Select Committee on Transport Written Evidence


Memorandum from Kelvin Hopkins MP (FT 42)

EURORAIL FREIGHT ROUTE (EFR)

  1.  We are pleased to have an opportunity to make this submission to the Transport Select Committee and to explain our proposals for the Eurorail Freight Route (EFR), a scheme which we believe will make a very substantial contribution to rail freight in Britain and which we consider will be significant for the country's long term economic success. The essence of the EFR scheme is the construction of a rail freight line from the Channel Tunnel to Glasgow, linking the major economic and population centres of Britain and built to a large gauge capable of transporting full sized (9ft 6ins) containers, (and ultimately double-stacked containers), as well as full sized lorry trailers between inter-modal terminals in Britain and continental Europe.

  2.  The scheme has been conceived and is being promoted by a team comprising the following:

Andy Berry—railway engineer and consultant with special expertise in signalling.

Tim Brown—railway engineer and consultant with 30 years experience in permanent way engineering.

Ken Russell—Director of Russell Transport, one of Scotland's largest freight haulage companies.

Kelvin Hopkins MP.

We have received much help and advice from others, including Railway Consultant Richard Tilden-Smith.

  3.  Our submission is developed in more detail below but this paper is still merely a summary text intended for ease of use by the Committee. More details can be provided as required and our team would be pleased to present oral evidence to the Committee if this was considered helpful.

  4.  We have made a number of presentations of our scheme to a wide range of interested parties. These have included Rail Freight Group (on five occasions), The Association of Railway Civil Engineers, Department for Transport officials, the Chief Executive of Network Rail, the President of the Institution of Civil Engineers, the Northwest RDA and SEEDA and others. The scheme was also presented to the House of Commons in an Adjournment Debate on 19 February 2007.

  5.  Beyond that we have made written representations and corresponded with many others, and we have on occasion informed the Chair of the Select Committee in writing of our ongoing representations. Our communications have included correspondence with Lord Neil Kinnock, former European Transport Commissioner, who has responded supportively, the Mayor of London, all of the RDAs on the line of route, the Freight Transport Association, a House of Lords rail freight inquiry chaired by Lord Woolmer and Sir Rod Eddington. We have also had private meetings with a range of experts, especially from the railway industry. The responses to our representations have been positive. Our representations are continuing and an ongoing series of meetings is planned.

  6.  What follows is a summary of our case for the construction of the Eurorail Freight Route.

THE NEED FOR A NEW FREIGHT ROUTE

  7.  Britain's roads and ports are suffering from considerable and increasing congestion. Estimates put the total cost to the economy of congestion at £20 billion a year, (FTA Estimate based on a previous OECD exercise), an enormous sum by any standards. Rail freight volumes have been growing but so too has passenger traffic, and in spite of increased levels of investment rail route capacity is increasingly under stress. Existing track routes must be used to the maximum, with modern signalling and higher operating speeds, but the reality is that existing routes will not cope with future growth.

  8.  Nor is it sensible to try to increase passenger and freight traffic on the same routes. Passengers and freight do not mix easily, with different operating speeds among other things, and there is therefore a great need both for additional track routes and for segregating freight and passenger traffic wherever possible. The Eurorail Freight Route will make possible a step change on both fronts. Statistical assessments of freight needs undertaken by MDS Transmodal show that there is a very substantial need for additional rail freight capacity north-south along the backbone of Britain. The EFR precisely matches that need.

THE EURORAIL FREIGHT ROUTE

  9.  As stated in the introduction to this paper, the essence of the EFR scheme is the construction of a railway line from the Channel Tunnel to Glasgow, linking Britain's major population centres and economic regions. The key to the success of the scheme and essential to it is that it would be built to a gauge capable of carrying full -sized (9ft 6ins) containers on standard wagons and would ultimately be capable of accommodating double-stacked 9ft 6ins containers on its core route all way to and through the Channel Tunnel. Another essential feature of the scheme is that it would be capable of transporting road trailers on trains both between terminals in Britain and between Britain and the Continent of Europe. The trailers would be delivered at both ends of their rail journey by short distance road haulage.

  10.  Our preliminary estimates suggest that the route would accommodate more than five million lorry journeys a year, operating effectively as a rolling motorway. It would thus provide for a large modal shift of freight to rail both within Britain and between Britain and the Continent. The EFR would also take freight traffic off the East Coast and West Coast Main lines, freeing up those routes for faster and more frequent passenger trains. If this were done, further and relatively modest investment in these two existing main rail routes would provide for 140mph trains on the East Coast Mainline and 135mph trains on the West Coast Mainline with the possibility of non-stop services at these speeds between London and Scotland. The East Coast Mainline in particular simply requires quadrupling of the track with a new viaduct to the north of Welwyn and some passing loops further north, together with signalling upgrades to make 140 mph non-stop working passenger services between London and Scotland possible. Indeed, on a test run in 1992 a train travelled from Kings Cross to Edinburgh with a two minute stop at Newcastle, in three and a half hours.

A DETAILED ROUTE FOR EFR

  11.  The EFR team has developed a detailed route plan making use of old track bed and under-utilised existing railway lines. The whole route would require only some fourteen and a half miles of new track route, 10 miles of which would be in tunnels, with a four mile link across open farmland in the Midlands. The chosen route would thus present minimal planning difficulties and would be very economical to build.

  12.  The EFR would be constructed in phases so it could begin to take traffic through the Channel Tunnel very soon. The first phase suggested would be a terminal on the North Thames linked directly to CTRL and using the CTRL line for the immediate future. CTRL has indeed been built to sufficient gauge to cope with full sized containers (and ultimately double-stacked containers) as well as lorry trailers. This would be a temporary arrangement until the EFR route under and to the south of the Thames is completed at a later stage.

  13.  The next phase of the route would include the existing Barking and Gospel Oak route round the east and north of London to join a new tunnel through Hampstead linking through to the Midland freight lines at West Hampstead. From there the route would branch off at Cricklewood to link up with the Chiltern lines where track would be reinstated. Another terminal would be constructed to the north west of London close to the M25, M4, M40 and M3 capable of taking lorry traffic from the South and West as well as the Midlands and North.

  14.  The route would then travel northwards on reinstated track on the old Great Central track bed to a terminal in the East Midlands and a branch linked to another terminal in Birmingham serving the West Midlands. Continuing northwards the route would link into the Midlands freight lines past Leicester and track northwards again to South Yorkshire to another terminal at Tinsley, between Sheffield and Rotherham, an existing but under-utilised freight terminal.

  15.  The line would then pass through the Pennines by way of the currently disused Woodhead Tunnel to a South Lancashire terminal near the M6 and M62 motorways. This would serve the North West and the major cities of South Lancashire. The line would then snake northwards to link with the Settle Carlisle route and on through Scotland to Glasgow. A link to Newcastle serving the North East would be built and additional links to other areas including the South West would be added.

  16.  The use of the CTRL route would be a temporary arrangement until the EFR is completed with a new tunnel under the Thames to the Medway Valley route and then on to the Channel Tunnel. Maps accompanying this paper illustrate the precise route[71] and this can be explained mile by mile as required. We must emphasise that our route has been very precisely researched and designed. It has also been presented to senior engineering figures from the railway industry, each of whom has confirmed that the route is precisely right and would be easy to construct. Standard operating speeds would range up to 100 mph.

CONSTRUCTION COSTS

  17.  Using the Channel Tunnel Rail Link costs as a model, our first estimate of costs for constructing the EFR line was between £3 and £4 billion. We have therefore used a working figure of £4.5 billion which is on the generous side. Indeed, one expert from the railway construction sector has suggested to us that he could construct the line for under £3 billion. We can provide a breakdown of costs as required.

  18.  The main reason why costs are so modest is that our team has gone to great lengths to avoid unnecessary expense in the choice of route. The former Central Railway proposal, which was significantly different in concept to the EFR, involved among other things a considerable length of new route circling London to the west, as well as a route through the centre of Manchester. We considered both of these to be unnecessary and both technically and politically difficult as well as expensive. EFR also links right through to Scotland which the Central Railway proposal did not. The EFR presents little technical or political difficulty and this has been confirmed in discussions with a number of experts. EFR should, we believe, become an integral part of Network Rail.

THE CHANNEL TUNNEL AND THE EFR

  19.  The Channel Tunnel was a bold and important advance linking Britain's railways with those of the Continent of Europe. However, since it opened it has been in almost continuous financial crisis and can only become financially viable with vastly increased traffic. Even with CTRL, the number of passenger trains through the Tunnel will always comprise only a very small proportion of its potential capacity. Indeed, with good signalling and timetable management, the Tunnel can comfortably accommodate 150 trains a day in each direction additional to Eurostar services. (Several times more than that number of trains could be accommodated each day with signalling upgrades.) 150 trains with 40 units (lorry loads) on each train would amount to 6,000 lorry journeys each way every day, potentially over four million lorry units a year. Even a fraction of that quantity would transform the economics of the Channel Tunnel and avoid the need for continued subsidies to the Tunnel paid in effect by taxpayers in Britain and France. The difficulty in achieving these levels of freight traffic through the Tunnel is simply that the rail network on the British side of the Channel is incapable of delivering the trains to and from the Tunnel. The track capacity is not there and the gauge required wholly absent. The EFR overcomes that difficulty.

SUPERMARKETS AND RETAILERS

  20.  There would also be considerable scope for domestic freight traffic on the EFR route. A group of supermarkets and large retailers are currently exploring the potential for transferring large quantities of their road borne services and traffic on to rail, should the capacity be available to make this possible. This group of nine such companies are discussing the possibility of some ten thousand lorry journeys a week being transferred to rail within Britain and there are other major supermarkets and retailers not in this group of nine who are also planning to seek similar modal shifts to rail. The EFR route would be ideally placed to accommodate much and perhaps most of their traffic. Without EFR, modal shift to rail of such traffic would inevitably be constrained by lack of track capacity.

  21.  These considerations have arisen because the supermarkets and other retailers wish to improve their green footprint and have been prompted partly by government request. The Department for Transport's own figures point out that CO2 emissions per ton mile for road freight are up to 12 times higher than that for rail freight. Transferring millions of units of road freight on to rail will therefore make a very large contribution to reducing CO2 emissions.

CONTINENTAL RAIL FREIGHT DEVELOPMENT

  22.  A large scale rail freight network is being developed on the Continent of Europe with enormous investments already under way. Among other things, two tunnels some 35 miles long in each case and dedicated to freight traffic are being built through the Alps from Switzerland to Italy and through the Brenner Pass in Austria. The 100 mile freight dedicated Beteuweroute in Holland has recently been built linking Rotterdam with the Ruhr with tunnels built to accommodate double stacked containers in the future.

  23.  These developments have been driven in part by the NEW OPERA initiative and the Trans-European networks concept. Lord Kinnock in his capacity as European Transport Commissioner personally took the initiative in promoting the development of a rail freight network across Europe and that is now moving on apace.

  24.  Britain is geographically peripheral to the continent of Europe and cannot afford to be left out of these major Europe-wide rail developments. Britain's existing rail network is incapable of taking the volumes of traffic required and most of the UK network is in any case incapable of taking full size container traffic and road trailers on trains. The Eurorail Freight Route would provide a major and vital artery for Britain's economy as well as making possible a step change modal shift of freight from road to rail.

SAVINGS TO THE TREASURY AND THE ECONOMY

  25.  There would be a number of indirect financial and economic benefits deriving from the EFR scheme. First of all, a significant shift of road traffic on to rail would have a proportionate effect in reducing road damage caused by lorries. It is the heavy axle weights of lorries which cause road damage and thus the need for road repairs with coned-off motorways and which in turn create congestion and associated costs. Both congestion costs and motorway repair costs would therefore be reduced. Heavy freight also has an impact on rail passenger routes, so taking freight off the East Coast and West Coast Main lines would among other things reduce rail maintenance and repair costs on those routes.

  26.  The road haulage industry would also benefit by guaranteeing delivery times on a dedicated and unrestricted rail freight network between Britain and the Continent and within Britain itself. Drivers' hours regulations would be less burdensome because many lorry journeys would simply be between points of origin and rail terminals and between rail terminals and final destinations, relatively short distances. There is currently a national shortage of road haulage drivers which the EFR would help to alleviate. It has to be emphasised however that EFR would provide a service to private hauliers and not be in competition with them. It would make a reality of an integrated freight transport industry.

CONCLUDING COMMENT

  27.  This is a brief sketch of the EFR proposals and we would be very pleased to have an opportunity to make an oral presentation to the committee. We have a relatively short power point presentation which might be helpful. We are continuing to discuss our scheme with the widest possible range of interests and experts and have been greatly encouraged by general expressions of support.

  28.  We believe that the EFR scheme would make a major and vital contribution to Britain's transport infrastructure. For a 400 mile long railway line at a cost around half that of the West Coast Main Line modernisation, half that of CTRL and a quarter of the expected costs of Crossrail, the EFR would represent great value for money. We are confident that the EFR would pay for itself without the need for ongoing subsidy.

  29.  We hope that our scheme for a Eurorail Freight Route will be of interest to the Select Committee and would be pleased to address any questions or comments members may have.

Kelvin Hopkins MP

For and on behalf of: Andy Berry, Tim Brown, Ken Russell

October 2007






71   Not printed. Back


 