainly more people now are beginning to ask, and there is a bigger debate about that. One of the things about the five-yearly cycle—and as you know, our prices are set for us by the economic regulator every five years—and what we are discussing with Defra at the moment (and we are very pleased that the current ministers are responding very well to this and, to be fair, the last minister too) is to look at the strategic direction of the water sector, to say long term what are the things that we have to take into account in terms of planning, and then to say, well, long term how do we need to make sure that we are fit for the future and therefore can we make sure that price reviews are not just a five-yearly battle where the environment wins one time or customers the other, prices go down or prices go up, or whatever else it may be, but making sure that those five-yearly price reviews are actually a stepping stone on the way to where it is we think long term we need to be. Part of that debate now is whether regulation as we currently have it is fit for the future, and if it is not what are things that are blocking it that we need to consider.

  Mr Horton: Just two points I wanted to make in relation to climate change. The first is we need to understand the impacts of climate change on the water industry. There is an awful lot of work going on to do that. Phill mentioned earlier some of the UKWIR work that is going on. We have been doing research on climate change for ten to 15 years already and our understanding is improving, although it is still not perfect, so we still need to do more work to understand the impact. Water companies and the regulator do not want customers to be paying for investment unnecessarily. The second point is that adaptations to climate change are not necessarily always going to cost a lot of money. In some circumstances they will but we should be looking for the most cost-effective and in the long term most sustainable solutions. Phill mentioned earlier things like SUDS, permeable surfaces, restoring natural flood plains and so on, and with things like the Water Framework Directive we are increasingly being given the tools to move towards those more low-tech, sustainable solutions which may be less costly.

  Q667  Chairman: Let us talk about sewer design because as I understand it, you are supposed to have your sewers designed to deal with a one in 30 year event. Who set that standard?

  Ms Taylor: All sewers since 1980 have met the standard of one in 30. That was actually something that the water industry itself pushed for as a standard.

  Q668  Chairman: Who decided that a one in 30 year event was the right number?

  Ms Taylor: Based on information that we had at the time in terms of the modelling available to us, information on climate change, demographics, the ways in which people are using water and so on, it was right and it looked as if it was right at the time, and it probably was right at the time.

  Q669  Chairman: So all sewers that we have got now ---?

  Ms Taylor: Only those built since 1980 were designed to meet the standard of one in 30.

  Q670  Chairman: Let us go back because an awful lot were built before then

  Ms Taylor: An awful lot, yes, but it is quite likely that many of those built before 1980 meet that standard too thanks to the Victorians, but it is also quite likely that a whole load of them do not meet the one in 30.

  Q671  Chairman: You said that the standard was set in 1980, so this is 27 years ago and the scenario of what you have to cope with because of development, and now climate change, has changed, but are you saying that the industry does not have knowledge of the status of the sewers that were built before 1980, because your response to my probing on that was of a general nature alluding to the fact that you hoped that much of the other infrastructure was up to the one in 30 year but you could not be certain?

  Ms Taylor: That is because we do not control all of the sewer network that we have to take responsibility for. We do not control the water that comes into it. We do not control the connections that people have and the automatic right to connect to it. We do not control the water run-off from highways and so on. As usual, there are too many things that we do not control in order for us to be able to—

  Q672  Chairman: You might not control it but coming back to this question of what we need to do, were it necessary to have a sewer system that can cope, there is lots you cannot control in terms of the liquid input, but you have already identified a large number of sources of water.

  Ms Taylor: Yes.

  Q673  Chairman: So I am just a little concerned that nobody has gone out and done some modelling.

  Ms Taylor: We have.

  Q674  Chairman: Right. Let me come to the simple layman's question: you might not be able to tell me exactly if all of the sewerage system is at one in 30 years, but let me turn it on its head, how much of it does not cope with what we have already got in terms of all this water coming into it, because otherwise, if it all coped we would not have any flooding?

  Mr Mills: You are correct, companies have done modelling since they took over the sewerage system in 1989 and they have been required to map sewers as well. They have not mapped all the sewers yet but they have done it on a risk assessment/risk management approach. They have looked at areas and sewers where they have problems and they have established what are their critical sewers, so they have looked at putting investment in those critical sewers, which could be because of the flow capacity or could be because of the impact if there was a collapse of a particular sewer, and the modelling has been geared towards that. They have also done lots of CCTV surveys to check the condition of sewers, so they have a good feel since 1990 of the condition of those sewers. The sewers are classified into Ofwat's five conditions from good, meeting all the standards, to those that are perhaps in imminent danger of collapse and need remedial measures.

  Mr Horton: It is important to remember also that the one in 30 is a standard and it is a theoretical standard largely. There are many, many rainfall events and floods that occur that are greater than one in 30 and do not cause any property damage or flooding. It also only reflects probabilities; it does not reflect consequences, so companies, I think rightly, take a risk-based approach.

  Q675  Chairman: The ABI use one in 75 years as their event number as a condition for providing insurance. In other words, if you are in an area where the flood risk is greater than one in 75 you are in trouble in getting cover. The insurers have one in 75; you are working to a standard of one in 30.

  Mr Mills: Is that not for different flooding?

  Chairman: It might be. I am just exploring with the benefit of your guidance and knowledge why there is a difference between the two.

  Mr Horton: Obviously it is possible to increase the size of sewers to achieve a higher standard. You could have a one in 100 standard for all sewers if you wanted to. It would cost an awful lot of money though, and we would argue that there are cheaper solutions to address those higher standards. The framework that we have got at the moment where we have a minimum of one in 30 for sewers has evolved over time, and that has been seen to work. On the whole, it has worked extremely well and extremely effectively.

  Q676  Chairman: I do not want to prolong discussion on this area but I think what I am getting at is that Pamela said that we have got all this water coming in, a lot of it we cannot control and she said in an earlier answer what we have also got to do is slow it down. If you are dealing with capacity, you may have got enough capacity if you can slow down the entry of the water into your system. I find it all quite difficult to imagine the dynamic of what is happening in the real world with the rain coming down, all this water hurtling in and me asking a question whether it is adequate. In the real world, when we had our friends from the GLA in and we were thinking back to the summer and some of those films of bits of London under railway bridges submerged, there are people under those circumstances who are going to say the drains are not big enough, they were not properly maintained, et cetera, et cetera, and you come to the real question we do not want this to happen again; we know there is a problem; how do we deal with the problem there when that kind of real world event occurs? I am getting the impression that there are so many variables that you have put before us that it is quite difficult to make any kind of prediction as to where you ought to invest to avoid the problem. The only way you can identify it is when the problem occurs and you do something about it retrospectively. Is that right?

  Ms Taylor: Nearly in that, yes, it is very, very difficult and, yes, there are many, many variables, but it is a menu of things that you need in order to try to deal with it, first of all, to try to prevent it happening and then, secondly, going back to the discussion we had right at the beginning, in terms of responsibilities and so on when it does happen. If you think about the classic picture in whatever city it may be of the railway bridge and flooding underneath it on the road and so on, it is quite likely if you looked back to when the homes around were first built they would have all had front gardens, they would not have been paved over, they would not have had cars parked on the front gardens, and you would not have roads that are really rivers now because they are acting almost as urban drains taking the water away. Of course, no drain is designed for that and no sewerage system is designed for that. We have to ask do we want to spend customers' money on expanding the size of the sewers or do we want to look at a menu of options here? One would be more permeable covering and so on for people's driveways, et cetera. Another would be slowing the water down in other ways, SUDS and so on. We think that it is a mixture of things, it is a menu of things that we need.

  Chairman: Paddy, do you want to come in on that?

  Q677  Paddy Tipping: I think that is right. You do things on the uplands and flood plains, SUDS and the kinds of things you have been talking about, but ultimately we are asking a very straightforward question. I think you told us that the standard was set at one in 30 in 1980. Is it going to increase? As a result of the problems this year are you going to increase the standards? Should they be increased?

  Mr Mills: The current Defra advice is for an uplift of 20% on that to 2050. It is a complicated issue to grasp but the one in 30 is obviously based on probability. However, as you move forward, the intensity of a one in 30 year return storm is going to increase anyway, so the design standard or the flow that you would expect to design for is going to increase anyway and there will be that increase in the standards. There is research going on at the moment into 21st century sewer design and what those future standards should be. I cannot emphasise enough that in future we are going to look at a twin-track approach, if that is the right word, and try and keep surface water out of sewer systems through sustainable urban drainage and getting water to percolate back into the ground rather than into pipe systems.

  Q678  Paddy Tipping: So you are saying to me that at some point in the future, and perhaps you would just clarify when that might be, with big new developments the sewerage infrastructure is going to be of a higher quality design and higher volume design?

  Mr Mills: Big new developments going forward ideally would have SUDS installations and retention basins so that that water would not go into the existing sewerage system because then it will overload it somewhere downstream.

  Mr Horton: Ideally in the future we would like new developments to be drainage neutral as well as carbon neutral and anything else neutral you want to make them.

  Ms Taylor: Exactly.

  Q679  Paddy Tipping: Just explain for us beginners what drainage neutral actually means.

  Mr Mills: No additional contribution to the drainage network.

  Ms Taylor: No additional burden on the drainage network.

  Mr Mills: So it would be offset by SUDS or green roofs or permeable surfaces or localised storage. Mr Horton: Just one very quick point on the one in 30 standard. Although we are looking at that and there is a project now, as Phill says, to look at the design standards of sewers in the future, the first thing we need to do is to make sure that the climate change scenarios of the future are built in. The one in 30 may still be a one in 30 standard but at least it has got the more intense rainfall events built in there.


 