Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 1-19)

DR IAN ROXBURGH, MR JAMES MORSE AND MR MARK HIGSON

25 FEBRUARY 2008

  Q1 Chairman: Good afternoon. Welcome to the Public Accounts Committee. Today we are considering the Comptroller and Auditor General's Report, Nuclear Decommissioning Authority: Taking forward decommissioning, and we welcome Dr Ian Roxburgh who is the Chief Executive of the Nuclear Decommissioning Authority. Would you like to introduce your two colleagues on either side of you, please?

  Dr Roxburgh: Thank you, Chairman. On my right is Jim Morse who is the NDA's Divisional Director Assurance; he is the cement that links the NDA to its 19 sites. On my left is Mark Higson who is Head of the Nuclear Unit within the Department of Business, Enterprise and Regulatory Reform.

  Q2  Chairman: Shall we start off by looking at the estimates and a useful guide to this, Dr Roxburgh, you will find on page 18, figure 8, which is a: "Growth in estimated remaining lifetimes costs of the Authority's sites". Am I right in thinking that in 2007 the latest estimate for decommissioning these sites is £73 billion?

  Dr Roxburgh: Yes.

  Q3  Chairman: We are talking about serious amounts of public money. This is now the fifth attempt, Dr Roxburgh. The estimates are still growing rapidly; should they not have stabilised by now?

  Dr Roxburgh: There are three elements to a lifetime plan, Chairman. The first is that we need an agreed process which can apply equally to all of our 19 sites so that the numbers emerging from each of those sites are comparable one with the other. I am confident that that process is now robust. It has been subject to significant external assurance. That makes us unique in the world in the sense that we are the only country, as far as I know, that can actually roll up its costs individually into a national figure. The second element of a lifetime plan is to actually understand what it is we have inherited at each site—the inventory of challenge—and then to schedule it in a logical way. The third element relates to cost. At one level what you say is absolutely right but at another level there is a slightly contradictory position. As the Report recognises it was always going to take a number of years to get to the final figure and in effect we have a process that everybody always recognised from the start would take four or five years. We are only part of the way through that process. In the normal course of events if somebody asks you to do something over five years you run the course and give them the figure at the end of it. However, because of our obligation under the FRS, we have to publish a number each year. It looks as though the number is rising; it was always going to rise. That is the explanation.

  Q4  Chairman: That sounds fine but, for instance, in 2005 to 2007 the costs have risen again by £11.7 billion. I think the public would understand if we were talking about something which was over a long period of time and difficult technology—we all know the difficulties you are facing—but look, for instance, at paragraph 2.8 at that first bullet point at the top of page 19. It is not rocket science; there are costs which you would expect: engineering support, human resources, financial services which are also increasing rapidly. This worries me because it suggests that perhaps you are not really in control of what is going on. This is not very difficult stuff; this is all human resources really.

  Dr Roxburgh: We share your concern and if I go back to the White Paper in 2002 the Government clearly took a view then that whilst the sites we have inherited were good in the context of winning a cold war or developing new methods of generating electricity, they were not the right vehicle to manage hazard reduction and decommissioning or indeed the management of the numbers attached thereto. At the same time the strategy said that it would not be until you brought in world class management that you would get absolutely world class numbers. I need to be quite clear, this is not a case in terms of "two legs bad, four legs good"; we have significant problems with the supply chain on the private sector side producing sound numbers as well. We have evidence of first class management already with our first competition, the low level waste repository contract; I will not give you the exact figure, but I can assure you that the figure that is formed into the contract shows a double digit decline in the lifetime figure of the low level waste repository.

  Q5  Chairman: One would expect there to be quite significant variations when you are talking about this very difficult technology over a long period of time, but if you look at the next bullet point you can see that even costs incurred in the near term, where you would have thought there would be much more certainty, it says here, "Costs expected to be incurred in the near-term had been subject to significant revision. We compared the size of the 2005, 2006 and 2007 lifetime plans over the first five-year period covered by each of these plans. For this period, the latest lifetime plan had aggregate costs 41% higher than the 2005 plan." This leads me to suggest to you that you are not really in control of what is going on and these estimates actually mean very little indeed. If we were to reconvene this inquiry in three or four years' time we might not be talking about £73 billion but a figure far in excess of that. There is no credence that we can give to any of these figures.

  Dr Roxburgh: I have explained to you that we are on our way through a process; I have explained to you that the supply chain has its weaknesses. One of the things that a world class management will bring is better management of the supply chain.

  Q6  Chairman: When we return to this at the end of this Parliament or the beginning of the next we will not see near term revisions of this order, we will not see this sort of increase in human recourses; all this will be under control will it? Can you give us that commitment?

  Dr Roxburgh: What I can give you is a rendition of the issues. We have 18 million cubic metres of contaminated land that we know of.

  Q7  Chairman: Can I just stop you there. "What I can give you is a rendition of the issues", what does that mean?

  Dr Roxburgh: What it means is that until you actually get into certain of the waste streams that we have inherited, for example we have a shaft at Dounreay which is tens of metres deep; it is back filled with waste, the exact nature of which is not known; until you get in there you cannot with certainty describe the cost of dealing with it.

  Q8  Chairman: That is fair enough; it is much better to tell the truth. The fact is that you are dealing with such difficult technology or circumstances that you simply do not know at this stage.

  Dr Roxburgh: That is not the case.

  Q9  Chairman: This figure of £73 billion is reliable, is it?

  Dr Roxburgh: Against where we are for the moment it is, yes, but as our understanding increases so the figure will.

  Q10  Chairman: Could it be £10 billion out or £5 billion out? Give me a ball park figure. We are the Public Accounts Committee and would like to have some idea. That is a staggering amount of money. We are already faced with this bill of £73 billion. We would like, as the Public Accounts Committee which is supposed to protect the interests of the tax payer, to have some idea of what this is going to cost us. I think, from what you have said so far, we have no idea because you simply do not have enough information at your fingertips yet.

  Dr Roxburgh: I have indicated to you that this is a four or five year process. We are not through it yet. I have indicated with the LLWR that the strategy is working. I have already seen serious evidence that at Dounreay, for example, we might also see that same model. The model that has been imported from the States is this, that over a period of four or five years, as you understand more, your costs increase. The remit is to turn every stone, if you turn every stone you discover more by definition. The costs then plateau and then as you apply innovation and world class management they start to come down. If you ask me for confidence, I am confident that model is actually working in the UK.

  Q11  Chairman: Can you help us at all about this figure of £73 billion? I am sorry to press you about this, but you can understand our concern; we would like to have some sort of idea as to whether this £73 billion bears any relation to reality.

  Dr Roxburgh: We are in the middle of a process and that is the figure we have at the moment.

  Q12  Chairman: Fair enough. That is an honest answer; it is much better to be honest. Would you like to look at paragraph 2.11, please? You have put a lot of time into these lifetime plans. Paragraph 2.11 says, "We found less evidence of challenge to the nature of the work content". That of course is NAO speak for saying that you are not actually being sufficiently robust in challenging these site licensees. Is that fair?

  Dr Roxburgh: At one level it is. As I say, we focussed on getting process right; we have now committed ourselves to much greater assurance over the next three years of the CSR. Could I explain the thinking behind that? If we are turning over approaching £2.8 billion a year and if we were engaged in a £2.8 billion take over then it would not be unreasonable to spend £30 million or £40 million on doing due diligence on that. You will be aware, I know, that for want of £25 million elsewhere in our estate we are having to slow decommissioning down. I have had to strike a balance between what it is reasonable to spend, given that there are alternative dispositions for that money where that money can really deal with hazard and decommissioning, and I have judged that over the next three years £5 million per year is about right.

  Q13  Chairman: So let us look at what we can now spend on decommissioning. We have had a discussion about the total bill so if we now turn to paragraphs 3.11 onwards on page 24 it says in the chapter heading—which is usually a good way of summing up the argument—"Significant resources have been allocated to decommissioning. But the progress at some sites has been hampered by emerging pressures on the Authority's financial position." Further on, at paragraph 3.12 at the top of page 25, we read, "So to the extent reductions are required these tend to fall on decommissioning Magnox". So lack of money has mainly hit decommissioning projects has it not? That is the problem we face.

  Dr Roxburgh: The budget that the NDA has has gone up year on year. The CSR settlement that we have negotiated with government sees a £671 million increase in hard cash and a 21% increase in grant in aid. In our strategy on pages 20 and 21 there is a very clear statement that our number one priority is hazard reduction. I very much regret that I am not able to satisfy all the demands upon our budget. The Government inevitably has that tough choice between affordability and desirability.

  Q14  Chairman: You have not answered my question. You have a worsening financial position; that is now hitting your ability to deal with decommissioning Magnox which is what you are supposed to be doing.

  Dr Roxburgh: The answer to that is yes, we are doing less Magnox decommissioning, potentially.

  Q15  Chairman: Why did you cut support costs first then?

  Mr Morse: You will see elsewhere in the Report a note that NDA have initiated a review of fixed costs across the estate out of that £2.5 billion that we applied to decommissioning, commercial operations and site support. During the course of next month that plan will come to fruition and we will be able to review plans across the estate to reduce fixed costs we hope upwards of 10%.

  Q16  Chairman: Are you going to continue to use costs plus contracts? How can you justify doing so?

  Dr Roxburgh: In general no we are not. In the competitions that we are currently running we are moving very much away from cost plus; they will still be cost reimbursable. At the moment the sites are paid on a performance based incentive which is a percentage of turnover assuming they deliver particular outputs. The competitions that we are currently running contractualise the winning bidders to actually deliver the figures against the lifetime plan improvements that they have proposed as part of the bidding process. If you will bear with me a moment I can take you through a schedule which I think illustrates the point very well, of how we are moving to a much more competitive environment.

  Q17  Chairman: This is dealt with in paragraphs 4.24 and 4.25 of the Report. Do you want to refer me to something else?

  Dr Roxburgh: No, I do not. What I want to do is share with you the incentivisation in the new form of contracts that we are currently in the process of letting. Initially we are offering a base fee because we want to attract world class teams; they come at a cost. It is part of the competitive tension when people bid in to win our contracts to let us know for how long they would want the base fee and what amount of base fee they would require. We take the view that by year four there should be no more base fee. At the same time, we are inviting the companies to rapidly move away from the current performance based incentive mechanism and move onto an efficiency fee target cost share basis. If I could put some flesh around that, again there is competitive tension; we are inviting the companies to tell us what proportion of the money saved they would want to take as part of the competitive dialogue process. At the moment if you looked at the PBI arrangement the fee paid in Sellafield, for example, in 2006/2007 was £53 million. We believe the minimum sum you might bid in at on the competition is about £30 million, the maximum will be £62 million. They have to decide whether they want to bid against that. Bearing in mind its efficiency fees which are funding the fee they should be self-funding.

  Q18  Chairman: You mentioned Sellafield but you are letting the Sellafield contract first and then you are trying to get a better contract. Is that right?

  Dr Roxburgh: Sorry, I do not quite understand the question.

  Q19  Chairman: How are you going to do the Sellafield contract? This is dealt with at paragraph 4.25 on page 34. Are you going to try to get a firmer, more robust contract and then let Sellafield? How are you going to do it?

  Dr Roxburgh: As part of the competitive dialogue process the bidders have to interrogate the current lifetime plan 2007 through something called an initiative cost base model. They have to show how they will improve on that existing lifetime plan and that forms the new base line that we will measure them against.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 10 July 2008