Select Committee on Public Accounts Minutes of Evidence


Supplementary memorandum submitted by the Department for Environment, Food and Rural Affairs

Questions 2-9 (Chairman):    SPS 2005—review of errors in claims and payment adjustments arising from this review

  The NAO's report (para 2.7) referred to a review of some 34,499 cases to determine whether the Single Payment Scheme (SPS) entitlements originally allocated to claimants were accurate. This note provides the results, to date, of that review and the consequential impact that this and other factors have had on payments under both the 2005 and 2006 SPS.

  The latest data extracts show the following changes in 2005 claim values for the 34,499 cases reviewed[13]:
Change in claim valuesClaimants—No Claimants—%Change—£m
Claim value increased12,611 36.528.6
Claim value decreased7,281 21.1-29.2
No change to claim value14,607 42.4
Total34,499 100.0-0.6


  The reasons for the changed values included human error in either omitting or manually inserting data (eg national reserve awards) from the various systems the Agency had to calculate entitlements and the results of both additional checks, particularly on land data, and inspection activity carried out in the normal course of business.

  In many cases, changes in claim value did not automatically give rise to an over or under payment. For example, some corrections took place after a partial payment had been made, but in time to ensure that the balancing sum was adjusted to reflect the revised full claim value.

  We have not kept separate data for cases where a top up payment was required after review of a claimant's entitlements. Nor can such data now be readily identified given the large number of partial and manual payments which have been made over the same time period.

  However, some data on overpayments is available. In addition to the review of entitlements, the overpayments occurred for a number of reasons, including the run of "duplicate" payments referred to in para. 2.9 of the NAO's report and the issuing of partial payment which proved to be greater, following eg the application of penalties, than the final sum due. In total, the overpayments are currently estimated to be:



Scheme year
No. of
overpayments

£m


SPS 200510,29920.0
SPS 20066,92517.6


*  taking account of overpayments occurring in both years the total number of claimants involved is 14,243


  From the work done so far in approximately 4,700 of these cases the amount concerned is less than €100 and will be written off. In some 70% of cases the overpayment amounts to less than £1,000 while in 0.8% it amounts to over £50,000. A plan to recover these payments is being implemented.

Questions 10-12 (Chairman):   Specific overpayments

  Details were requested of the 23 cases referred in paragraph 2.9 and figure 2 of the NAO's report as having been overpaid more than £50,000 as a result of an erroneous payment run in August 2006 when claimants received nearly double the amount due. Names and addresses are provided in the Annex to this Memorandum in respect of 19 of the cases. The remaining four have been reviewed and the overpayment is now believed to be below £50,000.

  It should be noted here that while all nineteen cases were all written to on 6 September 2006 and some telephoned around then, the RPA explained in all cases that the claimants should await an invoice before making repayment. Given the priority attached to making outstanding payments, invoices only started to be issued in November 2007.

  For the current exercise, wherever possible, invoices are only being issued once it is confirmed that there are no other outstanding actions on the claimant's account for any scheme year. Given many claimants have been affected by more than one issue that might affect the sums due (changes in entitlement values, manual payments, partial payments and penalties), this is currently a very complicated and time consuming process. To date, invoices have been issued for only two of the 19 cases, one of which has been queried and will need to be reviewed again.

Questions 28-30 (Mr Curry):   Common land issues raised by David Curry MP

  First, in respect of tenants claiming SPS support in relation to common land registered under the Commons Registration Act 1965, we understand that the tenants are not registered commoners, but exercise a right to graze the common under the terms of their tenancy agreements. In cases where a structural grazing surplus exists on common land and the common owner has chosen not to claim for it under SPS, it is possible for the excess to be distributed between tenants with legitimate agreements wishing to claim subsidy. However, It is incumbent upon the RPA to ensure that such claims are legitimate and so it is possible that evidence may be sought from owners or tenants to establish the basis for their grazing rights.

  Establishing eligibility to claim SPS support can at times involve a complex process. It is standard practise for the RPA to verify the eligibility of tenants to claim SPS (on behalf of commons owners) from the details provided on the tenancy agreement(s) involved. Copies of agreements can be provided by the tenants themselves or the agent for the Duke of Devonshire in relation to Chatsworth Estate. In the case of Chatsworth Estate, the claims concerned have not been rejected but are currently under review by the RPA.

  The requirement for rights to be exercisable over a piece of land for a period of at least 10 months flows from the EU rule governing the SPS that land used to support payment claims must be at the claimant's disposal for a designated 10 month period during the year (the 10 month rule.) Where a grazier is legally restricted in exercising rights of common so that he cannot satisfy the 10 month rule (eg where a local byelaw restricts grazing to the summer months, or the registered right is declared to be exercisable for only eight months each year), he is not eligible to claim payment under the SPS. However, where a grazier is entitled to graze all year round but chooses to remove animals from the grazing, whether because of local custom or to meet the terms of an environmental agreement his SPS claim will be unaffected. Following pressure from the UK and others, the 10 month rule will be replaced by a one day (for instance, 15 May) rule from the 2008 SPS which should in many cases help to avoid this problem arising in future.

  Finally, in respect of the calculation of livestock units (Lu), grazing rights are converted into Lus to take into account the different types of animals with rights to graze and the numerous variations of how rights have been entered onto the 1965 registers. The values used for calculating livestock units are 1.0 Lu for a cow and 0.15 Lu for a sheep. It is accepted that these values do not always reflect the local customs or practise as recorded on the common land register. However, these values have become the accepted standard since the inception of farming subsidies under the Integrated Administration and Control System (IACS) introduced in 1993. Since then, they have continued to provide the most reliable indication of the overall grazing pressure, experienced on common land, across England.

  The values are applied to each entry in each register to enable the RPA to calculate a maximum value with which the apportionment of individual claims can be made. It is not possible to consider changing this methodology due to the need to apply an approach that is consistent across all English common land.

Questions 93-100 (Mr Bacon):   Payments to Accenture

  Accenture is one of several IT contractors employed by RPA. Others include IBM and Xansa. Total spend to all such contractors between 2004-05 to the end of financial year 2007-08 will be approximately £210 million.

  Total spend with Accenture from January 2003 until the end of financial year 2007-08 will be approximately £122 million. Some £90 million of this sum is in respect of IT development, with the balance relating to business support, delivery of the live RITA service, model office and management information. The £79 million mentioned by Tony Cooper at the hearing (Q94) referred to spend on IT developments up to and including the 2007 SPS, but not preparation for subsequent year schemes.

Additional funding from Defra

  The additional funding of £40.1 million from Defra for the recovery campaign is for the period 2007-08 to 2009-10. In addition, Tony Cooper mentioned in his evidence (Q.100) that RPA had already planned investment of around £15 million. The actual figure was £15.6 million for IT changes around known policy developments for this period. The breakdown of this investment is as follows:
2007-08
£m
2008-09*
£m
2009-10*
£m
Total
£m
Defra bid16.813.5 9.840.1
RPA budget66 3.615.6
TOTAL22.819.5 13.455.7
*(*Funds for 2008-09 and 2009-10 remain to be confirmed but are likely to be lower than bid).


  This funding is being managed as a single pot to achieve the improvements described on page 21 of the NAO report.

  Spend on Accenture for IT development from the £55.7 million is expected to be approximately £32.6 million (£12.6 million for 2007-08, £10.5 million for 2008-09 and £9.5 million for 2009-10) The estimate for 2009-10, in particular, may change as the content of future IT releases is defined. In addition some elements of the work may be put to competitive tender and Accenture will be free to bid for this work should they wish.

  In addition to these development costs Accenture will, from the £55.7 million, receive up to £7 million for business support and project delivery spread across the three years.

IT developments outside the recovery campaign

  In this period there will also be other IT work outside the recovery campaign to which Accenture will contribute. This will include re-architecture of IT systems, upgrading the Rural Land Register. Costs around this work are not clear as yet.

  As part of the renegotiated contract, from 1 September 2007 Accenture receives a managed service fee of £14 million in total until 2009-10. This covers the costs of architecture support, management of delivery, technology and infrastructure management, release planning and management services etc. As mentioned in Helen Ghosh's evidence (Q.109) the new contract also includes risk-reward mechanisms around costing and delivery of IT releases.

Questions 124-127 (Mr Bacon):   Reconciliation of disallowance figures

  Paragraph 2.16 of the NAO's report refers to a possible overall correction of for the Single Payment Scheme of £292 million. This comprises:
SPS Provisions£222 million
SPS Accruals£  63 million
SPS Contingent liabilities£  7 million


  Both the accrual and contingent liabilities figures relate to late payment penalties under the 2005 scheme.

  In her evidence Mrs Ghosh (Q.63) referred to a total provision (so not including accruals or contingent liabilities) for EU disallowance of £348 million. This comprises:
SPS Provisions£222 million
Other CAP scheme provisions£  92 million
Provisions for Devolved
Administrations CAP expenditure£  34 million


  Of the £92 million for other CAP scheme provisions, £55 million relates to the arable crop payments referred to in the case study at figure 3 on page 13 of the NAO's report. The fruit and vegetable scheme referred to at Q.63 and Q.124 is aid paid to Producer Organisations. Accruals totalling £17 million were made in respect of this aid in the Department's 2005-06 accounts.






13   Additional cases to review will be identified as a result of eg appeals by claimants and on-farm inspections. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 15 July 2008