Select Committee on Transport Second Report


2  METRONET'S TIED SUPPLY CHAIN

13. A significant part of Metronet's obligations under its PPP Agreements was intended to be delivered through contracts with its shareholders with some 60% of its projected capital expenditure in the first 7½ year period to be awarded to its parent companies—Atkins, Balfour Beatty, Bombardier, EDF Energy, and Thames Water. Other than for rolling stock work, which was managed by Bombardier, this was organised through another company, Trans4m, which was in turn owned by the remaining four of the Metronet shareholders. This structure has been widely recognised as having contributed to the inefficiencies of Metronet, a conclusion which the Arbiter reached in 2006.[18] Metronet's former Chairman, Graham Pimlott, conceded that

    I think that there is little doubt that in the case of stations the contractual arrangements with the shareholders was a very negative factor from Metronet's point of view. Metronet had a contract with Trans4m, which was a contract that gave Metronet very little in the way of leverage over Trans4m. It had to pay money when bills were presented and it did not have the ability to withhold it, for example for performance failure.

14. Outside the stations modernisation programme, the problem also appears to have plagued Metronet's track replacement work, which was contracted solely to Balfour Beatty, and the Arbiter assumed during the Extraordinary Review that a notional Infraco operating in an efficient and economic manner would not have had Metronet's tied supply contract for track replacement.[19] The contract was in the process of being renegotiated by Metronet prior to administration. Conversely, Metronet's contract with Bombardier for rolling stock upgrades appears to have been working better. Mr Pimlott suggested this might have been because it was more "output-based", whereas the stations contract was more like a building contract.[20] In fact, the Arbiter was satisfied that it was, on the whole and following inefficiencies during the first two years of the PPP Agreement, being operated efficiently and economically, and that price increases were as a result of omissions from the bid.[21]

15. Metronet responded to concerns about the tied supply chain by beginning to award contracts for station upgrades outside the chain using competitive tendering.[22] However, in September 2007 the Arbiter reported that Metronet's issues with its supply chain had not been fully addressed prior to the Extraordinary Review and Metronet's subsequent administration.[23] He told us that "a well-managed company would have resolved those issues well before Metronet started addressing them."[24] Mr Pimlott agreed that

    the problem was known […] The Arbiter and London Underground and Metronet and the shareholders were over a period of time trying to do something about it but they did not get it done fast enough.[25]

16. However, his subsequent claim that he was threatened with litigation when he tried to reduce the amount of work going to the shareholding companies casts serious doubt on the suggestion that the shareholders were committed to doing anything about the problems caused by the tied supply chain.[26] We are not persuaded that Metronet's shareholders had any inclination to address the problem of the tied supply chain nor, as the intended beneficiaries of the system, did they have very much incentive to do so.

17. The Arbiter insists that it is possible to operate a successful tied supply chain, although he stressed the importance of a clear distinction between the roles of shareholder and supplier.[27] However, he was also of the opinion that some of the problems with the supply chain could have been anticipated.[28]

18. When the bids for the PPP contracts were being assessed, it should have been possible for the Government and London Underground, then under national control through London Regional Transport, to foresee that Metronet's proposed tied supply chain model, which guaranteed the lion's share of work to its parent companies, did not include the necessary safeguards. The fact that such a management structure was judged to be capable of efficient and economic delivery seems extraordinary now that Metronet has collapsed but the ultimate recipients of the money which was paid to the company have walked away with limited losses. The Government must not allow this blurring between the roles of shareholder and supplier in future bids to carry out work by the private sector. Bids where competitive tendering for sub-contracts is proposed are likely to ensure that the best price is obtained.


18   Office of the PPP Arbiter, Annual Metronet Report 2006,16 November 2006 Back

19   PPP Arbiter, Initial Thoughts, 21 September 2007 Back

20   Q 179 Back

21   PPP Arbiter, Initial Thoughts, 21 September 2007 Back

22   "Metronet awards first six station projects outside of its supply chain: further initiatives to accelerate programme", Metronet press release, 23 February 2007 Back

23   PPP Arbiter, Initial Thoughts, 21 September 2007 Back

24   Q 9 Back

25   Q 199 Back

26   Q 227 Back

27   Q 42 Back

28   Q 57 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008