Select Committee on Public Accounts Forty-Fourth Report


1   Delivering the roll-out project

1. In March 2000, the Prime Minister announced plans for combining the Employment Service and the Benefits Agency into a new Agency, Jobcentre Plus. In autumn 2001, the Department for Work and Pensions (the Department) launched 56 pathfinder projects to test the feasibility of combining benefits and employment services within one organisation, and in April 2002, the merger of the two bodies took place. Subsequently, the Treasury approved a business case to roll out an integrated network of offices across Great Britain over four years, at a cost of £2.2 billion.[2]

2.  The first 225 offices were delivered using the contractual arrangements in place for the Benefits Agency and Employment Service estates. Following a new tendering process, 14 contractors were subsequently appointed to deliver the remainder of the programme to fit out offices using an innovative partnering approach. In the light of the announcement in 2004 of a Government-wide programme of efficiency improvements, Jobcentre Plus staffing was reduced by 15,000, and benefits processing was transferred from Jobcentre Plus offices to 79 centralised processing centres. These developments and revised plans resulting from tighter internal management, led to a reduction in the planned number of offices to 860 from the original estimate of 1,000.[3]

3.  By April 2008, the new network had been largely rolled out across the country. Two offices—in Portsmouth and in Laurieston—remain to be completed. In two further cases, developments will be funded from outside the roll-out programme which is now closed; one existing office in Cumnock, which will be refurbished, and one in Glasgow Pollok where suitable premises have not yet been found. Some of the offices were completed later than the original four-year time frame mainly because of changes to the scope and design, particularly the need for some re-planning following the changes in scale arising from the efficiency programme. Overall, however, the total cost of the roll-out of £1.9 billion was £314 million less than budgeted.[4]

4.  The initial budget and the planned number of offices were based on development assumptions before the network was finalised. Improvements to the anticipated service levels were made as the project progressed and the team's understanding of what was needed changed. Alternative service channels were developed and benefits processing within Jobcentre Plus was centralised. The revised approach required fewer staff, and hence fewer offices in the network.[5]

5.  The governance of the programme exemplified good practice. There was support from the senior management of the Agency, a clarity of purpose and vision of the customer service improvements sought through the programme, a consistent senior management team throughout the programme, and a gateway process to control the implementation at each office. Importantly, the team also learned as the project progressed. The project came in under budget partly because the team was prepared to modify the plans in response to internal pressures and developments external to the project.[6]

6.  A major feature of the senior leadership team was the decades of experience in the Agency's activities which they brought to the project. This experience was combined with their understanding of front-line issues acquired through working their way up through the organisation from relatively junior positions. They applied this experience in consulting staff on the ground, and in building plans with the support of staff and other local stakeholders.[7]

7.  Other government bodies planning procurement and service transformation projects of this kind could learn much from the successful implementation project. The DVLA, the Driving Standards Agency and the Courts Service have sought advice from the Agency and, as a member of the permanent secretaries' management group and the head of profession for operational delivery, the Chief Executive of the Agency is well placed to disseminate the lessons more widely. Projects to centralise benefits processing and to introduce the Employment and Support Allowance have benefited from the lessons learned in the office roll-out project.[8]

8.  Alongside refurbishing offices, the business change programme introduced new ways of working for staff to transform the service for customers. Listening to people at the front-line and engaging them in the project are critical success factors, and the Agency provided a small amount of funding to allow local staff to work out how best to deliver services in the new environment. Equipping staff with the right skills to meet the higher standards of service is also important. The Agency acknowledged that not all staff were comfortable with the new way of working, but hoped that, with greater experience of the changes, staff would become more content with the changes.[9]

9.  The project team recognised the importance of local ownership of the programme and initially allowed local discretion over some aspects of implementation. As the project proceeded, however, they identified that this approach reduced efficiency and led to more space being used in the early offices, with a likely impact that the project would exceed its budget by some £100 million. The team recognised the need to tighten financial management, even at a risk to local staff morale, which they mitigated by explaining the reasons for the change in approach to local staff. A further £17.4 million might have been saved had these disciplines been in place from the start. Forty-seven of the offices rolled out had been closed subsequently. £20 million had been spent in refurbishing these sites and a further ten offices that Jobcentre Plus intends to close, but closing them had saved £13.5 million a year in running costs. [10]


2   C&AG's Report, paras 1.2-1.5  Back

3   Q 64; C&AG's Report, para 1.10 Back

4   Qq 86-90; C&AG's Report, para 2.10 Back

5   Qq 8, 25-26, 28-32, 44, 58-59 Back

6   Qq 2-3, 11, 13 Back

7   Qq 37-43, 97 Back

8   Qq 11-17, 108 Back

9   Qq 91-92, 97 Back

10   Qq 9,18-24, 33-34, 45-47, 54-56 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 11 September 2008