Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 40-59)

DEPARTMENT FOR TRANSPORT

9 JUNE 2008

  Q40  Mr Bacon: I have just been reading Lou Gerstner's biography; he was the chap who turned round IBM. I would just like to ask each of you a question. Mrs Moorhouse, you are a graduate of Cambridge.

  Miss Moorhouse: Oxford.

  Q41  Mr Bacon: I am sorry; I can see how you could be offended by that. You were at Oxford where you read PPE and then you were in the private sector for ten years. If I may say so, you have a reasonably smart looking CV. What degree did you take? What honours degree did you take?

  Miss Moorhouse: Politics, philosophy and economics.

  Q42  Mr Bacon: What class of degree?

  Miss Moorhouse: Upper second.

  Q43  Mr Bacon: Mr Devereux, you were reading maths at St John's College, Oxford. What class of degree did you get?

  Mr Devereux: I got a second in the days before they divided them.

  Q44  Mr Bacon: I am sorry about that! What Lou Gerstner says in his book right at the beginning when he takes over IBM and tries to figure out what is wrong with it that IBM, just like the Civil Service, has a very large concentration of very talented people who are highly educated. He says, "I began to puzzle over how such intelligent people could arrive at such a morass". What I want to know is how is it that such intelligent people as yourselves arrive at such a morass.

  Mr Devereux: I think in order to answer that you are inviting me to conclude that I am in a morass. I have told the Chair already that the situation we find ourselves in, in this snapshot, is not acceptable. We will turn this round. How did we get here? The NAO has written down at some length the four or five contributory factors which actually all connect with each other as you can see: the time, the pressure, the need to actually get on and define business processes (which you acknowledge are difficult to do). If you put all of those things together it comes to a difficult position. Was it the failure of intelligence to even perceive this? We took advice from some serious people. We did not embark on this on a "Let's just do shared services"; we have done quite a bit of work on it. The whole reason for having an outline business case followed by an interim business case once you have got a design is to enable you to note some of these things. We went through it in stages. It is the case, as the record shows, that in that critical period from about April 2006 to August 2006—post the design and post the letting of contracts to suppliers who we must assumed believed they could deliver this thing for August 2006—a lot of things came out which actually meant that it was not possible to do it in that time.

  Q45  Mr Bacon: You remind me exactly of what Helen Ghosh said to us not so long ago about the Rural Payments Agency: "We advised ministers it was possible when in fact it was impossible".

  Mr Devereux: I did not advise ministers.

  Q46  Mr Bacon: I did not say that you did, but you just reminded me of what you said.

  Mr Devereux: Well, I am sorry.

  Q47  Mr Bacon: The thing that strikes me is that the problems that you have encountered are in some respects absolutely classic: the failure to test adequately. This is not new; we had that in tax credits; we had that over the Criminal Records Bureau; we had that over the Passport Agency. There was the failure to have somebody clearly in charge. When I was first on this Committee seven years ago we looked at the National Probation Service and the implementation system strategy; it had seven managers in seven years. The NHS IT systems had six bosses in five years. The Bowman Radio Communication System had nobody in charge. It says here quite clearly at paragraph 1.22 on page 16: "Neither the Programme Board nor the Driver and Vehicle Licensing Agency initially appointed any one individual in Swansea to coordinate the overall design of, and activities across, the five teams, or delegate sufficient authority to the teams to act without continual reference to the centre. Consequently, progress reporting to the Programme Board in the central Department was often confused and contradictory." Higher up it says, "The division of responsibility ... weakened reporting and accountability and slowed communications. ...Contractors working on the Programme told us that it was often difficult to resolve issues as they received inadequate or insufficient guidance." Surely getting these questions resolved early on of who is in charge, who is responsible and how the Programme management is actually going to operate is essential to making adequate progress. Why was that not done?

  Mr Devereux: You will understand that I have spent quite a long time preparing for this hearing to try and make sure I understand that story. Let me just observe the following: because this was going to be a departmental exercise which necessarily required all the different seven business units you describe to subscribe to a single set of processes and yet it was being built by the DVLA and its contractor without trying to make it entirely a DVLA takeover, there is a sort of inherent tension in there which I fear was never adequately resolved.

  Q48  Mr Bacon: It was the responsibility of the people at the top running the show to identify those tensions and to resolve them so that the poor contractors at the bottom are not running around in seven different directions at once.

  Mr Devereux: I agree.

  Q49  Mr Bacon: It was not done, was it?

  Mr Devereux: We have to look at this in three pieces. There was a period in 2005/06—virtually the whole of that financial year—during which the Department was engaged in the design process. At that stage, very clearly, the central department was coordinating, because, for the reasons I have given you, we wanted to make sure this was going to turn up with a system at the end of the day which each of the agencies would buy into. That is quite different by the time you get to April 2006 by which time we have appointed a director of Shared Service Centre in Swansea. That individual has themselves signed contracts with IBM which are warranted to deliver the system that we have now designed by a roll out date of 31 August 2006. There is one story going on in respect of the design period, 2005/06; there is another one going on in respect of April to August 2006.

  Q50  Mr Bacon: If IBM are going to fulfil their obligations or what it says it is going to do, you have to fulfil what you say you are going to do. Paragraph 1.16 at page 13 it says clearly: "Early fixed price agreements with IBM" (which would have saved you money presumably) "had not been successful as the Department had not fulfilled its obligations in terms of making appropriately skilled staff available or making design specifications sufficiently clear". There is no point entering into an agreement with IBM if, when it comes down to it, you cannot make available the appropriately skilled staff. Surely if you enter into the agreement you should make sure you are able to make the appropriate skilled staff available or you do not do it.

  Mr Devereux: Correct.

  Q51  Mr Bacon: But you did not.

  Mr Devereux: What we did was recognise that that commitment was required. It was clear to the chief executives in each of the agencies that we needed staff to be deployed in Swansea from their businesses with detailed knowledge of their own processes and preferably with detailed knowledge of the SAP system. The reality was that those staff were not delivered.

  Q52  Mr Bacon: I would just like to go back to something you said to the Chairman. You talked about the timetable being aggressive by design. It was a wonderful piece of euphemism actually. You said it was aggressive by design but the safety valve for this was intended to be slippage in migration. That sounds very much like, "We decided to do it fast and if it did not work we would do it slow". That is basically what you are saying.

  Mr Devereux: You can parody it in that way.

  Q53  Mr Bacon: I am actually trying to translate it into English that all of us can understand.

  Mr Devereux: I did not say with the intention of.

  Q54  Mr Bacon: Neither did I; I said, "And if it does not work we would do it slow".

  Mr Devereux: No, you said "intended" I think. We could have set off to design and do this in two years; that was a choice open to us in 2005. That is effectively what we have done, we delivered this in April 2007, we started in April 2005. We chose not to do that. We chose to intend to try to get this delivered in April 2006 in a one year timeframe. If you were to say to me, "Surely that was madness, why did you set such an aggressive timetable; you must have had a plan B up your sleeve", the recognition was that if we did deliver this in 18 months that would still be a good outcome. The question is: do you think that if you give an organisation—and certainly seven organisations—more time, is that time well spent? The judgment the Board was taking, quite deliberately was "No, let's put some pressure on this organisation; let's make sure that we try to get this through".

  Q55  Mr Bacon: Surely to goodness, Mr Devereux, whether the time is well spent or poorly spent depends on how it is managed from the top.

  Mr Devereux: That is correct.

  Q56  Mr Bacon: I would just like to ask you about the testing. In paragraph 1.19 it says, "To limit cost increases, in November 2006 the Programme Board removed some technical elements of the Programme, including the full pre-production environment." That is a wonderful way of putting it, but imagine if you were developing a motor car and your bosses said to you, "Mr Devereux, I know you are developing a motor car but in order to save on cost increases we want you to remove the full pre-production environment". When finally the car hit the showrooms would you want to buy it or get into it or drive it, when you knew the pre-production environment to this car had been removed?

  Mr Devereux: If you are understanding by "pre-production environment" something that was on the critical path to the first of April you are misunderstanding what that is.

  Q57  Mr Bacon: It means adequate testing, does it not?

  Mr Devereux: No, it does not; that is what I am trying to describe. This piece of the software system is basically there to replicate the built system in order that subsequent releases could be safely tested off the live system. Since in this period we are actually talking about getting to the start of the first live system, it is strictly not on the critical path.

  Q58  Mr Bacon: It says further down in that paragraph that they were actually in practice tested on the live system: "When the first two agencies began using shared services in April 2007, all further system upgrades and remedial testing were conducted on the live system".

  Mr Devereux: That is what I have just said. The result of not having the pre-production environment was that subsequent releases were tested on the live system.

  Q59  Mr Bacon: What I meant was inadequate testing of the thing before you go live. That is all I was trying to say.

  Mr Devereux: I am making a distinction in that going live for DVLA and the DSA on the first of April 2006 did not strictly require the pre-production environment in the way you have just described. It is required absolutely for the safe testing of subsequent releases. What the Report is saying is that actually in the first instance, that environment not being available, that safe testing environment did not exist. That is why we subsequently put it back in again.

  Chairman: I am sorry, I cannot delay your migration any more Mr Bacon, your time is up.



 