Select Committee on Transport Written Evidence


Memorandum from Tube Lines (PPP 04)

OVERVIEW

  Tube Lines' achievements, in the years since the PPP contracts commenced, show clear and demonstrable progress in the improvement of the underground network, reliable and consistent improvement in day to day performance, completion of upgrade projects on time and on budget, clear benefits for passengers and value for money for taxpayers whilst maintaining high standards of safety.

1.  About Tube Lines

  1.1  Tube Lines is the infrastructure and asset management company responsible for maintaining and upgrading the Jubilee, Northern and Piccadilly lines, under a 30 year partnership with London Underground, which commenced on 31 December 2002.

  1.2  Tube Lines is responsible for the following:


Asset
Actual
Percentage of total

Track
320 km
30%
Trains
255
42%
Stations
100
39%
Escalators
227
55%
Lifts
79
73%
OTHER
Employees
3,500
Passengers (per weekday)
1,941,000
39%


2.  Progress to date and benefits to passengers

  2.1  Tube Lines has delivered real benefits to passengers over the last five years.

  2.2  Availability, cited by the Committee during its previous inquiry as the most important factor for Tube travellers, has improved significantly over the last five years. Lost customer hours, the main measure of delay, has halved since transfer. On the Piccadilly line, delays have been cut by up to 70% and on the Jubilee line, the figure is 30%. Both are performing ahead of internal targets and ahead of the commitments we made to London Underground (LU). The Northern line remains our most complex set of assets and at transfer, was in a worse state than anticipated. Performance deteriorated over our first year, but we have more than recovered this, although it still falls short of the target we set ourselves. Through increased investment, we are tackling the problems of the Northern line. 80% of these are currently fleet-related but we are close to signing an amendment to the PFI contract we inherited with Alstom, the fleet maintainer, aimed at improving maintenance and performance.

  2.3  The PPP has brought about much greater monitoring and scrutiny of performance than was ever the case before transfer. However, it is clear that current performance levels are better than the period pre-transfer.

  2.4  All of our major capital investment projects have been completed on schedule, bringing significant benefits to passengers. Some projects have cost more than anticipated (see 2.6) but overall, we have been able to remain within our planned budget.

  2.5  In early 2006, we completed a major project to add an additional car to every Jubilee line train and introduce four new trains. This project, which increased passenger capacity on the line by 17%, was completed, ahead of budget, two days early.

  2.6  We have modernised or refurbished all 47 of the stations required to be upgraded to date under our contract and are halfway through our station modernisation programme. Each upgrade brings enhanced security and information for passengers and a cleaner, brighter environment: this is done through the installation of additional CCTV cameras and passenger help points, new indicator boards, upgraded facilities and a comprehensive redecoration. However, this programme has been significantly more complex and costly than anticipated at transfer, principally resulting from the interpretation of scope. We had to manage the balance between the ambitions of London Underground and the specification we had committed to deliver (see 5.4).

  2.7  We have refurbished 52 escalators to date. We have also replaced or refurbished over 90 km of track (out of 320 km), which allows passengers to experience a smoother ride, helped to reduce incidents of track failure by 44% and also reduced noise from the railway for residents living in the vicinity of the track. A programme of 10 km of track replacement and refurbishment carried out intensively over 40 weekends on the Northern line has resulted in a large body of work completed 2-3 years early. This programme has also resulted in a reduction in track and signal failures on the Northern line by approximately 15%.

  2.8  We have taken a number of initiatives to improve the travelling environment for passengers on the trains. We never knowingly put a train into service with graffiti on and we have made significant improvements to the cleaning regimes. Our ambience scores, the contractual figures used for measuring the quality of the travelling environment, have risen significantly since transfer and are ahead of internal targets and the LU benchmark.

  2.9  We completed an upgrade to Wembley Park in 2006, to expand the station in order to accommodate the demands of the new stadium. The upgrade was completed on time for the scheduled opening of the stadium in spring 2006, although the stadium itself opened a year late. Other achievements have been signalling work to support the Piccadilly line extension to Heathrow Terminal 5 and the installation of lifts at a number of stations to provide step free access. This additional work is currently valued at approximately £300 million.

  2.10  More significant improvements for passengers will come with the line upgrades, which will deliver further improvements to reliability, increased capacity and a reduction in journey times. Upgrades to all three lines are running on schedule; the Jubilee line will be completed in 2009, the Northern in 2011 and the Piccadilly in 2014. A new fleet of trains will also be introduced on the Piccadilly line in 2014.

  2.11  The Committee's previous inquiry expressed a concern that some work might have to be delayed until the second review period. Tube Lines' progress to date means that there will be no such delays.

3.  Innovation and change

  3.1  A key factor behind Tube Lines' success is the importance attached within the company to innovation, change and new ways of working.

  3.2  We have made significant investment in training and development. £10 million has been invested in a state-of-the-art training centre in Stratford to allow all of our training programmes to be provided under one roof. We have introduced a suite of leadership development programmes and other competency schemes for employees at all levels throughout the business. We have also enlarged the size of our graduate and apprentice schemes. All of this is underpinned by informal coaching and mentoring opportunities for employees. The aim of these initiatives is partly to ensure that we have the skills and competencies required in the business and can ensure that we are not adversely affected by skills shortages in the industry. Just as importantly, these initiatives are designed to provide motivation and encouragement to employees to come up with ideas themselves for innovations and changes. A number of the initiatives later in this section have been developed by employees on the frontline.

  3.3  We have also been innovative in our employment relations policies. We concluded the first ever two year pay deal on the Underground in 2004—previously there had only been one year deals—and reached a further two year deal in 2006. We have launched a profit share scheme from which all employees benefit and we have also put in place various schemes to recognise individual contributions made by employees.

  3.4  We have been able to monitor the positive effect which these changes have had on our employees through our biennial survey. The last one, carried out in 2005, showed increases in employee motivation of 13% and employee satisfaction of 19%, to levels above the UK norm. These levels of improvement in satisfaction and motivation are almost unprecedented within UK industry. The next survey is taking place in autumn 2007.

  3.5  By employing new methods of planning, innovative shift patterns and improved welfare facilities for site operatives, we have been able to reduce the time taken to reduce escalator refurbishments from 26 weeks to as little as eight weeks. This has a clear passenger benefit in that escalators are out of passenger service for less time.

  3.6  By applying best industry practice we have been able to make the process of station modernisations more efficient. Where before and at transfer, each upgrade could take over two years, we are now able to complete this type of work in as little as four months. This also has passenger benefits in that the amount of time they have to travel through a half-refurbished station is now reduced. In addition, we are now able to work on 15 stations at a time, whereas before, only two or three could be worked on at any one time. We have also reduced the cost of each upgrade by 40% since we began our programme. This improvement was critical as we needed to bring rigorous cost control to the work on stations where this had been lacking in the past.

  3.7  We have invested in a number of processes and equipment to make maintenance more efficient. We have, for example, introduced a new "Tubevac" machine, which is like a giant vacuum cleaning machine and is used to replace compacted ballast which causes trains to bump, increasing rail and wheel wear. The machine enables us to increase productivity by 300%. In the past, the same work was done by people shovelling ballast by hand; teams of 12 typically completed a third of the work which the machine can achieve each night. Another device which is being rolled out across the network is allowing our teams to get on site almost immediately after the current is turned off rather than having to wait for valuable minutes for clearance to access the track as in the past. This will mean that more work can be completed each night, during engineering hours. We believe this has the potential of saving tens of millions of pounds per annum.

  3.8  We have also taken a number of steps to put more emphasis on preventative maintenance rather than simply waiting for infrastructure to fail, as happened in the past. We have introduced a new "smart step" which can be used to gauge, in advance, when an escalator is in danger of breaking down. We have also introduced a new computerised enterprise system to record the history and geography of our assets, to make it easier to anticipate when a repair will be needed.

4.  Safety

  4.1  Safety is at the heart of Tube Lines' business and in everything we do, we seek to ensure the highest standards of safety for the travelling public. We operate under London Underground's safety case, which has been accepted by the Health and Safety Executive, and it is our policy to comply with not just the letter, but the spirit of all health and safety and railway legislation and codes of practice. All safety training is approved by London Underground and is consistent with the training provided to all others who work on the underground, regardless of their employer.

  4.2  Since transfer, we have improved our regime to detect potential incidents. This means that potential issues are identified at a much earlier stage and that there is a much better preventative safety mechanism in place than ever before. The lost time injury rate has fallen by 80% over the last four years.[10]

  4.3  Tube Lines is committed to the safety and welfare of our own employees and contractors. We believe that all accidents are preventable and are committed to continuous improvement and learning from past events to identify and mitigate potential risks. We are a member of CIRAS, which operates the industry's nationwide confidential helpline on safety issues, and any employee who has any safety concerns about his or her work is encouraged to ring the helpline.

  4.4 We have introduced a number of initiatives to enhance safety. We operate a "beacon site scheme" where individual work sites can gain accreditation for operating the highest standards of health and safety and act as a beacon of good practice for other sites to follow. The idea is to incentivise individual site teams to aim for excellence and set the standards for others to follow. We have also devised a new track gauge which is able to detect track wear and tear much more effectively and comprehensively than in the past.

  4.5  We are very proud of our safety record to date and are confident that we can and will continue to improve even further.

5.  Risk transfer

  5.1  Tube Lines believes that risk has effectively been transferred to the private sector under the PPP.

  5.2  Our performance regime incentivises good performance and penalises poor performance. On availability, cited by the Committee during its previous inquiry as the most important factor for Tube travellers, the abatements for poor performance are greater than the bonuses received for good performance. In addition, the financial penalties for late completion of station and line upgrades are significant.

  5.3  The contract is structured so that we suffer the financial consequences for all asset problems, not just those caused by our own maintenance, but those resulting from inherited problems and other factors. For example, we incurred a financial impact of £7 million in relation to the Camden Town derailment in late 2003, even though the cause was a historic design failure and Tube Lines was completely exonerated; we invested £20 million on a refurbishment of part of the Piccadilly line fleet, to make good years of make-do-and-mend prior to transfer; and we have spent an extra £20 million on the Northern line to rectify inherited conditions.

  5.4  This is a fixed price contract. We bid for the work on the basis of what we believed the cost of the maintenance and upgrade programme would be. Where we have found projects to be more complex than expected, we have had to take on the additional cost ourselves. For example, at Arsenal station, we had, unexpectedly, to replace the existing roof with a new one. This was done at Tube Lines' own cost; that is to say, the risk lay with the private sector. We have only received supplementary funds from London Underground a) when we have been instructed to carry out additional work, such as the expansion of Wembley Park, referred to above; and b) when LU have widened the scope of projects or changed the standards by which we are expected to perform and deliver our programme of work. There have been occasions on which we and LU have disagreed over the cost of scope extension, but the PPP dispute process has worked effectively on these occasions to resolve these issues.

  5.5  Most of our contract is output-based. This means that we have a set of broad, passenger-facing targets, which are principally around reducing journey times and improving the condition of the infrastructure and it is down to us to design the programme appropriate to delivering this. This means that the risk is transferred to us for the whole lifespan of the assets. The exception to this is the stations programme, where the nature of the upgrade was much more closely defined in the contract by LU and consequently is largely input specified.

  5.6  In recent years, there has been an increasing tendency to offer work to alternative providers through conventional contracts. The disadvantage to the taxpayer of this approach, particularly if it results in the descoping of work from the PPP contract, is that the risk is transferred away from us and back into the public sector.

6.  Value for money

  6.1  Tube Lines believes that the PPP model for upgrading the Underground does constitute value for money.

  6.2  Without the PPP, the current, unprecedented levels of investment would not be sustainable. Investment levels are running at about 3-4 times that seen at the time of transfer. Prior to that, there had been decades of under-investment.

  6.3  The PPP is enabling upgrades which had been put off for years to be completed. The addition of the extra car to the Jubilee line fleet, completed in late 2005, and the current Jubilee line signal upgrade are being carried out now only because they had to be descoped from the original extension project in the late 1990s. The problem was that annualised budgets meant that upgrade programmes were cut back when funding streams ran out and what upgrades were completed were usually over budget and heavily descoped.

  6.4  Underpinning the PPP is an approach known as whole life asset management. This means that we design, build, maintain and manage the entire infrastructure—we are responsible for everything that happens to our assets, throughout the entirety of their lifespan. This, combined with the security of long term funding, means that:

    —  we can take a long term and holistic approach to planning and strike the right balance in terms of funding and personnel towards maintenance and upgrade activities; and

    —  our projects can be delivered much quicker as we can go through the scoping, design and construction phase without having to lose time to secure new money or tender for new suppliers as might have happened in the past.

  The relationship between projects and maintenance, and achieving the right whole life balance between them, is at the heart of this approach.

  6.5  The output-based components of our contract are able to be delivered much more efficiently than the input-based components, where our programme is subject to significant outside intervention. Should there be a move towards a more input-based structure, the capital investment programme would become more complex to deliver, and there would be more unhelpful intervention, leading to additional costs. The fact that the risk would be transferred back to the public sector means that these additional costs would have to be met by the taxpayer.

  6.6  The PPP has led to the recruitment of world class project management and engineering expertise, with strong track records of delivering programmes on schedule and to budget.

  6.7  The innovations detailed above can be linked both to the influx of talent and to the long term and output-based nature of our contract: we had to make changes to create a viable, efficient business, fit to look after the infrastructure for 30 years. A conventional contractor would not have had to do this. These innovations have in turn generated cost savings which could be shared with the public purse through the periodic review process in 2010. Should part of the work undertaken under the PPP be returned in-house, there would be a risk of a return to the resistance to change and entrenched attitudes which militated against innovation before transfer.

  6.8  Tube Lines' business model is based on a competitive supply chain. All sub-contracted work goes out to the best value provider, offering the best quality. This ensures efficient, value for money work.

  6.9  At the heart of Tube Lines' business model has been a drive to reduce dependency on consultants and sub-contractors throughout the business. Prior to transfer, numerous consultants were engaged to undertake specialist roles, at significant cost to the taxpayer. Tube Lines embarked on a process of in-sourcing these roles. A further drive has been to cut out principal contractors on station and track upgrade work and to engage sub-contractors directly. This model is similar to Network Rail's drive to bring work in-house. It also provides significant value for money benefits.

7.  Summary and conclusions

  7.1  Tube Lines has achieved significant progress to date.

  7.2  This has been underpinned by significant business and technical innovations.

  7.4  Tube Lines is proud of its improving safety record.

  7.5  Tube Lines believes that the PPP does offer value for money to the taxpayer and effective risk transfer to the private sector.

  7.6  We would be delighted to give oral evidence to the Committee or organise a visit for Members to see at first hand the work undertaken by Tube Lines.

October 2007







10   The lost time injury rate is one of the standard measures used to measure our safety performance. It is a normalised rate based upon the number of employees absent from work for more than three days. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008