Select Committee on Public Accounts Minutes of Evidence


Supplementary memorandum submitted by the Ministry of Defence

Questions 4-7 (Mr Edward Leigh): Transfer of £1 billion worth of defence procurement between budget lines

  The principle applied to the transfer of costs from the projects listed was to ensure that the costs were allocated in such a way that the performance of individual project teams in controlling direct project costs could be effectively monitored and measured, for example in maintaining Defence critical industrial capability, in accordance with the Defence Industrial Strategy. Where costs have been transferred to other equipment and support budgets we have sought to absorb the impact across the wider equipment and support programme (some 600 project lines) by managing them within the context of the Department's Planning Round process. In each Planning Round cost growth is addressed (as well as the introduction of new capabilities and priorities) across the whole equipment procurement and support programme.

  Capability Audits and Balance of Investment reviews identify where opportunities exist for the Department to make choices on how to re-balance the equipment and support programme, taking into account current pressures such as operations and the need to deliver Defence priorities. It also allows the Department to review its priorities and seek to absorb the transfer of costs from the MPR community within the headroom generated across the wider equipment and support programme. Investment can then be reduced (or indeed increased) accordingly in areas of capability and support, with least impact on current outputs and operations to accommodate these costs; we are not able to identify specific reductions relating to specific transfers, and the related impacts, as they are dealt with across the whole plan.

Question 110 (Keith Hill): It is the case, is it, that these kind of slippages in time and in cost are experienced across the board by our allies and indeed in other countries, as far as we can tell? Perhaps we could have one or two examples of that

  Comparison of MoD performance in terms of time and cost to that of our allies and indeed other countries is difficult as the fundamental assumptions underpinning the project can be difficult to establish or vary significantly. The baseline for a like for like comparison is therefore difficult to establish. Nevertheless, a number of studies and benchmarking exercises over the past few years have confirmed that in general terms the MoD compares favourably in its overall acquisition performance compared to International Counterparts. Following the Committee of Public Accounts hearing on Major Projects Report 2006 a specific comparison of cost history of nuclear attack submarine construction in the United Kingdom compared to the United States of America was provided. This confirmed that despite cost overruns on the Astute Class submarine the forecast outturn was below the trend line four comparable submarine projects.

  Although a comparison of individual projects on a like for like basis remains difficult a number of studies and benchmarking exercises have focused on a more generic assessment of performance. These include:

    —  The former Defence Procurement Agency (DPA) undertook an annual assessment of how good Project Management Capability was compared to other project management organisations, including the Australian Department of Defence, by applying the Human Systems Ltd Corporate Practice Assessment. The DPA scored highly in terms of its approach, coming second overall in the entire network and ranked ninth overall for its deployment. Overall the DPA ranked in the top quartile of participants. This assessment will continue for Defence Equipment & Support.

    —  Work by HVR Consulting Services Limited in 2005, at the request of the Department, to scrutinise cost and time estimates for 22 major programmes, using information from the Major Projects Report 2004, and comparing this to outcomes in other nations and historic Departmental projects. Thirteen of the projects scrutinised were forecasting to deliver at or below the cost forecasts produced by the model, and 21 projects were expected to deliver ahead of the schedule determined from analysis of comparable programmes.

    —  The RAND report—Why has the cost of Navy Ships Risen?—a macroscopic examination of the trends in US Navy ship costs over the past decades published in 2006 stated that the cost of US nuclear attack submarines was $2.427 billion. This figure was also quoted by the Electric Boat President John Casey during a briefing in June 2006. A generic exchange rate for that period would make the cost of each boat some £1.403 billion. Current projections suggest that in steady state production ASTUTE will outturn below £1 billion per hull.

    —  In 2005 John Dowdy of McKinsey & Company and Megan Schwartz of University College London's Defence Engineering Group published a comparison between the US and UK. This set out to compare performance of 20 major projects spanning the last decade with the sample constructed to yield a small number of comparable programmes in each major project category. The analysis of the sample by Dowdy & Schwartz showed that the US has suffered four times greater cost overruns than those experienced in the UK, with an average 29% increase in the US, versus 8% in the UK, as measured by unit costs versus original approval. In schedule performance the average delay for the sample was 46% for the UK and 41% for the US, although the US analysis was based on less data. The US result was also significantly influenced by delays on one programme—the V22. With this removed average schedule overrun reduced to 23%. The article did, however, acknowledge that a direct comparison was difficult.

    —  The United States Government Accountability Office (GAO) carries out an annual assessment of selected defence programmes and although, as highlighted earlier, it is not sensible to make any direct comparison the most recent report, published 31st March 2008 shows that for the 95 programmes assessed total acquisition costs increased 26% from first estimates and the average schedule delay in delivering Initial Capabilities was 21 months.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 July 2008