Select Committee on Public Accounts Fortieth Report


1  Learning the lessons from past difficulties in managing expenditure

1.The Department for Environment, Food and Rural Affairs (the Department) is responsible for tackling climate change and maintaining our natural environment. Along with its agencies and non-departmental public bodies, the Department delivers a range of different services and operations. Most of these activities are funded by the taxpayer, and the Treasury set the Department an expenditure limit of £3,617 million for 2007-08. The principal objective of the Department's Accounting Officer and Management Board was to manage the resources efficiently and effectively within the funding provided.[2]

2.  In May 2006, the Department's Management Board recognised that, as a result of poor financial management, the Department faced a significant risk that it would exceed its expenditure limit in 2006-07. The Department instigated a series of budget reductions to generate £170 million in savings, but the mid-year timing of these reductions had an adverse impact on policy delivery within the Department and its delivery bodies. The Marine and Fisheries Agency, for example, deferred a vessel decommissioning grant scheme aimed at reducing over-fishing by helping trawler owners to leave the industry, and the Veterinary Laboratories Agency reduced its scientific surveillance work.[3]

3.  In 2007-08, the total cost of the Department's approved business plans exceeded its resources by some £66 million, and in April and May 2007, certain Policy Groups within the Department declared financial commitments above the agreed budget allocations. The risk of overspending was compounded further by a number of unforeseen events, including floods, and outbreaks of foot and mouth and avian influenza, which required additional expenditure of some £60 million. A series of meetings with senior managers was required to agree budget reductions. This meant that final budgets were not allocated to Policy Groups until August 2007, five months into the financial year.[4]

4.  At the start of 2006-07 and 2007-08, the Department's Management Board agreed budgets which exceeded the funds available, because in previous years budget holders had typically over-estimated their budgeted expenditure. The Board, therefore, believed that the excess budgeted expenditure would not materialise. The difference between the Departmental Expenditure Limit and actual expenditure had declined in recent years, however, and in 2005-06 the underspend was less than £1 million (Figure 1). Senior officials were not sufficiently aware of the impact of changes in financial practices within the Department which had led to the tauter budgeting.[5]

Figure 1: The Department's actual expenditure came close to its Departmental Expenditure Limit in 2005-06

Source: C&AG's Report, Figure 3

5.  The absence of a Finance Director with Management Board status contributed to Board Members' lack of awareness and understanding of the effective management of expenditure. Until April 2007, the Departmental Finance Officer had reported to the Director General of the Service Transformation Group. Subsequently, the Accounting Officer replaced the Finance Director and some members of the finance team. She upgraded the Financial Director role to a Director General with a place on the Department Board, reporting directly to her. The Finance Director is now empowered to hold each part of the Department to account for their budgets. He is supported by 27 fully qualified accountants in the Department and 29 in training, as well as a further 48 accountants in the Department's agencies. The Accounting Officer and Management Board intend to undertake the Treasury's on-line computer training course to improve their understanding of good financial management. [6]

6.  The Management Board's monitoring of financial performance had been hampered by difficulties in obtaining timely and realistic monthly profiles of expected expenditure from delivery bodies. Following the change in Finance Director, however, the Department introduced more robust arrangements to collect financial performance data from all parts of its operations on a timely basis. Delivery bodies now submit monthly financial data direct to their associated sponsor team in the Department.[7]

7.  Following the introduction of a Financial Management Improvement Programme for 2008-09,[8] the Department has agreed budgets in accordance with the Comprehensive Spending Review 2007 allocation. The Accounting Officer does not expect the problems of 2006-07 and 2007-08 to recur in 2008-09. Better project management, leading to closer management of expenditure by teams, is expected to reduce the likelihood of resources being significantly over- or under-spent. The Department has been innovative in applying project management techniques to implement policy related topics, but has not applied these techniques effectively to internal projects and procedures. The Management Board has now put in place more rigorous financial and outcome monitoring systems. Intensive business case development for new projects means that before approving an activity the Management Board is aware of the expected outcome, its risk and costs, and the impact on customers. Senior responsible officers for budgets would be told that their key objective was to manage finances effectively.[9]


2   Q 57; C&AG's Report, para 1 Back

3   Qq 1-3, 41; C&AG's Report, paras 1.4, 2.6; Appendix 2 Back

4   Qq 2, 13, 28-29; C&AG's Report, para 2.7 Back

5   Qq 3, 28-29, 35-41; C&AG's Report, paras 1.3, 2.5, Figure 3 Back

6   Qq 13, 16; C&AG's Report, para 2.16 Back

7   Qq 8-9, 13, 16-18; C&AG's Report, para 2.8 Back

8   The Financial Management Improvement Programme aims to improve financial management capabilities across the Department, and to achieve faster preparation and completion of its annual accounts. Back

9   Qq 2, 4, 12-13, 42, 50, 57, 62; Committee of Public Accounts, Twenty-seventh Report of Session 2005-06, Lost in Translation? Responding to the challenges of European Law, HC 590; Fifty-fifth Report of Session 2006-07, The Delays in Administering the 2005 Single Payment Scheme in England, HC 893  Back


 