Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questinos 20-39)

DEPARTMENT FOR CULTURE, MEDIA AND SPORT

30 JUNE 2008

  Q20  Keith Hill: I would expect to see all of these set out on a piece of paper. How would they be expressed on a piece of paper?

  Mr Burr: There would be what is known as a risk register, which would list what those risks are, and it would give some indication of how likely they were to happen, how serious they would be if they did happen, and who was responsible for attending to them.

  Q21  Keith Hill: In paragraph 1.19 you use the phrase "cross-cutting risks to the programme, which may not be visible to individual delivery organisations". How does that work?

  Mr Burr: An individual manager of a particular project or an individual player in the larger programme may be very conscious of the things that they have to watch out for but they may not have a bird's eye view of the links between the different components of the programme and the issues that those may raise, hence the need for top-down oversight of the programme as a whole, which is all we were really seeking to emphasise.

  Q22  Keith Hill: In paragraph 1.20 you use the phrase "programme-level risks". What is a programme-level risk?

  Mr Burr: A risk for the whole programme as distinct from a risk for a particular project within that programme.

  Q23  Keith Hill: How does that work, a risk for the whole programme?

  Mr Burr: Again, one would expect to see at that top level an identification of the risks largely relating to the whole being more than the sum of its parts, as it were, so that there are risks relating to the whole which are distinct from those which relate to the individual components, and those too need to be managed.

  Q24  Phil Wilson: When we won the Olympics, we knew straight away that the two issues that we would be faced with would be first, cost overrun, and secondly, will we be on target. Every Olympics, ever since there has been an Olympics, it has always been the same, and the press would obviously focus on that, whether it is the truth or not. I just want to reiterate what Keith Hill has said, which is in paragraph 22 of the Report on page 7, which is just to say the construction programme is broadly on track, procurement systems you have put in place are being handled well, et cetera. I think basically you have got off to a good start really. I just wanted to ask a few questions about managing the budget. In paragraph 2.14 of the Report on page 18 it talks about £853 million of savings you have assumed in your cost forecast. How much of that has been secured already?

  Mr Higgins: Quite a lot of that has been secured through redesign and targeting of the individual tenders so, as Jonathan said earlier on, we have just under £3 billion worth of contracts now let; a lot of the design work on those, including the main venues, is well-developed, with even subcontractors and suppliers in place. The importance of securing those savings is to ensure that the process of design development, planning, and then tendering and procurement keeps track with the overall project timetable, and that has been achieved over the last year.

  Mr Stephens: It is worth, if I may, citing the example of the work that has been done on the reconfiguration of Olympic venues as a good example of how we aim to bear down on costs. Our aim now is to ensure that we build the absolute minimum of temporary venues and use, wherever possible, existing venues within London. The plan for the venues has been reconfigured, releasing significant savings as a result of that.

  Q25  Phil Wilson: You do not say these savings will be at the expense of the legacy benefits of the park and the venues?

  Mr Stephens: No, indeed. This is partly in order to protect the legacy benefits and to focus the spending on the venues and infrastructure that will be there permanently.

  Q26  Phil Wilson: The other point is on paragraph 2.20, Mr Stephens. How were you able to forecast the cash flow requirements for the life of the programme when you have not completed a Programme Plan yet?

  Mr Stephens: We do have a complete cash flow forecast for the various different funders and over the life of the programme through to 2012. Of course, that will change as the rate of spend changes, and we have also considered with all the funders the various contingency plans we need to ensure that the cash can always keep flowing.

  Q27  Phil Wilson: Another question. In figure 4 it shows there are several pots of contingency, totalling nearly £3 billion. When contractors know you have all that contingency, how does it incentivise strong project and budget management?

  Mr Higgins: As was noted in the previous Report to PAC, incentives should be put in place with contractors to save money, and that is exactly what we have done on the Stadium and the Aquatic Centre, for example. So we incentivise behaviour that is aligned with our behaviour to get the right outcome but also time and cost. If you look at the three big pots of money, the first amount, which is project-level contingency, we expect to spend. That has been created in many ways from the value engineering and the cost savings we have carried out over the last year. It has been approved by the Department to commit to spend, but we then target that within our organisation with strict change control. The second £1 billion is set aside for unexpected ground conditions or inflation and, as an example, the price of reinforced steel a year ago was £400 per tonne; now it is £800 a tonne, so that second £1 billion is to allow for unexpected inflation. The third £1 billion is there for unpredicted events, and the credit crunch, now nine months in duration, is certainly an unpredicted event. That is those three amounts of money, and there is a gateway to each of those three amounts of money which is harder and harder to get through.

  Mr Stephens: If I may just add the point that, of course, as well as bearing down and ensuring that there is minimal use of contingency wherever possible, as the NAO Report makes clear, there are circumstances, particularly on a time-limited project of this sort, where early use of the contingency is actually the value-for-money option to ensure that costs and risks do not pile up at the end of the project, where contractors would have us over a barrel. It is important to understand that early use of the contingency may well be good management and good value for money. [2]

  Q28  Phil Wilson: One final question. We have just talked about unforeseen circumstances in the future, for example. You have mentioned property values, et cetera. If there is a downturn in property values, how do you expect to get the £1.8 billion from the sale of land and property after the Games?

  Mr Stephens: That was an estimate by the GLA to inform the work that they did on the memorandum of understanding. I should be clear that that estimate is not built into the Olympic budget. It is not part of the budget. It is not part of the Lottery projections either, going forward. The work done last year was to ensure that there was in effect a profit-sharing agreement between the Mayor and the Government to ensure that future profits from the sale of the land after 2012 were shared with the Lottery, with the aim of enabling repayment of the extra £675 million.

  Q29  Phil Wilson: So that figure could change. You continue to review that figure, do you?

  Mr Stephens: It has not been reviewed. It was done originally by the GLA. It is based, of course, on long-term property values over a period of 20 years or so, so it has not been reviewed recently.

  Q30  Mr Bacon: I would like to ask about the village, and just to start with, Mr Stephens, I would like to clarify a couple of things. The Report says the village will cost over £1 billion. How much more than £1 billion? What is a rough estimate? Is it £1.1 billion or is it £1.9 billion?

  Mr Higgins: I think at this stage £1 billion is probably a reasonable estimate of the total cost.

  Mr Stephens: I am sorry. It is really important that we should be absolutely clear. This is not cost to the public purse.

  Q31  Mr Bacon: I am aware of that and that was my next question. I just want to be clear that the £1 billion, or £1.2 billion or whatever it is, sits entirely outside the £9.325 billion headline budget. Is that correct at the moment? You have a budget. The Report says the overall cost is likely to be, the headline budget which you will deliver this thing within, is £9.325 billion, and the £1 billion for the Olympic Village sits entirely outside of that because it is private sector funding. Is that correct?

  Mr Higgins: No, that is not correct, because the budget that we have, the ODA, which is the £6 billion, includes some money for contribution in Stratford, which can be recovered against future land sales. So some of it is a component of that. You will see that in that figure there which includes the IBC and the village. Then you have the second £1 billion, which is the programme contingency, which covers abnormal inflation or ground condition, and the overall funders' contingency, and that covers unpredicted events such as the credit crunch. So if, as our Chairman noted the other week in a statement to the media, there may well be the need to draw on some portion of that second £1 billion to fund the village, that was always set aside for unpredicted events.

  Q32  Mr Bacon: So the bit that sits outside the £9.325 billion is the private sector funding?

  Mr Higgins: That is correct. That is right.

  Q33  Mr Bacon: Good. The contingency is £2.7 billion?

  Mr Higgins: It is potentially just over £2 billion for the ODA.

  Q34  Mr Bacon: It is £2 billion? I thought it was £2.7 billion.

  Mr Higgins: No. The announcement in March 2007 said there was an unallocated contingency of £2 billion for the ODA, and the budget announcement in March 2007 additionally allocated £0.5 billion to the ODA programme. That made £6 billion baseline budget for the ODA, plus up to £2 billion contingency, just under £1 billion for other costs and provisions, and £238 million for security contingency. [3]

  Q35  Mr Bacon: How much of the contingency has been spent in total so far? I have read £500 million but what is the most up-to-date figure?

  Mr Higgins: None of the £2 billion, either the programme or the funders' contingency, has been spent or committed or asked for.

  Q36  Mr Bacon: So there is still £2 billion sitting there?

  Mr Higgins: Correct.

  Q37  Mr Bacon: If you were to add that to get your £9.325 billion, the £2 billion would comprise part of that sum?

  Mr Higgins: Correct.

  Q38  Mr Bacon: In other words, what I am really getting at is, were you to have to—and I am not expecting you to have to—to pay for the Olympic Village entirely out of the contingency, you could?

  Mr Higgins: You would never do that because—

  Q39  Mr Bacon: I did not say that you would. In fact, I actually said I did not expect you would. What I am really asking is, if you had to, the contingency is so humongously large that you could. There is enough money there because it is so big. I am really asking you to confirm that £2 billion is larger than £1 billion, Mr Higgins.

  Mr Higgins: Correct, but the second £1 billion is used—



2   Note by Witness: This is set out in the NAO Report in Section 9 of Appendix 4. Back

3   Note by Witness: A contingency of 2.7bn was set aside in the March 07 statement. £500m was provisionally allocated in that statement to the ODA to meet known cost pressures and is now incorporated in the ODA's £6.1bn baseline budget. In addition, £238m was set aside as contingency for wider security and policing and is therefore not available to the ODA. This leaves £2bn contingency potentially available to the ODA above its baseline budget of £6.1bn. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 24 July 2008