Select Committee on Transport Minutes of Evidence


Examination of Witnesses (Questions 120-139)

SIR IAN MCALLISTER, MR IAIN COUCHER, MR SIMON KIRBY AND MR THOMAS M MCCARTHY

23 JANUARY 2008

  Q120  (23.01.08) Clive Efford: Can I clarify this? When were Virgin first contacted by anyone to inform them that there was a likelihood of a delay?

  Mr Coucher: First of all, Virgin and Network Rail and the train operators share an integrated control centre in Birmingham, so they are constantly aware of what is going on because they get exactly the same information for running trains. They are in the same office. The first time that we notified the train operators to create contingency plans for a possible overrun was after the conference call on Sunday, 30th December at 12 noon.

  Q121  (23.01.08) Clive Efford: So they would not have been aware of Mr Kirby's meeting on 27th?

  Mr Coucher: No, because at that point in time we genuinely believed that we could still complete the work in time for the overrun. The first thing we did when we realised that there may be an overrun was to speak to Virgin and London Midland to advise them to put in place contingency plans for the possibility of an overrun.

  Q122  (23.01.08) Clive Efford: At any time prior to the work starting, to the blockade starting, or whilst the work was going on prior to 30th, did Virgin raise any concerns about the possibility of delay?

  Mr Coucher: There were constant project meetings. I met with Tony Collins and the Virgin team the week before the start of the work when we were talking about the possibility of extra days. There was a constant dialogue between Network Rail and—

  Q123  (23.01.08) Clive Efford: I think the answer is yes or no? Did they raise any concerns about the possibility of delay?

  Mr Coucher: Yes.

  Q124  (23.01.08) Clive Efford: Prior to 30 December?

  Mr Coucher: Before we even started the work, they wanted to be assured that we could get in there and get out and do the work, and that is the normal standard. We always take all of our customers through the work we are going to be doing so that they are aware of what we are doing.

  Q125  (23.01.08) Clive Efford: So there were nothing other than the normal concerns for a train operating company in this particular set of projects and they did not express specific concerns to say that you will never get this work done on time?

  Mr Coucher: No. There were no new circumstances. Of course whenever we do a piece of work like this there are always risks that we may not complete the work on time. We cannot afford the luxury of padding our possession simply to protect ourselves from an overrun. We knew that this was tight but we also knew that if we did not do this work over the Christmas period we would not deliver the December 2008 timetable upgrade. If we did not proceed, that was the rest of the work programme for the rest of the year.

  Q126  (23.01.08) Clive Efford: Sir Ian, you seem a bit irrelevant in this. What are your role and responsibilities?

  Sir Ian McAllister: There is a complete separation of responsibilities between the non-executive Chairman and the executive. The executive are responsible for operating the company and I am responsible for managing the board and reporting on our performance to our members. The board holds the executive management of the company to account.

  Q127  (23.01.08) Clive Efford: What is your role in all this?

  Sir Ian McAllister: I have no operational role whatsoever.

  Q128  (23.01.08) Clive Efford: In terms of your appearance before this committee, what have you got to say to us about the situation that occurred over the New Year and Christmas?

  Sir Ian McAllister: I think the situation was a very difficult one. It should not have happened. I expected and I was assured and I accept that the necessary mitigation measures were in place well before the blockade took place. It was in fact a discussion that we held with the board in December. We were not expecting an overrun. When the overrun occurred, then it is the operating responsibility to sort it out as quickly as possible.

  Q129  (23.01.08) Clive Efford: When did your phone first ring in your office at home?

  Sir Ian McAllister: My phone first started to ring on 31 December.

  Q130  (23.01.08) Clive Efford: When you were referring to the situation changing hourly, in your answers to the Chairman earlier on, what were you referring to?

  Sir Ian McAllister: I was referring to the changing situation with regard to the likelihood of a recovery taking place. In the initial stages, the recovery was not forecast to be three days; it was forecast that there would perhaps be a seven to eight hours overrun. That was bad in itself but the situation developed as the time went on.

  Q131  (23.01.08) Clive Efford: We have a situation here where Network Rail potentially is exposed to quite a substantial fine for what has gone on. Is that right?

  Sir Ian McAllister: Yes.

  Q132  (23.01.08) Clive Efford: Where is your responsibility in that and do you feel that you have been well served in the information that has been provided to you about the ongoing situation at the time?

  Sir Ian McAllister: The situation was changing very, very rapidly indeed. As I said earlier, the principal objectives we had were, first of all, to get the problem sorted out as quickly as possible. Iain and I discussed it. He took on that responsibility and Simon started to get additional resources into the Rugby area. The second part of the issue was to ensure that the information provided to passengers was as comprehensive and as accurate as it could be. That was why Robin Gisby was doing that because he was hard-wired into Simon and therefore knew exactly what the situation was that was up to date. These are very fast-moving situations as they develop. As I mentioned earlier, I was first advised of the Liverpool Street issue on the morning that Liverpool Street should have returned to work and in the same conversation Robin advised me that the restoration of the lines would start from around, if I recall, noon to 2 o'clock that afternoon as the InterCity trains were coming into Liverpool Street and the whole station would be back in operation for the evening peak. So it was a very quick situation.

  Q133  (23.01.08) Clive Efford: Everything was fast-moving but the trains! On the inquiry into what has gone on there are gaps in what is in Network Rail's evidence to us. They seem to have found conclusions about the supply of engineers and the fact that you need to have a bank of engineers available, particularly at public holidays, but there are not any conclusions. We are a month on. You are a multi-million pound operation. You are one of the biggest public organisations—you are certainly one of the biggest in transport—and yet a month on you have not come to any conclusions. Have you been sleeping on the job? I am asking Sir Ian because I think this is a responsibly of the board of Network Rail.

  Sir Ian McAllister: The board has asked for a full report on what has happened. That report will be provided by the executive team.

  Q134  (23.01.08) Clive Efford: Do you think it is timely? Do you think you have been working—

  Sir Ian McAllister: I think they are going as fast as they possibly can. As Iain was saying, we discussed this at length at the board meeting last week but what we had was a preliminary report rather than a complete report. It does take time to get to the bottom of these issues. You have suggested that certain payments were being made by contractors. That will have to be investigated. These things do take time.

  Q135  (23.01.08) Mr Martlew: Can I take you back to the board meeting in December, Sir Ian? The plans for Rugby, the plans for Liverpool Street and all the other plans for the work over the bank holiday were presented to the board, were they not?

  Sir Ian McAllister: No, they were not. The issue there was that at the time the company had asked for an additional day to do the work at Rugby. Virgin had objected to that and had applied to the Office of Rail Regulation for a ruling on whether or not that extra day should be given. The Office of Rail Regulation agreed that that day should be given. The board were advised of all the necessary details supporting that and at the same time the executive team have all these major reviews that take place to determine whether there is a go/no go decision. Ian sought assurances from the various companies that the blockades would take place and the work would be delivered.

  Q136  (23.01.08) Mr Martlew: At any point was the board told of all the works that were going to go on over this period?

  Sir Ian McAllister: The board was aware of all of those, but the board does not get a regular schedule of every single possession that is taking place because there are about 100,000 possessions a year. What the board is looking for is assurance on certain issues. At a December meeting, or rather shortly after a December meeting, I asked for a paper to be presented to the January board that was going to look at the whole of the possessions on the West Coast Main Line throughout the whole of 2008 and what the appropriate risks were to the delivery of the December 2008 timetable. That paper was overtaken by events over Christmas.

  Q137  (23.01.08) Mr Martlew: I am sorry, Sir Ian, I have probably not explained myself very well. It is becoming apparent that Network Rail had overstretched itself throughout the rail network over this period. Did your board sanction that work at any point?

  Mr Coucher: Can I just add—

  Q138  (23.01.08) Chairman: No, I think the Chairman was being asked. Mr Coucher, we would be delighted to talk to you in a moment.

  Sir Ian McAllister: The answer to the question is: no, the board did not go through every single possession and review the work.

  Q139  (23.01.08) Chairman: You did not think it was surprising that you were only told four hours before the services were resumed? You told us that you were given the information then.

  Ian McAllister: That was Liverpool Street. The information about the overrun, as I recall, only occurred around 2 o'clock in the morning of that day. I was called first thing in the morning and told that there was going to be an overrun. It was very late-running information.

  Chairman: A lot of it was late-running, yes.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 21 July 2008