Supplementary memorandum submitted by
the Environment Agency
Question 22 (Mr Edward Leigh): Are you prepared
to give a list of the systems in the northern area and Lincolnshire
and Cambridgeshire which are not in an adequate condition.
We are currently reviewing what our `fit for
purpose' standards ought to be. The fact that an asset is not
at our `preferred' condition does not mean that it is inadequateless
than 1% of floods result from asset failure, a fact borne out
in the recent floods.
We have produced a Report from our asset register,
the National Flood Coastal Defence Database (NFCDD) of all asset
systems in Northern Area Anglian Region. This comprises the county
of Lincolnshire, parts of Northamptonshire and Northern Cambridgeshire.
We record below the headline details of systems that pass our
preferred target condition. In addition we provide a complete
schedule of each system that does not achieve our target.
Anglian Region Northern Area
System Details (as at 31/03/2007)
1. Summary
high risk systems total 101
passed 49
did not pass 52
medium risk systems total 44
passed 35
did not pass 9
low risk systems total 50
passed 30
did not pass 20
2. Schedules of Systems that do not meet
our preferred condition target.
We provide below a complete list of all systems
in Northern Area Anglian region that are not at our preferred
condition. The lists are separated into High, Medium and Low risk.
Notes:
The following information is provided
(a) The unique system reference. This is
provided under the heading "FRM system"
(b) A brief description of the location and
extent of the system, headed `Group Description'.
(c) Confirmation of the `Catchment' in which
the system sits headed `Catchment'.
(d) Confirmation of the consequence of failure
of the system, Headed `consequence rating'. The measurement of
risk takes into accountthe likelihood of a flood occurring combined
with its possible consequences.
HIGH RISK SYSTEMS
| | | |
| FRM System | Group Description
| Catchment | Consequence Rating
|
| FR/01/S003 | EAST DRAIN, Humber to top end of wrawby catchwater and Little carr drain, also including bonby, worlaby catchwaters and land drain
| Lincolnshire | HIGH |
| FR/01/S004 | L ANCHOLME, Harlem hill lock to bishopbridge, including Kingerby beck, east drain upper and east drain trib
| Lincolnshire | HIGH |
| FR/01/S005 | M ANCHOLME, bridge st, brigg to Harlem hill lock, including all the major tributaries along this length
| Lincolnshire | HIGH |
| FR/01/S022 | STALLINGBOROUGH, stallingborough north beck,Humber to stallingborough road and Oldfleet drain, humber to healing road
| Lincolnshire | HIGH |
| FR/01/S023 | R FRESHNEY, Alexandra road bridge to Laceby bypass bridge including full length of new cut drain
| Lincolnshire | HIGH |
| FR/01/S026 | BUCK BECK, Humber to toll bar road bridge
| Lincolnshire | HIGH |
| FR/01/S028 | LOUTH CANAL, tetney lock to riverhead road, including mother drain, poulton drain, black dike and parts of mother drain, new dike and oldfleet diversion
| Lincolnshire | HIGH |
| FR/01/S032 | GREAT EAU, great eau, tidal outfall to belleau bridge and long eau, great eau to A157 and muckton beck
| Lincolnshire | HIGH |
| FR/01/S034 | WOLDGRIFT DRAIN, Tidal outfall to upstream limit at saleby
| Lincolnshire | HIGH |
| FR/01/S036 | R STEEPING, wainfleet clough to Mill bridge including wainfleet relief channel and burgh relief channel
| Lincolnshire | HIGH |
| FR/01/S042 | Maud Foster Drain carries higland water past Stickney & Sibsey before passing through Boston and discharging into the Witham Haven
| Lincolnshire | HIGH |
| FR/01/S043 | RIVER BAIN carries water past the villages of Kirkby-on-Bain, Tattershall and Coningsby
| Lincolnshire | HIGH |
| FR/01/S045 | HORNCASTLE is a market town through which the Rivers Bain and Waring pass.
| Lincolnshire | HIGH |
| FR/01/S055 | South Forty Foot Drain is a large rural catchment draining over 30 IDB pumped catchmnets and upand villages such as Helpringham, Swaton Pointon and Billingborough.
| Lincolnshire | HIGH |
| FR/01/S062 | SLEA drains Sleaford, Ruskington and Leasingham
| Lincolnshire | HIGH |
| FR/01/S067 | Lincoln City system protects the city and numerous elements of major infrastructure
| Lincolnshire | HIGH |
| FR/01/S075 | GRANTHAM large market town protected by raised defences private structures
| Lincolnshire | HIGH |
| FR/01/S078 | Witham Haven tidal channel draining large market town of Boston and extensive fen floodplain
| Lincolnshire | HIGH |
| FR/01/S079 | Winteringham to Ferriby Cliff, entire length protects winteringham and arable land
| Lincolnshire | HIGH |
| FR/01/S080 | Ferriby Cliff to EH Skitter, entire length entire length protects numerous small towns Barton-on-Humber, Barrow-on-Humber internationally designated sites and nationally important industrial areas
| Lincolnshire | HIGH |
| FR/01/S081 | EH Skitter to Pyewipe, entire length protects numerous small towns Barton-on-Humber, Barrow-on-Humber internationally designated sites and nationally important industrial areas
| Lincolnshire | HIGH |
| FR/01/S085 | Mablethorpe NE to Sandilands,entire length protects Mablethorpe, Trusthorpe and major tourist industry
| Lincolnshire | HIGH |
| FR/01/S087 | Chapel Point to Lagoon Walk, entire length protects Ingoldmells and major tourist industry inc Butlins Holiday camp and several thousand caravans
| Lincolnshire | HIGH |
| FR/01/S089 | Gib Point to Horseshoe Tidal defences protecting large areas of high grade arable and villages including Friskney, Wainfleet St Mary
| Lincolnshire | HIGH |
| FR/01/S090 | Horseshoe to Hobhole Tidal defences protecting large areas of high grade arable and viallages of Wrangle, butterwick and Freiston Shore and HMIP North Sea Camp
| Lincolnshire | HIGH |
| FR/01/S091 | Frampton Tidal defences protecting large areas of high grade arable and RSPB reserve. Would flood land fill tip and industrial area of Boston
| Lincolnshire | HIGH |
| FR/01/S099 | River Welland from the A427 to the disused rail bridge in Market Harborough, and the entire lengths of the River Jordan, Dingley Dyke, West Brook and Brookfield Drain.
| Welland and Nene | HIGH |
| FR/01/S104 | North Brook from Greetham Pumping Station to the Main River Limit.
| Welland and Nene | HIGH |
| FR/01/S119 | Fluvial Welland, from its outfall into the Tidal Welland to the A15 road bridge upstream of Market Deeping.
| Welland and Nene | HIGH |
| FR/01/S122 | Includes Car Dyke Eye, Folley River, Brook Drian (excluding the Woodcroft Arm), Werrington Brook, Paston Brook, and Marholme Brook and also includes the Paston and Marholme COW's, in Peterborough.
| Welland and Nene | HIGH |
| FR/01/S124 | Maxey Cut, entire length.
| Welland and Nene | HIGH |
| FR/01/S126 | Tidal Welland, entire length
| Welland and Nene | HIGH |
| FR/01/S127 | Tidal Nene, entire length and Main River section of the North Level Main Drain.
| Welland and Nene | HIGH |
| FR/01/S134 | River Nene, Dog in a Doublet to Orton Dyke Outfall, and the entire lengths of Fletton Springs, Stanground Lode, Orton Dyke, Thorpe Meadows and Thorpe Drain, in Peterborough.
| Welland and Nene | HIGH |
| FR/01/S136 | River Nene, Wansford to Warmington including Yarwell Mill Tail, Elton Mill channel and Broadreach Back channel.
| Welland and Nene | HIGH |
| FR/01/S143 | River Nene, Upper Wellingborough Lock to Lower Wellingborough Lock, and Dennington Brook, Wellingborough.
| Welland and Nene | HIGH |
| FR/01/S150 | River Nene, Billing Bridge to South Bridge, including Bypass and Mill Channels, Northampton.
| Welland and Nene | HIGH |
| FR/01/S160 | Gretton Brook, Gretton Rd Bridge to Separation Chamber
| Welland and Nene | HIGH |
| FR/01/S172 | Harpers Brook, Sudborough Rd Bridge to Main River Limit
| Welland and Nene | HIGH |
| FR/01/S180 | Skew Bridge Dyke, entire length, Rushden
| Welland and Nene | HIGH |
| FR/01/S184 | River Ise, Warkton Rd Bridge to A43
| Welland and Nene | HIGH |
| FR/01/S187 | Swanspool Brook, entire length, Wellingborough.
| Welland and Nene | HIGH |
| FR/01/S188 | Harrowden Brook, entire length, Wellingborough.
| Welland and Nene | HIGH |
| FR/01/S189 | Slade Brook, Outfall to Glendon Rail Culvert, and the entire length of the East Brook.
| Welland and Nene | HIGH |
| FR/01/S195 | Ecton Brook, entire length, Northampton.
| Welland and Nene | HIGH |
| FR/01/S202 | River Nene, Kislingbury Branch, including Weedon Branch, Heyford Brook and Bugbrooke Brook downstream of the Canal, Camp Lane Dyke, Harpole Mill Bypass, Red Lion Dyke, A45 Tributary, Stowe Brook and the Wooton Brook and tributaries downstream of Quinton Rd Bridge, East of Northampton.
| Welland and Nene | HIGH |
| FR/01/S214 | River Glen, Surfleet Sluice to Kates Bridge.
| Welland and Nene | HIGH |
| FR/01/S217 | Bourne Eau, entire length including COW, Car Dyke North entire length, and the Car Dyke South downstream of Fen Rd Bridge, Bourne, Lincolnshire.
| Welland and Nene | HIGH |
| FR/01/S224 | Latimer Brook, entire length, Burton Latimer.
| Welland and Nene | HIGH |
| FR/01/S227 | Witham Top Pond
| Lincolnshire | HIGH |
| FR/01/S997 | Kibworth Brook and Meadow Brook, entire lengths, Market Harborough.
| Welland and Nene | HIGH |
| FR/01/S998 | Raunds Hog Dyke and Parallel Channel, entire length including COW
| Welland and Nene | HIGH |
| | |
|
MEDIUM RISK SYSTEMS
|
| | |
| FRM System | Group Name |
Catchment | Consequence Rating |
| FR/01/S037 | COW CR DRAIN, Croft pump station to Bratoft road, entire length
| Lincolnshire | MED |
| FR/01/S044 | HORNCASTLE CANAL protects villages of Haltham and Dalderby and contrbutes to protection of Horncastle
| Lincolnshire | MED |
| FR/01/S048 | DUCKPOOL C 3m raised earth defences protecting high grade arable and isolated residential properties
| Lincolnshire | MED |
| FR/01/S060 | KYME EAU 3m raised earth defences protecting high grade arable and isolated village Chapel Hill
| Lincolnshire | MED |
| FR/01/S064 | BILLINGHAY N CUT 2m raised earth defences protecting high grade arable and numerous villages Billinghay, Digby
| Lincolnshire | MED |
| FR/01/S065 | CARR DYKE & DELPHS 2m raised earth defences protecting high grade arable and numerous villagesPotterhanworth, Branston Timberland and Walcott
| Lincolnshire | MED |
| FR/01/S072 | CLAYPOLE defended rural channel protecting Claypole, foston and Westborough
| Lincolnshire | MED |
| FR/01/S116 | Foxton Brook, entire length.
| Welland and Nene | MED |
| FR/01/S183 | River Ise, Outfall to Warkton Rd Bridge
| Welland and Nene | MED |
| | |
|
LOW RISK SYSTEMS
|
| | |
| FRM System | Group Name
| Catchment | Consequence Rating
|
| FR/01/S008 | Grasby Beck, Howsham Road bridge to Hill Farm, entire length
| Lincolnshire | LOW |
FR/01/S009 | CREEK DRAIN, Caistor Canal to Upstream limit, entire length
| Lincolnshire | LOW |
FR/01/S010 | South Kelsey Catchwater, Caistor canal to Kelsey road, entire length
| Lincolnshire | LOW |
FR/01/S011 | THORNTON catchwater drain, entire length
| Lincolnshire | LOW |
FR/01/S051 | STAINFIELD BECK drains arable land isolated prperties
| Lincolnshire | LOW |
FR/01/S057 | CLIFF BECK drains arable land
| Lincolnshire | LOW |
| FR/01/S096 | River Welland from Rockingham Bridge to the A427 including the Great Bowden Flood Relief Channel, and the entire lengths of Ashley Dyke, Slawston Brook, Langton Brook and Stonton Brook are also included.
| Welland and Nene | LOW |
| FR/01/S115 | Medbourne Brook, upstream of FSR embankment, east and west arms.
| Welland and Nene | LOW |
| FR/01/S120 | River Welland Millstreams and the River Welland from Tallington to Uffington Rd Bridge.
| Welland and Nene | LOW |
| FR/01/S123 | Brook Drain Woodcroft Arm
| Welland and Nene | LOW |
| FR/01/S158 | Willow Brook, Bulwick Rd Bridge to Weldon Central Stream confluence, and Gretton Brook from its outfall to Gretton Rd Bridge.
| Welland and Nene | LOW |
| FR/01/S164 | Perio Herne, entire length
| Welland and Nene | LOW |
| FR/01/S170 | Harpers Brook, Brancey Brook to Sudborough Rd Bridge.
| Welland and Nene | LOW |
| FR/01/S179 | Chelveston Brook, entire length
| Welland and Nene | LOW |
| FR/01/S182 | Knuston Brook, entire length
| Welland and Nene | LOW |
| FR/01/S194 | Barton Brook, entire length
| Welland and Nene | LOW |
| FR/01/S211 | Heyford Brook, Canal to Main River Limit
| Welland and Nene | LOW |
| FR/01/S213 | River Nene, Everdon and Newnham arms
| Welland and Nene | LOW |
| FR/01/S218 | Car Dyke South, Fen Rd Bridge to Main River Limit.
| Welland and Nene | LOW |
| FR/01/S996 | River Nene, Church Brampton Branch, entire length
| Welland and Nene | LOW |
| |
| |
Question 33 (Mr David Curry): We had a Planning White Paper
recently and we will have planning legislation presumably quite
soon. Are there things which ought to be in that planning document
which would address this issue.
The Planning White Paper was published in May 2007. It follows
the previous planning reforms in the Planning and Compulsory Purchase
Act 2004. It is effectively in two parts, with a number of minor
reforms to the town and country planning system and a new system
for dealing with major infrastructure projects. The latter could
result in a Planning Reform Bill in the Autumn, subject to Parliamentary
time being available.
None of the town and country reforms in the White Paper specifically
cover either the issue of flood risk or sustainable drainage systems.
However, one of the proposals in the White Paper is that Communities
and Local Government: "produce a more strategic, clearer
and more focused national policy framework with (Planning Policy
Statement) PPS1Delivering Sustainable Development at its
heart"".
PPS1 provides policy support for sustainable drainage systems,
along with PPS25 Development and Flood Risk which includes a key
planning objective to: "reduce flood risk to and from new
developments through location, layout and design, incorporating
sustainable drainage systems (SUDS)"". Both PPSs provide
strong policy support for the use of SUDS so it is important that
in producing its `more strategic, clearer and more focused national
policy framework' the government does not lose this important
policy advice. Equally PPS25 provides increasingly strong policy
on development and flood risk and this must also be protected
in any policy reforms.
With strong policy promotion of SUDS in planning and plenty
of technical guidance on how to do SUDS the issue preventing the
widespread use of SUDS appears to be that of adoption. There are
growing signs that water companies are willing to take on the
adoption of SUDS but funding their long term maintenance is a
key problem. A funding solution needs to be found quickly to enable
these proven systems to be used. Renewed effort is required to
resolve this issue, including involvement of key stakeholders
such as Ofwat, water companies and the major housebuilders.
We are building substantial numbers of new homes that will
still be around in 50100 years. The decisions we make now
about their design and layout will have an impact on flooding
into the future. It is important that they are designed in a way
that minimises the chances of major urban flooding in the future.
Urban flooding will only be effectively tackled by key stakeholders
working together to common standards. Longer term (25 year) strategic
planning of drainage infrastructure that takes account of climate
change and sets out responses of different organisations involved
will be a key mechanism. In January this year, Defra launched
a £1.7million programme to pilot this approach in 15 areas
of the country. The Environment Agency is involved in all of the
pilots, and is the lead organisation in Surrey, Newcastle, Lincoln
and Torbay.
But we believe that Local Authorities are best placed to
co-ordinate production of these plans, whereas the Environment
Agency is best placed to contribute to their production, and ensure
they are fit for purpose for the long term.
In terms of the major infrastructure proposals in the Planning
White Paper, we need to ensure that major developments do not
give rise to flood risk elsewhere and that they avoid high flood
risk locations wherever possible. It is proposed that planning
consultees, such as the Environment Agency, have a key role to
play in the developments of major infrastructure proposals, and
we expect developers to pay particular attention to our advice
on flood risk. The Planning White Paper proposes `streamlining'
the planning process. Whilst we accept this is needed, we would
want to avoid a watering down of the commitments secured in the
Planning Policy Statement 25 and ensure that EA views are taken
into account in decisions on infrastructure proposals and that
the option for call in is retained where EA sustains an objection.
New National Policy Statements will be created to guide major
infrastructure proposal decisionswe believe these should
be subject to Strategic Environmental Assessment to help ensure
these objectives are achieved. The overall purpose of the new
major infrastructure process should be the achievement of sustainable
development, which mirrors the purpose given to the Town and Country
Planning system in the 2004 Act.
Question 86 (Mr Richard Bacon): If there are various sources
of funding, a clear note that sets out in a chart where they all
come from and what they all add up to so we know what we are talking
about. Could you also, within that, specify capital expenditure,
maintenance expenditure and new expenditure and do it for each
of the last five years and what your planning assumptions are
going forward.
Our income comes from Flood Defence Grant in Aid (Defra),
Local Authority Levies, Private Contributions, Charges and Precepts
(such as drainage charges to Internal Drainage Boards), and other
income (from sale of assets & rental charges).
(a) Breakdown of funding sources by type:
2006/07

|
| Source | £m
| % |
|
| FDGiA | 419.2 | 93.9
|
| Contrib | 0.4 | 0.1
|
| Charges | 10.9 | 2.4
|
| Other cap | 8.6 | 1.9
|
| Other rev | 15.9 | 3.6
|
| Total | 454.6 | 100
|
|
| | |
(b) Table of expenditure 2002-03 to 2006-07 (all
figures £m)
| Year | 2002-03 |
2003-04 | 2004-05 |
2005-06 | 2006-07 |
| Capital | 170.1 | 172.4
| 176 | 255.3 | 195
|
| Revenue (includes Maintenance) | 183.1
| 183.3 | 220.6 | 291.2
| 259.6 |
Total | 353.2 |
355.7 | 396.6 | 546.5
| 454.6 |
Note: In order to enable a comparison with earlier years and alignment with the future years' Government funding figures the above table does not include Local Levy funded expenditure (Table 6 in the NAO Report is total expenditure including Local Levy)
| | | |
| |
Our planning assumption has been modest growth for capital
and reduction in revenue, however recent announcements on funding
have changed the degree to which capital expenditure is likely
to grow and we are presently making adjustments to our forward
plans. It is not yet clear how much of the new funding will come
to Environment Agency and when.
Question 86 (Mr Richard Bacon): Administrative costs
Administrative costs in 2006-07
| National Costs | £k
| Narrative | |
| National Centres and Services | 6,197
| Services, including internal audit, National Environment Assessment Services, science and fleet operations,provided for frontline staff centrally
| |
| Policy Units & Business Process Units |
7,237 | Develop and implement national polices, design and monitor consistent processes
| |
| Corporate Information Services | 7,694
| Information technology development and support for all FRM staff
| |
| National Corporate Directorate costs | 7,637
| Cost of the National Directorates including the cost of the Executive and Board
| |
| Accommodation and Depots (National) | 10,736
| All accommodation rent/rates including the costs of depots for the workforce
| |
Regional Support Service Costs
| 14,813 | Delivery management teams and their local support, including Regional Management Teams, finance, HR and facilities management
| |
| Regional Strategy Teams inc Corporate Affairs etc
| 6,037 | Local customer and stakeholder engagementstrategic environmental and FRM planning
| |
| Area Support Services |
| | |
| Area Customer Services | 3,498
| Provide a customer focus for planning and general liaison with the public and stakeholders
| |
| Total | 63,849 |
| |
| | |
|
Question 139 (Mr Edward Leigh): I want to know, reference paragraph
3.8 on page 24, why you spent so much developing plans for new
flood defences rather than actually building them.
Activities classified as Development.
Development costs cover all the study work, investigations
and design activity that may lead to construction work. The portfolio
of study work involved also contributes to actions not involving
the Environment Agency in construction activity. These include:-
Future approaches to development control
Action by other operators (such as improved surface
drainage)
Changes to maintenance regimes
Catchment Flood Management Plans & Shoreline
Management Plans
Detailed feasibility of `short listed' priority
schemes
Planning approvals, including enquiries
Detailed design of schemes.
Scheme drawings and contract documents
In 2005-06 we spent £64.5m on "development costs""
and £161m on construction work.
Our investment in these studies yields benefit for the public
purse through :-
Non construction activities
Selection of the preferred scheme option (eg water
storage area or higher defences)
Identification of highest priority works
Actions to enhance efficiency
To pursue future improvements we have:
Focussed on improved construction delivery giving
greater confidence to delivery of programme and reducing the degree
of contingency schemes required as programme `float'. External
benchmarks show that our performance on budget management places
us in the top 10% of construction clients in the UK This has progressively
improved and now allows us to reduce the proportion of schemes
in development at any one time.
Developed new tools to map and quantify costs,
damages and risks. These enable more effective and efficient early
calculation of the costs and benefits of a flood risk area, allowing
early curtailment of work on low priority locations.
In combination these improvements will allow us to reduce
total expenditure on study work and other development costs by
3% a year for the next 2 years. In addition we are currently developing
further supporting tools on risk mapping, and longer term investment
plans that will enable further efficiency savings.
Question 139 (Mr Edward Leigh): I want to know why such a small
proportion of your construction budget is available for new projects,
with reference to figure 15 on page 23.
The proportion of committed work varies from year to year
depending upon the portfolio of projects that makes up the programme.
Currently we have a number of multi year schemes including for
example works at Nottingham (£46m over 5 years), works on
the coast at Dymchurch (£54m over 10 years) and Broadland
PFI (£130m over 20 years).
This year we have £104.7m committed on 163 projects,
so only £20.2m is available to start 33 projects. This will
change from year to year as projects end, and new, long term projects
begin.
Typical Project Timeframes
In order to ensure efficient construction we are often constrained
to delivering works in only part of the year (normally summer
months) thus our larger projects often take a number of years
to complete. Our commitment to such projects means that only limited
funds are available each year to start new projects. In practice
we ensure that contractual provisions exist for us to efficiently
delay or curtail work and provide greater opportunity to introduce
new work, however this is often undesirable and rarely offers
better value for money.
Question 139 (Mr Edward Leigh): I want to know why it is that
six years after the last NAO Report, your data systems are still
of such poor quality, with reference to summary paragraph 5, final
bullet on page 7.
Asset data and the National Flood and Coastal Defence Database
(NFCDD)
We have worked hard to tackle the weaknesses identified in
the previous NAO Report. In particular, we have
Improved greatly the quality and completeness
of the data
Developed a standard set of Reports available
nationally and regionally, including those on asset condition,
asset maintenance, work planning and programming priorities, system
condition target Reports and inspections due, programmed and carried
out.
NFCDD is not designed as a data management system but as
secure data storage. This can slightly increase the complexity
of its use, but has other benefits in terms of data security.
Since completing the improvements we made in 2006, we commissioned
a further review of NFCDD to tackle the issues identified in the
current NAO Report, and have begun to implement many of its recommendations.
For example we have improving the capacity to download data and
provide nationally consistent Reports, and identified the work
required to move to a full asset management system.
As we expand our business, learn from experience and evolve
new techniques and approaches, so our data needs change. We are
constantly working to ensure our data and systems are fit for
purpose.
Additional briefingCatchment Flood Management Plans (CFMP)
The EA is in the process of developing 68 CFMPs in England
(to be completed by end December 2008) and for nine in Wales (to
be completed by end March 2009). Whilst these plans are essential
for long term planning of flood risk management the absence of
a plan does not mean that no action is planned to be taken to
reduce risk. The EA mapping systems and our National Flood Risk
Analysis already drive much of our investment and are used extensively
to manage our capital and maintenance programmes targeting investment
where risks are highest.
The absence of a completed plan for Sheffield, Hull, Leeds
or Doncaster does not mean that no solutions to flooding problems
have been contemplated or acted upon. Proposals for Leeds are
well advanced and much work has previously taken place around
Hull. However, it has to be recognised that even with defences,
much of the recent flooding would not have been avoided since
it effectively resulted either from drainage systems being overwhelmed
or from overtopping of flood assets due to extreme rainfall levels.
Catchment Flood Management Plans take a strategic long-term
look at flood risk in a river catchment. Each plan considers the
main physical processes and factors that generate flooding and
evaluates flood risks. This process covers from the moment rainwater
falls onto the land, via the passage of floodwater through river
valleys and how it affects floodplain settlements, to the sea.
The plans set out how flood risk is likely to change over
the next 50-100 years when considering the impact of climate change
and how land is used and managed.
CFMPs will shape the future of flood risk management in England
and Wales. They will set out objectives for the catchment and
develop local flood risk management solutions. The plans develop
an action plan that sets out how risk can be managed in that catchment
in a sustainable way using a broad portfolio of flood risk management
tools. The action plan will drive what we and others can do to
reduce flood risks to people and the natural and built environments.
Why do we need CFMPs?
Catchment Flood Management Plans will support the development
of better, sustainable and safe communities and we hope they will
encourage people and organisations to work together to avoid,
manage or live with flood risk. We know we can only produce effective
Catchment Flood Management Plans with help from other organisations,
such as planning authorities and other flood operating authorities.
Agreeing policies to manage flood risk in a given catchment and
making those policies work, requires co-ordinated action by these
local organisations and groups, and we hope that they will use
CFMPs to inform their own plans and activities.
What do CFMPs look at?
Catchment Flood Management Plans take a strategic approach
to flood risk management by assessing the risks across the whole
catchment. As part of this approach, they will focus on:
Flood risk management planning
CFMPs will set out our objectives for the catchment, what
policies will be adopted to enable us to best deliver those objectives,
and outline the range of flood risk management responses that
will work for that catchment. They will enable the prioritisation
of actions based on risk, so we can target our investment in the
highest risk locations first.
Climate change
CFMPs include an assessment of what flood risk could look
like in 50-100 years time in the catchment. By considering the
long-term we can start to plan for future climates and make decisions
whether they way we are managing risk now will still work in the
future.
Spatial planning
Spatial planning has a very important role to avoid new flood
risks being created through inappropriate development. Flood plains
are essential for rivers to live and breathemaking space
for floodwaters in rural areas and through towns is essential
to reduce flood risk and benefit wildlife.
Catchment Flood Management Plans will help spatial planners
undertake their Strategic and Local Flood Risk Assessments and
assess how safe and sustainable their development proposals are.
In England, we want Catchment Flood Management Plans to support
Spatial Strategies, Local Development Frameworks and associated
Flood Risk Assessments; in Wales, we want them to support the
Wales Spatial Plan, Local Development Plans and associated Flood
Consequence Assessments.
Urban drainage
Poor surface water drainage in urban areas can cause local
flash flooding. The increase in high intensity rainfall which
climate change is expected to bring will make this worse. Catchment
Flood Management Plans will indicate where this could be a problem
now and where problems may occur in the future, and therefore
identify where integrated urban drainage plans should be considered.
Although as we have seen in the last few days traditional flood
defence will not alleviate all urban flooding in face of significant
rainfall.
Additional briefingProgress since 2001
We have made significant progress since the 2001 report in
areas such as gaining greater oversight of flood risks, creating
new guidance on climate change, improving management of major
construction projects and protecting more people (all confirmed
in the NAO Report).
Strategic Planning
We have progressed the development of Catchment
Flood Management Plans (CFMPs) in partnership with other key organisations.
We delivered the coastal strategic overview.
We met Defra's High Level Target to develop costed
action plans for all 64 priority Water Level Management Plan (WLMP)
sites that we have responsibility for by the April 2007 deadline.
A £14 million programme to implement those costed action
plans is currently underway.
Data
We have improved National Flood Risk Assessments
(NaFRA).
We have provided better flood risk data to the
insurance industry so that they can continue to provide insurance
cover to those at risk of flooding.
We have delivered our asset register in the form
of the National Flood and Coastal Defence database. Our database
now includes a more comprehensive list of flood defences. We have,
as the NAO report recognises, " ... established a more rigorous
system for classifying, recording and monitoring the condition
of flood defence assets"".
Flood Mapping
We have mapped the probability of flooding for
almost all of the land in England and Wales. Over 99% of properties
are now covered and the information is available free to householders
on our website or through our Floodline service.
Flood Risk and Development
We have supported the development and implementation
of Planning Policy Statement 25 (PPS 25) at a local level.
We have updated guidance on the impacts of climate
change on flood risk for inclusion in Planning Policy Statement
25 (PPS 25) and Flood and Coastal Defence Project Appraisal Guidance.
Flood Defences
There are 24,000 miles of flood defences and 46,000
flood defences structures protecting properties in England, a
substantial increase since 2001 when we had 11, 000 miles of defences
and 23,000 structures. This is due to the inclusion of coastal
defences, the inclusion of defences transferred from local authorities
and IDBs, as well as reflecting our more accurate and comprehensive
records.
We have inspected and classified our 3,300 systems
across England and Wales as High, Medium or Low risk
We have improved our asset inspection process.
It is now recognised in the NAO report as "effective and
practical"".
The replacement costs of all our assets at today's
prices is £20bn.
Over the 5 year period 2003-042007-08 we
will have created nearly 960 hectares of Biodiversity Action Plan
habitat.
Protecting Communities
We have improved the standard of protection for
100, 000 houses between 2003-04 and 2005-06 against the target
set by Defra of 80,000. We are also on track to exceed the target
of improving protection to a further 85,000 properties between
2005-06 and 2007-08; we will have reduced flood risk to over 164,000
houses by the end of 2007-08.
Capital Programme
Since the publication of the last report we have
dramatically improved our delivery of the capital programme. This
is recognised in the NAO report, and other `scrutinies' such as
The NAO Report on Improving Public Services Through Better Construction
(HC364 I) and the Zero Based Review (June 2006). Points to note
are:
Better project management through a national capital
project management service;
The development of a state of the art procurement
process;
Full delivery of a major project programme that
has doubled, from £104M in 2000-01 to £211M in 2005-06;
We have achieved value management savings (costs
avoided and cash released) of £22.2M since 2003-04;
Our average project development time has reduced
from by half;
Almost three quarters of the aggregates we now
use have been recycled;
Flood Awareness, Forecasting and Warning
We have developed and implemented a new, more
effective flood forecasting service that allows us to provide
greater accuracy in forecasting floods and issuing warnings;
We launched a direct flood warning system in 2005.
Almost 300,000 of properties at highest risk are now registered
on it. This means more people at higher risk are receiving warnings
when it really counts. During the June 2007 floods, over just
one week, (25th June to 2nd July), Floodline Warnings Direct sent
out 91,986 messages.
The Environment Agency's Flood Awareness Campaign
is a programme of communications to raise awareness of flood risk,
encourage people to prepare in advance and targeted campaigns
to vulnerable groups and specific communities
It is supported by our Floodline call centre in
(opened in 1999) to provide the public with recorded flood warning
information and access to trained staff 24 hours a day. The service
has received more than one million calls in the last five years,
and calls have doubled since the launch of Floodline Warnings
Direct in 2005. In June 2007 the call centre was dealing with
500 calls an hour at the peakthe daily average is 256 calls.
Floodline has responded to the challenges of efficiency,
answering 95% of calls within 15 seconds (on a par with some of
the top performing police authorities) and quality, reporting
84% overall satisfaction measured in our challenging "mystery
shopping"" quality assurance programme.
More people than ever are going to our website
for information about floodingit is a critical service
for flood warning information and advice. During the June 2007
floods we used a special version of our website to provide greater
access to the public as demand increased. The website served 11,500,000
pages and had 850,000 unique visitors in 5 days (25th-29th June)around
10 times our normally weekly traffic. During peak times we were
serving over 250,000 pages to 30,000 users an hour.
We have improved stakeholder and community engagement.
We are developing toolkits to help communities adapt to flood
and coastal erosion management policies and climate change, guidance
for land use to mitigate flood risk, and improved evaluation of
multiple benefits.
We have carried out market research since 1997
to measure the general awareness of flood risk, our role in managing
flooding, behaviours of those at risk preparing for flooding in
advance and post floods surveys to find out if people took the
right action in response to flooding. The public is more aware
of our role in flooding (71% in 2006)a 23% increase since
1997.
Awareness amongst those who live in flood risk
areas has fluctuated since we began the surveys in 1997. Awareness
rose following the Autumn 2000 floods, then dipped and rose again
following the launch of our Flood Map on the internet in 2004.
The last recorded survey (2006) saw a downturn in awareness but
our market research agency advised that high level of awareness
are unlikely to be sustained without major flooding/mass media
coverage of flooding on a national scale.
Funding
We have successfully implemented the 2002 Spending
Review and recommendations from the 2003 Flood and Coastal Defence
Funding Review.
We have restructured our emergency response teams
released efficiency of £4.7m per annum without compromising
standard of service provided.
We are increasingly moving towards focusing our
resources on high-risk systems. This has improved particularly
since 2004 when the Environment Agency gained increased responsibility
for funding decisions from the former Regional Flood Defence Committees.
Moving from past conventions to the current year where we now
invest approximately 3.5 times as much in maintenance and operations
of High risk as we do in Medium and Low risk systems.
Additional BriefingLessons learned following the recent
floods
As is our normal practice, we have commenced a review of
Lessons Learned following the recent floods.
Meantime, it may be useful for you to have our preliminary
view on some of the big issues emerging so far.
1. The weather events were severe and, in some cases,
the sort of event which would be considered less probable than
1 in 150 years.
2. Our forecasting and warning worked well.
3. Inter-agency collaboration through Gold and Silver
commands generally worked well, as far as our issues are concerned.
4. A major cause of floods and, in some cases, for example
Hull, the prime cause was the overwhelming of surface water drainage
systems by large volumes of water. We are committed to collaborating
with Defra on the urban drainage pilot studies which are underway.
This work needs to proceed with pace to ensure there is clear
responsibility given to identified bodies, probably local authorities,
working with water companies, to draw up 25 year strategies for
drainage capable of withstanding an increasing number of extreme
events. Climate change proofing urban drainage systems will require
substantial investment and considerable lead-time to re-engineer
existing drainage systems. Stronger measures need to be available
to ensure new development is climate change/flood-proofed.
5. Our defences in the vast majority of cases worked
to their design standard. The severity of the events meant that
many floods occurred because the defences were overtopped by the
extreme volume of water. The government's advised standard for
riverine flood defences is to a 1 in 100 year event. There needs
to be a review of what level of risk is acceptable and therefore
what standard of protection is needed in view of the anticipated
increased severity and frequency of such events with climate change.
6. Much of our infrastructureroads, railways,
schools, hospitals, electricity generation and distribution, police
and fire stationsis in the flood plain and needs climate
change/flood-proofing.
7. Though increasingly effective measures to prevent
inappropriate developments in the flood plain have been provided
to us, the legacy of considerable flood plain development over
the last three decades remains. We need to consider how to offer
better defences where appropriate and to retro-fit resilience
measures to buildings to reduce the damage when floods occur.
8. We welcome the announcement of additional funds. Indications
of amounts and timings are needed as soon as possible to allow
us to target these at the highest priorities in a systematic way
that delivers the most effective flood risk reduction.
9. There were two incidents involving reservoirs and
a review of the legislation and regulatory framework would be
timely.
10. Some commentators are already suggesting disaggregation
of flood risk management to more local control. We should recall
that government consulted on governance and funding after the
extensive Autumn 2000 floods and concluded that a national approach
was needed to enable effective focus on priorities and more efficient
use of resources and skills.
Also, the integrated management of rivers, including pollution
control, water resources, the land/water interface and biodiversity
as well as flooding was an important principle when the Environment
Agency was created and is even more valid now.
|