Select Committee on Transport Written Evidence


Memorandum from Chris Bolt, the PPP Arbiter (PPP 01)

THE ROLE OF THE PPP ARBITER

  1.  The functions and duties of the PPP Arbiter were established by the Greater London Authority Act 1999 (GLA Act). The PPP Arbiter's role is principally to ensure that any differences between the PPP Parties about the price to be paid to the Infracos for carrying out obligations under the PPP Agreements can be resolved independently, with certainty and in a timely way.

  2.  Although the Arbiter can be asked for guidance or directions at any time, it was expected that he would exercise formal functions in three main circumstances:

    —  in giving an annual "definitive statement" on the performance of the two Metronet infracos;

    —  at the Periodic Review of the Agreements which takes place every 7½ years; and

    —  at an Extraordinary Review of the terms of a PPP Agreement if there were material changes in costs and revenues within a Review Period.

  3.  The PPP Agreements establish the concept of a "Notional Infraco"—an entity which has the same obligations as Infraco, which carries out its activities in an overall efficient and economic manner and in accordance with Good Industry Practice, and has certain other specified characteristics. A key part of the Arbiter's role is therefore to assess what constitutes Good Industry Practice and the level of performance and cost which would be efficient and economic.

  4.  Chris Bolt was appointed as the first Arbiter on 31 December 2002, and his appointment now runs to 30 December 2010. He is supported by a small permanent staff. As he is appointed as an individual, and is personally responsible for the exercise of his statutory functions, he has also appointed an Advisory Board to provide independent and expert challenge to his decisions and procedures. Although he is not required by statute to do so, he has published each year a Business Plan and the Annual Report and Accounts setting out the work programme of his Office and the resources used.[1]

ACTIVITIES TO DATE

  5.  The Arbiter's initial focus was on two main workstreams:

    —  developing clear and transparent procedures for handling references, which have been published—after consultation—as a "Procedural Framework for Use in the Giving of Directions and Guidance" together with a series of more detailed supporting documents relating to different types of reference; and

    —  initiating a programme, jointly with the PPP Parties, to develop a basis for assessing the key concepts of efficiency and economy and of Good Industry Practice; this has included developing a framework for benchmarking between the infracos, initial work on international benchmarking and specific studies on aspects of good practice in asset management, procurement etc.

  6.  The two Metronet Agreements provide for an annual reference to the Arbiter for guidance in the form of a definitive statement as to whether "Infraco has performed its activities in an overall efficient and economic manner and in accordance with Good Industry Practice" or not (the "annual Metronet Report"). It was expected that the first report would be prepared in 2005, covering the two year period from Transfer in April 2003. Preparing for this reference was an early priority for the Arbiter and his Office.

  7.  In the event, it was agreed by Metronet and London Underground not to seek this independent report from the Arbiter in 2005, and Metronet secured a waiver from their funders to permit this.[2] Although Metronet and London Underground agreed to undertake, with the Arbiter, some preparatory work for the 2006 report, which enabled some issues such as the presentation of variance analysis to be taken forward, a significant consequence of this decision was that the emerging overspend in Metronet was not fully analysed for a further 12 months.

  8.  Five references were made to the Arbiter for guidance in the year 2006-07:

    —  a reference from Tube Lines for guidance on the treatment of investment which straddles a Periodic Review;

    —  references from Metronet BCV and Metronet SSL for the 2006 annual report; and

    —  references from Metronet BCV and Metronet SSL for guidance on the treatment of investment at an Extraordinary Review.

  9.  These references were handled in accordance with the Procedural Framework. The final guidance in each case has been published.

  10.  Of particular significance was the annual Metronet Report 2006, published on 16 November 2006. This concluded that neither of the two Metronet infracos had performed its activities in an overall efficient and economic manner and in accordance with Good Industry Practice in the first three years of the contract. The report made some specific criticisms of the supply chain arrangements which Metronet put in place at Transfer, and of Metronet's governance. The Arbiter also expressed surprise at the lack of detailed information on important aspects of Metronet's activities.

  11.  The report also identified a significant overspend, at that stage estimated at about £750 million for the two infracos combined, for the first 7½ year Review Period. To the extent that an Extraordinary Review concluded that these additional costs were efficiently incurred, all but £100 million would be borne by London Underground (either through additional Infrastructure Service Charge (ISC) or through a reduction in obligations); costs inefficiently incurred would be borne by the relevant infraco.[3] Given this scale of overspend, the Arbiter considered that it was important to clarify the responsibility for cost overruns through an Extraordinary Review.

  12.  The Arbiter had discussed with Metronet the possibility of their making a reference for direction on Eligible Costs and ISC (essentially a determination of the increase in efficient and economic costs and revenues above the contractual baseline) alongside the 2006 annual report, but in the event Metronet did not make that reference.

  13.  Initially, Metronet considered that it was preferable to negotiate a settlement with London Underground, rather than use the contractual processes. Anticipating the possibility of an Extraordinary Review, Metronet made a further reference to the Arbiter for guidance on the treatment of seven specific investments at an Extraordinary Review on 14 November 2007, and the Arbiter's final guidance was published on 13 March 2007. Although London Underground and the Mayor were publicly urging Metronet to call an Extraordinary Review from February 2007, the Arbiter did not receive a reference until June 2007.

METRONET EXTRAORDINARY REVIEW

  14.  Metronet BCV made a reference to the Arbiter for an Extraordinary Review of its PPP Agreement on 28 June 2007. This sought three separate directions: on the form and structure of the Extraordinary Review, on Net Adverse Effects and the consequent increase in ISC for the full 7½ year Review Period, and on an interim increase in ISC ("Interim ISC") while the Extraordinary Review was being conducted.

  15.  Draft directions on Interim ISC, covering a 12 month period to 28 June 2008, were published on 16 July 2007. These directions allowed Metronet BCV only £121 million of the £551 million interim funding the company had sought. On 18 July, both Metronet BCV and Metronet SSL entered PPP Administration.

  16.  To allow the Administrators time to develop their plans for Metronet, and reflecting the availability of alternative interim funding, the Arbiter suspended on 30 July the previously announced timetable for the Extraordinary Review which covered the publication of final directions on Interim ISC and holding a post-reference meeting to establish the timetable for the full Review. However, he also said that he was continuing work on analysing submissions from Metronet BCV and London Underground.

  17.  The Administrators of Metronet have told the Arbiter that they do not currently envisage withdrawing the reference, and indeed are considering whether to make a reference for an Extraordinary Review of Metronet SSL's Agreement. Because the Metronet BCV reference remains on the table, the Arbiter is under a statutory obligation to give directions. On 21 September, he published his Initial Thoughts on both the level of efficient costs and revenues for Metronet BCV, and the potential implications for Metronet SSL, and on the form and structure of the whole Extraordinary Review. He has asked for representations by 12 October.

  18.  The Arbiter's current proposals in respect of Metronet BCV envisage draft directions on Net Adverse Effects being published on 12 November, with final directions on 14 December. Draft and final directions on the resulting changes in ISC will follow, with the process being completed in January 2008, unless additional time is required to assess the impact of changes in Infraco Obligations on affordability or practicability grounds.

THE PERIODIC REVIEW

  19.  The Arbiter is continuing his preparations for the first Periodic Review of the contracts, due to be completed in 2010. The current focus is on the format of cost and performance information to be provided, and the internal and external benchmarks which will assist in evaluation of infraco projections. The Arbiter's office now chairs the Joint Benchmarking Steering Group, and the Arbiter chairs regular meetings with Metronet, Tube Lines and London Underground to review overall progress.

  20.  The current programme for the Periodic Review envisages that the business plan currently being developed by each infraco will provide the basis for an initial assessment by London Underground of affordability in the second Review Period (2010-17/18) and by the Arbiter of efficiency and economy. The results will allow an updated business plan to be developed at the end of 2008 as the basis for detailed negotiations between infracos and London Underground, and any directions by the Arbiter, during 2009. New pricing and financing arrangements need to be in place by the start of the second Review Period (1 July 2010 for Tube Lines, 4 October 2010 for Metronet).

ISSUES RELEVANT TO THE CURRENT INQUIRY

  21.  Under the terms of the PPP Agreements, the infracos are incentivised to deliver improvements in three main output measures: capability (in terms of capacity and journey times); availability (performance of trains on the day); and ambience (of both stations and trains). They are also required to deliver a station improvement programme in line with dates specified in the Agreements. The infracos are under an obligation to demonstrate an efficient and economic whole-life cost approach to asset management, by reference to Good Industry Practice.

  22.  Since Transfer, performance of the Infracos on the availability measure (train performance "on the day") has generally been better than the level in the two years before Transfer, although the improvement has been different for different lines. Delivery of the stations programme has also varied between the infracos, with Tube Lines delivering on time, but Metronet delivering substantially later than the contractual dates. Tube Lines is also projecting costs in the first Review Period broadly in line with bid, in contrast to the overspend under the two Metronet Agreements.

  23.  Although the Arbiter has no role in establishing the obligations to be delivered under the PPP Agreements, or in monitoring and enforcing delivery of those obligations, his guidance and directions are central to delivery of value for money under those Agreements (as recognised by the National Audit Office in their report on the PPP).

  24.  The Arbiter identified in his guidance on investment which straddles a Periodic Review, issued in November 2006, some weaknesses in the PPP Agreements in giving adequate incentive to the infracos to innovate where this increased costs in the short term but brought longer term benefits. Recent events have also highlighted some areas where the PPP Agreements may not be fully effective in promoting value for money. These include the arrangements for updating and reviewing business plans, provisions relating to the triggering of an Extraordinary Review, and the provisions for handling delay in the delivery of obligations. There are also questions about the effectiveness of lenders in using their powers under the funding agreements to hold Metronet to account.

  25.  It also seems clear that there have been differences of understanding between Metronet and London Underground about the allocation of different risks under the contract. In particular, the cost consequences of increases in the scope of work required to deliver obligations are mostly borne by London Underground; only the (low) Materiality Threshold and the cost consequences of delivering inefficiently are borne by Metronet. Thus, even where sums were omitted from the original bid, or disputes about contractual requirements have been won by London Underground (such as whether Low Loss Conductor Rail for the Victoria Line was an original obligation or not), London Underground still has to bear the efficient increase in costs.

  26.  Quantification of risk will be particularly important in assessing the value for money of different options for the future structure of Metronet, in particular if this involves a comparison of public and private sector ownership models. Experience in developing the Public Sector Comparator (PSC) at the time of the original contract award may be particularly relevant. It should also be borne in mind that the PSC for SSL was assessed as being between £500-£1000 million more expensive than the Metronet bid for the first 7½ years.[4]

  27.  Uncertainties surrounding the future structure and ownership of Metronet (in both the short and longer term) make it particularly difficult to plan effectively for the Periodic Review, in particular given the expectation that comparisons between the three infracos would be a primary source of information for the Arbiter. However, the Arbiter remains of the view that the basic structure of the PPP Agreement remains sound, and that maintaining an output-based contract is important for delivering value for money in the longer term.



1   These are published on the Arbiter website, at http://www.ppparbiter.org.uk/output/page19.asp?DocTypeID=4. Back

2   Although the annual report is specifically referred to in the PPP Agreements, the reference is discretionary. However, Metronet's funding agreements make it mandatory that such a reference is made by 30 April in each year from 2005. Back

3   Changes in the efficient level of costs and revenues are referred to in the Agreements as Net Adverse Effects. Net Adverse Effects in excess of a Materiality Threshold are borne by London Underground. The Materiality Threshold is £50 million indexed in each Review Period for the Metronet infracos, and £200 million indexed for Tube Lines in the first Review Period and £50 million in subsequent Review Periods. Back

4   Present value over 7½ years. Source: Final Assessment Report, 2 February 2002, Table 20.1. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008