Select Committee on Transport Written Evidence


Supplementary memorandum from Department for Transport (DAR 01E)

SPRING SUPPLEMENTARY ESTIMATES 2007-08

  Thank you for your letter of 31 March with questions on the Department's Spring Supplementary Estimates. Taking the order of your questions, answers are:

1.   The Supplementary Estimate allocates a total of £121 million of additional resources to Crossrail. The Committee would like to know why the Department did not include this significant expenditure in the Main Estimate or Winter Supplementary Estimate, since the Crossrail project has been underway for some time?

  The expenditure was not included in the Winter Supplementary Estimate because the 2004 Spending Review Settlement made no specific provision for the funding of Crossrail development costs in 2007-08. Decisions on funding therefore had to be taken in year and it was agreed with HM Treasury to review the funding position before the Spring Supplementary to determine whether a claim on the Reserve would be required or whether the costs could be funded from headroom in other programmes and/or End Year Flexibility.

2.   The Department has used £150 million of EYF for capital grants to the Greater London Authority (GLA) in respect of Metronet, in order to provide Transport for London with short-term flexibility while the costs associated with Metronet's administration remain uncertain. Please can you explain what use TfL has made of this additional flexibility, and whether the Department made any provisions to recover the grant if it was not required?

  The provision of this grant has allowed Transport for London to manage the short term impact of Metronet's administration on its finances at the same time as continuing to maintain day to day operations. The Department has no plans to recover the grant.

3.   The Supplementary Estimate includes significant additional resource provision of around £32 million for the Shared Services Project (£17 million has been added to the central administration subhead and the DVLA's capital grant-in-aid allocation has been increased by £15 million). Please could you explain why the £32 million of resource requested here wasn't anticipated at the time of the Main Estimate, given that the DVLA/DSA phase of the project went live in April 2007? Will this additional resource have any impact on the expected total cost of £113 million, as mentioned in the Committee's evidence session on 30 January?

  No provision for the Shared Services Project was included in the Department's Spending Review 2004 settlement. This meant the shared services budget requirement had to be funded from in year savings and End Year Flexibility which could not be included in Main Estimates. The provision sought in the Spring Supplementary was included in the total cost of £113m reported to the Committee in January 2008.

4.   £60 million of capital grants to local authorities have been transferred to non-voted, primarily to fund the Integrated Transport Block (£35 million) and UK Trust Ports (£21 million). This reduction represents a 5.5% cut in the Department's resource provision for local authorities by way of capital grants. Please can you outline the Department's assessment of what the impact on local authorities will be from this reduction and what benefits are expected to arise from the Integrated Transport Block and UK Trust Ports projects?

  The transfer of funds out of the LA Major Schemes budget followed our forecast of an underspend in that area, rather than a policy decision to cut spending and move resources elsewhere. The emerging underspend reflected a number of factors, including in particular delays in local authorities submitting Business Cases to the Department and slippages in construction timetables (eg due to the relatively bad weather during 2007-08).

  The Integrated Transport Block is capital funding for local authorities outside London to improve their highways and transport infrastructure.

  The types of project supported (and the proportion of local authorities' total investment on them during the first local transport plan period) are:

    —    Public transport 26% including:

    —  bus or HOV lanes/Quality bus corridors (8%),

    —  bus Improvement schemes (7%),

    —  interchange schemes (6%),

    —  park and Ride Schemes (2%), and

    —  light Rail and Guided Busway schemes (2%).

    —    Safety Schemes (17%).

    —    Walking, cycling and road crossing schemes (15%):

    —  walking schemes (6%),

    —  cycling schemes (6%), and

    —  road crossing schemes (3%).

    —    Traffic management schemes (15%).

    —    Local road improvement schemes (including rural bypasses) (9%).

    —    Travel plan schemes (1%).

    —    Others (17%) (including composite schemes).

  These projects have contributed to many local outcomes—including reductions in deaths and injuries on the road network, more patronage on bus corridors, increased satisfaction with local bus services and more travel choices.

  The £35 million transfer of funding into the integrated transport block enabled the Department to provide total capital allocations of £571m for 2007-08, 4.4% or £24 million higher than the total for 2006-07. It avoided a reduction in the integrated transport block. It enabled the Department to target additional funding towards areas assessed as having delivered well before and as having produced strong forward plans.

  The £21m requirement for Trust Ports is for borrowing by six Trust Ports in England and Wales (Tyne, Harwich, Shoreham, Poole, Milford Haven and Dover) which are classified as Public Corporations. The amount of borrowing is determined by the Trust Ports themselves - independently of the Department—and represents the sum of what each considers necessary to help best meet their priorities and objectives.

5.   The Estimate Memorandum details a number of movements that result in £182 million of additional non-voted funding for London and Continental Railways. Please can you explain why this expenditure wasn't anticipated prior to the SSE and give a breakdown of what it relates to, along with a timescale for it utilisation?

  London and Continental Railways (LCR) was reclassified by the ONS as a non-self-financing public corporation in 2006. Consequently, LCR operating losses, together with any capital investment requirements and associated cost of capital charges, are reflected in Departmental budgets.

  No provision had been made in the 2004 Spending Review Settlement for the budgetary impacts of this reclassification. HM Treasury partially adjusted the Department's budgets at the time of reclassification in 2006, however the Department was required to meet the remaining impact by using End Year Flexibility and by utilising emerging headroom in other programmes. Therefore, it was prudent to wait until the position on LCR's operating losses and capital investment requirements for 2007-08 was more certain before drawing down EYF.

  The £182 million of non-voted funding for LCR to be utilised in 2007-08 breaks down as follows:
Operating Losses:Resource DEL (near cash) £73 million
Cost of capital charges:Resource DEL (non cash) £ 6 million
Capital Investment:Capital DEL £103 million
6.   In Part II of the SSE, the resource to cash reconciliation, the Department outlines a movement in provisions for liabilities and charges of £104 million. This movement does not appear to be explained in the Estimate Memorandum. Treasury guidance requires departments to provide information on the stock of the department's provisions, as well as explaining the changes (HM Treasury, PES Paper (2004) 14 Annex D, paragraph 9). Please can you explain the reason for this movement in provisions?


  The total movement includes a reduction of £143 million for the Highways Agency's estimate of provisions for the year, largely because of adjustments to provision in relation to new EU tunnel safety regulations. The provisions were actually taken up in 2006-07, but this was after the 2007-08 budget had been set on the assumption that utilisation of the provision would be required in 2007-08.

  In addition there was a further reduction of £30m from a write back of the provision taken in March 2006 for disputed assets and dilapidation costs arising from the ending of the South Eastern Trains franchise.

  These reductions were partially offset by an increase of £70m in relation to Rail pension schemes accounted for under FRS17, reflecting the forecast movements in the scheme's assets and liabilities.

7.   In Part II of the SSE, the resource to cash reconciliation, the Department shows a movement in creditors of £174 million. Please can you explain the reason for this movement in creditors?

  The Spring Supplementary Estimate presented an opportunity for the Department to adjust its net cash requirement to bring it in line with its latest cash forecasts from the central Department and its Agencies. During the last quarter of the year a more detailed breakdown of cash forecast (payment and receipts) was available compared to previous period estimates submitted in the Winter Supplementary Estimate. An adjustment was necessary to increase creditors by £174m related to Deemed Supply.

*  Numbers and percentages in the above answers are rounded.

April 2008





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 13 June 2008